ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Mangal Business Park - Gautam Apartment

Registered No litigation declared Commercial project

Mangal Business Park - Gautam Apartment

By MANGAL BUILDHOME PRIVATE LIMITED

RG-MH-07323 · RERA P51800054656 · Last updated on MahaRERA portal: 3 Jul 2026

Source: official MahaRERA filing

Red flags

  • Rs 50.00 crore secured on the land, in favour of BHARAT CO OP BANK MUMBAI LTD

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Staircases, 90%
150 of 278Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

Mangal Business Park - Gautam Apartment is a Commercial project by MANGAL BUILDHOME PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800054656 on 2 Feb 2024. Possession is promised by 31 Mar 2027. 128 of the 278 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameMangal Business Park - Gautam Apartment
  • TypeCommercial
  • Location
    • S V Road
    • Mumbai
    • Malad
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800054656
  • ReraGenie IDRG-MH-07323

Builder

  • NameMANGAL BUILDHOME PRIVATE LIMITED
  • Entity typeCompany
  • CINU45201MH2010PTC259841
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsAKSHAY AJAY KULKARNI, VAIBHAV RAJESH DESAI
  • Other registrations6 more →
  • Completed2 of 7
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredFeb 2024PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Feb 2024
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed92 files

Current status

46%128 of 278 units booked
57.4%Work done, per cost certificate

Figures as on 3 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Mangal Business Park - Gautam ApartmentNA21210278278

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

Mangal Business Park - Gautam Apartment: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 3 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed240

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots240
Closed/Covered240

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,093 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBHARAT CO OP BANK MUMBAI LTD
Secured amountRs 50.00 crore
CERSAI search filedYes
Declared on19 Jul 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI14121.35
Proposed, not sanctioned14,121 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1st Floor Sun City Theatre M G Road Vile Parle East Mumbai 400064
Estimated costRs 85.50 cr
Cost incurredRs 49.05 cr
Work done57.37%
BuildingWingEstimatedIncurred
Mangal Business Park - Gautam ApartmentNARs 85.50 crRs 49.05 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMONIK AJAY SHAH
EngineerVINAYAK CONSULTANT
EngineerUnisteps Consulting Pvt. Ltd
Chartered AccountantPRAVEEN MANIYAR & ASSOCIATES
Chartered AccountantRanka dargar & co.
Chartered AccountantS M BHAT AND ASSOCIATES
PartnerRole in project
MANGAL BUILDHOME PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: ENGINEERS CERTIFICATE FOR QUALITY ASSURANCE Mangal Business Park.pdf3 Jul 2026
Form 5 (FY 2024-2025)File: SIGNED - Form 5 - MANGAL BUSINESS PARK 24-252.pdf1 Jul 2026
Withdrawal Update Form 1File: Form1 mbp rera certificate.pdf18 Apr 2026
Withdrawal Update Form 2File: Form2 MBP rera certificate.pdf18 Apr 2026
Withdrawal Update Form 3File: form3 MBP rera certificate_compressed.pdf18 Apr 2026
Withdrawal Update Form 1File: form 1Rera certificate GAUTAM.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 mbp final.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 mbp date 191compressed.pdf20 Jan 2026
Withdrawal Update Form 1File: Form1 mbp 30925.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2 15102025.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3 MBP 30925.pdf17 Oct 2025
Withdrawal Update Form 1File: Form 1 Withdrawal Update.pdf29 Jul 2025
Withdrawal Update Form 2File: Form 2mbp30625.pdf29 Jul 2025
Withdrawal Update Form 3File: FORM 3 CA Certificate.pdf29 Jul 2025
Form 1File: Form130062025 Architects Certificate.pdf20 Jul 2025
Form 2File: form2Engineer CertificateJune2025.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold 30625.pdf20 Jul 2025
Form 3File: MBP - FORM 3 CA CERTIFICATE_signed.pdf20 Jul 2025
Form 1File: Architects Certificate FORM 1.pdf17 Jul 2025
Form 2File: Engineer CertificateFORM2.pdf17 Jul 2025
Form 3File: CA Certificateform 3.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory.pdf17 Jul 2025
Form 1File: 31032025 Architects Certificate.pdf17 Jul 2025
Form 2File: form2Engineer CertificateMar2025.pdf17 Jul 2025
Form 3File: form3 CA certificatemarch 2025_compressed.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked inventory 310325.pdf17 Jul 2025
Form 1File: 30062024 Architects Certificate.pdf17 Jul 2025
Form 2File: form2Engineer CertificateJun2024.pdf17 Jul 2025
Form 3File: form3 ca certificate jun24compressed.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 30062024.pdf17 Jul 2025
Form 1File: 30092024 Architects Certificate.pdf17 Jul 2025
Form 2File: form2Engineer CertificateSep2024.pdf17 Jul 2025
Form 3File: form3CA certificate sep24_compressed.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 30092024.pdf17 Jul 2025
Form 1File: aRCHITECT MARCH24.pdf17 Jul 2025
Form 2File: form2Engineer CertificateMar2024.pdf17 Jul 2025
Form 3File: Ca Certificate 310324.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 31032024.pdf17 Jul 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: SIGNED - Form 5 - MANGAL BUSINESS PARK 24-252.pdf13 May 2025
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30062024 Architects Certificate.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30092024 Architects Certificate.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032025 Architects Certificate.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3 ca certificate jun24compressed.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3CA certificate sep24_compressed.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3 CA certificatemarch 2025_compressed.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2Engineer CertificateJun2024.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2Engineer CertificateSep2024.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2Engineer CertificateMar2025.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked inventory 310325.pdf19 Apr 2025
Details of encumbrances concerned to LegalFile: Encumbrance Certificate.pdf19 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SIGNED - Form 5 - MANGAL BUSINESS PARK 23-241.pdf19 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Encumbrance Certificate.pdf19 Apr 2025
Declaration about Commencement CertificateFile: Declaration about CC.pdf3 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: 2465661_FurtherCC_signed.pdf1 Mar 2025
Building plan approvalFile: 2456165Amendlettersigned.pdf20 Feb 2025
Building plan approvalFile: Amended plan.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificateform 3.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate31Dec2024.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 2456165Amendlettersigned.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Amended plan.pdf20 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory.pdf20 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer form 2A 23-24-11.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3112024 Architects Certificate FORM 1.pdf31 Jan 2025
Declaration in FORM BFile: FORM B.pdf24 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Certificate.pdf24 Jan 2024
Layout approvalFile: Sanctoned Plans.pdf18 Jan 2024
Copy of Layout Approval (in case of layout)File: Sanctoned Plans.pdf18 Jan 2024
Details of encumbrances concerned to FinanceFile: No Encumbrance Certificate Concerned to Finance and Legal.pdf11 Jan 2024
Details of encumbrances concerned to LegalFile: No Encumbrance Certificate Concerned to Finance and Legal.pdf11 Jan 2024
CERSAI detailsFile: Undertaking Confirming No Security interest been Created.pdf11 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about seperate bank account.pdf11 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real Estate Organization.pdf8 Jan 2024
Proforma of Allotment letterFile: Allotment Letter.pdf8 Jan 2024
Proforma of Agreement for saleFile: Agreement for Sale as Per MahaRERA.pdf8 Jan 2024
Building plan approvalFile: IOD Certificate.pdf2 Jan 2024
Building plan approvalFile: IOD Plans Duly signed and issued.pdf2 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD Certificate.pdf2 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD Plans Duly signed and issued.pdf2 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf28 Dec 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise2 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
RoyaleP51800045406Vile Parle East, Mumbai Suburban-May 2022CompletedMay 2025Oct 2024
Mangal SmritiP51800028224NEAR DIAMOND GARDEN, Mumbai Suburban-Feb 2021Certificate SignedJun 2022Late, Apr 2023
SHREE MANGALP51800004380Andheri, Mumbai Suburban-Aug 2017CompletedDec 2017Late, Mar 2018
MANGAL VILLAS77 78 79 80 84 TUNGARLI LONAVALA DISTRICT PUNE6-CompletedDec 2015Sep 2015

How this compares with Mumbai Suburban

46%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mangal Business Park - Gautam Apartment on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mumbai6,700+ in Mumbai Suburban

2 kmMangal Business Park - GCompleted 146Lapsed / revoked 90Other 159Dot size: filed unitsN

Filed coordinates, straight-line distance. 395 registered projects within 2 km.

Builder: MANGAL BUILDHOME PRIVATE LIMITED

MANGAL BUILDHOME PRIVATE LIMITED has 7 registrations on MahaRERA, including SHREE MANGAL and AMRAPALI. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 4 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Mangal Business Park - Gautam Apartment is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mangal Business Park - Gautam Apartment?

The registered promoter entity is MANGAL BUILDHOME PRIVATE LIMITED, a company as per the filing. Its CIN U45201MH2010PTC259841 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mangal Business Park - Gautam Apartment?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mangal Business Park - Gautam Apartment?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mangal Business Park - Gautam Apartment?

The professionals named in the filing: Architect: MONIK AJAY SHAH; Engineer: VINAYAK CONSULTANT; Engineer: Unisteps Consulting Pvt. Ltd; Chartered Accountant: PRAVEEN MANIYAR & ASSOCIATES; Chartered Accountant: Ranka dargar & co.; Chartered Accountant: S M BHAT AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mangal Business Park - Gautam Apartment?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mangal Business Park - Gautam Apartment. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mangal Business Park - Gautam Apartment to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.