Home / Browse projects / Pune, Maharashtra / DD SQUARE
DD SQUARE
RG-MH-19502 · RERA P52100077795 · Last updated on MahaRERA portal: 30 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DD SQUARE is a Residential / Group Housing project by DATTADIGAMBAR ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100077795 on 30 Oct 2024. Possession is promised by 31 Dec 2028. 12 of the 84 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameDD SQUARE
- TypeResidential / Group Housing
- Location
- NEAR WASHING CENTRE
- BHOSARI
- Haveli
- Pune
- 411039
- Pincode411039
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100077795
- ReraGenie IDRG-MH-19502
Builder
- NameDATTADIGAMBAR ASSOCIATES
- Entity typePartnership
- PartnerAJIT VINAYAK DESAI
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on30 Oct 2024
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed64 files
Current status
Figures as on 30 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DD SQUARE | NA | 13 | 12 | 84 | 0 | 84 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.
DD SQUARE: 56% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 35% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
Progress on shared amenities15
As on 30 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed126
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership10
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SUNIL SHNAKAR GAVHANE | - | Pune |
| ATUL GYANESHWAR GAVHANE | - | Pune |
| Jyoti Gavhane | - | Pune |
| Preetam Gavhane | - | Pune |
| Ranjana Gavhane | - | Pune |
| Abhijit Gavhane | - | Pune |
| Shubhangi Walke | - | Pune |
| Ashwini Pawle | - | Pune |
| Dhanashree Ghule | - | Pune |
| Pranav Gavhane | - | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| DD SQUARE | NA | Rs 16.70 cr | Rs 4.35 cr |
| - | NA | Rs 1.00 cr | Rs 3.25 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VISION ASSOCIATES |
| Engineer | ARROW STRUCTURAL CONSULATANTS |
| Chartered Accountant | BANSAL GARG & ASSOCIATES |
| Partner | Role in project |
|---|---|
| DATTADIGAMBAR ASSOCIATES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Oct 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Oct 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed64
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM 1 31122024.pdf | 30 Mar 2026 |
| Form 2File: FORM 2 10042025.pdf | 30 Mar 2026 |
| Form 3File: Form 03 31122024.pdf | 30 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: 15012025.pdf | 30 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: 06042025.pdf | 30 Mar 2026 |
| Form 3File: Form 03 31032025.pdf | 30 Mar 2026 |
| Form 2File: FORM 2 10042025.pdf | 30 Mar 2026 |
| Form 1File: FORM 1 31032025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: FORM 1 30062025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: FORM 1 30062025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: FORM 1 30062025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: FORM 1 30092025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: FORM 1 30062025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: FORM 1 31122025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: FINALFORM2.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: FINALFORM2.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: FINALFORM2.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: FORM 2 08102025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: FORM 2 15072025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: FORM 2 05012026.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form 03 30062025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form 03 30062025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form 03 30062025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form 03 30092025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form 03 30062025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form 03 31122025.pdf | 30 Mar 2026 |
| Proforma of Agreement for saleFile: BLANK.pdf | 28 Jan 2025 |
| Proforma of Agreement for saleFile: BLANK.pdf | 28 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC verification DD square.pdf | 18 Oct 2024 |
| Building plan approvalFile: Building Plan.pdf | 9 Oct 2024 |
| Building plan approvalFile: Layout Plan.pdf | 9 Oct 2024 |
| Copy of the legal title reportFile: Final Title-DD Square.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Legal.pdf | 9 Oct 2024 |
| Proforma of Allotment letterFile: Allotment Letter - DD Square.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf | 9 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Layout Plan.pdf | 9 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf | 9 Oct 2024 |
| Other - LegalFile: CC verification.pdf | 9 Oct 2024 |
| Declaration about Commencement CertificateFile: Format D.pdf | 9 Oct 2024 |
| CERSAI detailsFile: Declaration CC.pdf | 9 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A DD square (1).pdf | 9 Oct 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf | 9 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance Legal.pdf | 9 Oct 2024 |
| Other - FinanceFile: Landowners declaration-DD Square.pdf | 9 Oct 2024 |
| Other - TechnicalFile: Annexture A Order no 50.pdf | 9 Oct 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation AFS.pdf | 9 Oct 2024 |
| Proforma of Agreement for saleFile: Final AFS-DD Square.pdf | 9 Oct 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf | 9 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: secured finance availed for project.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FINALFORM2.pdf | 12 Aug 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DECLARATION NAVNATH.pdf | 9 Aug 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DECLRATION VIJAY SUBHASH PARANDE.pdf | 9 Aug 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DECLARATION SHEETAL.pdf | 9 Aug 2024 |
| Details of encumbrances concerned to FinanceFile: Dattadigambar Associates Declaration to finance.pdf | 20 Jul 2024 |
| Declaration in FORM BFile: FORMBPARTNERS.pdf | 20 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Dattadigambar Associates Declaration to finance.pdf | 20 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DECLARATION NITIN.pdf | 20 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DECLRATION SUPRIYA ATUL PARANDE.pdf | 20 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DECLARATION AJIT.pdf | 20 Jul 2024 |
| Layout approvalFile: ilovepdf_merged (15).pdf | 17 Jul 2024 |
| PAN CardFile: pan.pdf | 17 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: ilovepdf_merged (15).pdf | 17 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE _ FORM 1.pdf | 17 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 17 Jul 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 64 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DD SQUARE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BHOSARI13,700+ in Pune
Filed coordinates, straight-line distance. 39 registered projects within 2 km.
ABHISHEK MEADOWS
Abhishek Construction
VISION EXOTICA
VISION AVIS GROUPS
VISION EXOTICA PHASE-II
VISION AVIS GROUPS
Diamond hills
A Square Properties
MRUDULA RESIDENCY
SAMARTH ASSOCIATES
SHEETAL BAG PHASE 3A
Jagdish Agashe Financing Co Pvt Ltd
Builder: DATTADIGAMBAR ASSOCIATES
DATTADIGAMBAR ASSOCIATES has 1 registration on MahaRERA, including DD SQUARE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if DD SQUARE is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DD SQUARE?
The registered promoter entity is DATTADIGAMBAR ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DD SQUARE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DD SQUARE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DD SQUARE?
The professionals named in the filing: Architect: VISION ASSOCIATES; Engineer: ARROW STRUCTURAL CONSULATANTS; Chartered Accountant: BANSAL GARG & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DD SQUARE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback