ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Malhar Malti

Registered No litigation declared Others project

Malhar Malti

By Atlanta Developers

RG-MH-18003 · RERA P51800076824 · Last updated on MahaRERA portal: 2 Jun 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
31 of 36Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 36 documents Report an error

Malhar Malti is a Others project by Atlanta Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800076824 on 28 Jun 2024. Possession is promised by 31 Mar 2027. 5 of the 36 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameMalhar Malti
  • TypeOthers
  • Location
    • R H B Road
    • Mulund West
    • Mulund
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800076824
  • ReraGenie IDRG-MH-18003

Builder

  • NameAtlanta Developers
  • Entity typePartnership
  • PartnersPratik Pramod Salvi, Pooja Pramod Salvi, Pramod Ramkrishna Salvi

Key dates

this monthRegisteredJun 2024PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Jun 2024
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed36 files

Current status

14%5 of 36 units booked
7.0%Work done, per cost certificate

Figures as on 2 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Malhar MaltiNA171632436

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Malhar Malti: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed29

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots29
Closed/Covered29

Land and ownership16

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area493 sq m
Land owned byThe promoter, with other names on the file
Named landowners16
LandownerVillageDistrict
Subodh Arun PuroMulundMumbai Suburban
Prachi Arun PuroThane (M Corp.)Thane
Ulka Mukund PuroMulundMumbai Suburban
Rahul Mukund PuroMulundMumbai Suburban
Sunita Vaibhav DahakeMulundMumbai Suburban
Sugandha Padmakar PuroMulundMumbai Suburban
Suhas Padmakar PuroMulundMumbai Suburban
Anjali Baburao ChoudharyMulundMumbai Suburban
Vasanti Murlidhar PuroMulundMumbai Suburban
Avinash Murlidhar PuroMulundMumbai Suburban
Sanjay Suresh PuroPune (M Corp.)Pune
Pratibha Suresh PuroMulundMumbai Suburban
Pushpa Jayram ReddyMulundMumbai Suburban
Sangita Nitin PattekarThane (M Corp.)Thane
Shilpa Sateesh PuroMulundMumbai Suburban
Jayant Murlidhar PuroMulundMumbai Suburban

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI1995.45
Proposed, not sanctioned1,121 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 3 and 4 , Jaideep Emphasis Opp Oriental Bank of Commerce Wagale Estate Thane West 400604
Estimated costRs 7.78 cr
Cost incurredRs 54.81 lakh
Work done7.04%
BuildingWingEstimatedIncurred
Malhar MaltiNARs 7.39 crRs 52.07 lakh
-NARs 38.92 lakhRs 2.74 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDesign Crest Axiom
EngineerR C Tipnis
EngineerSK Consultants & Engineers
Chartered AccountantPrachi Sawant and CO
Chartered AccountantN B Sayed & Associates
PartnerRole in project
Atlanta Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed36

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: ARCHITECT'S CERTIFICATE Malhar Malti 31-03-2025.pdf2 Jun 2025
Form 2File: Form 2 31-03-2025.pdf2 Jun 2025
Form 3File: Form 3 31-03-25.pdf2 Jun 2025
Form 1File: ARCHITECT'S CERTIFICATE Malhar Malti 30-06-2024.pdf30 May 2025
Form 1File: ARCHITECT'S CERTIFICATE Malhar Malti 30-09-2024.pdf30 May 2025
Form 2File: fORM 2 30-9-24.pdf30 May 2025
Form 3File: Form 3 30-9-24.pdf30 May 2025
Form 3File: Form 3 31-12-24.pdf30 May 2025
Form 2File: Form 2 31-12-24.pdf30 May 2025
Form 1File: ARCHITECT'S CERTIFICATE Malhar Malti 31-12-2024.pdf30 May 2025
Other - FinanceFile: ilovepdf_merged (18).pdf10 Apr 2024
Other - LegalFile: Partnership Deed_compressed (2).pdf22 Mar 2024
Layout approvalFile: Building Approval -Layout Plan-1.pdf21 Mar 2024
Building plan approvalFile: Building Approval 2 -3.pdf21 Mar 2024
Building plan approvalFile: Building Approval 4 -5.pdf21 Mar 2024
PAN CardFile: Atlanta Developers PAN card.pdf21 Mar 2024
Copy of the legal title reportFile: revised title malhar guide.pdf21 Mar 2024
Details of encumbrances concerned to FinanceFile: No Encumbrance Letter Finance.pdf21 Mar 2024
Details of encumbrances concerned to FinanceFile: No Encumbrance Letter Legal.pdf21 Mar 2024
Details of encumbrances concerned to LegalFile: No Encumbrance Letter Finance.pdf21 Mar 2024
Details of encumbrances concerned to LegalFile: No Encumbrance Letter Legal.pdf21 Mar 2024
Copy of Layout Approval (in case of layout)File: Building Approval -Layout Plan-1.pdf21 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Approval 2 -3.pdf21 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Approval 4 -5.pdf21 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Malti Bhavan Plinth CC.pdf21 Mar 2024
Declaration about Commencement CertificateFile: Format D Malhar Malti.pdf21 Mar 2024
Declaration in FORM BFile: Form B of Developers.pdf21 Mar 2024
CERSAI detailsFile: cersai declaration.pdf21 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20240624154859---.pdf21 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ilovepdf_merged (12).pdf21 Mar 2024
Proforma of Agreement for saleFile: Agreement for sale.pdf21 Mar 2024
Proforma of Allotment letterFile: Allottment letter.pdf21 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format 'A'.pdf21 Mar 2024
Deviation Report with respect to Allotment letterFile: edited Draft Deviations in the Allotment Letter (1).pdf21 Mar 2024
Deviation Report with respect to model copy of AgreementFile: edited Draft Deviations afs.pdf21 Mar 2024
Other - TechnicalFile: 1 Other - Technical (18) (1).pdf21 Mar 2024

How this compares with Mumbai Suburban

14%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Malhar Malti on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund West6,700+ in Mumbai Suburban

2 kmMalhar MaltiCompleted 118Lapsed / revoked 98Other 148Dot size: filed unitsN

Filed coordinates, straight-line distance. 364 registered projects within 2 km.

Builder: Atlanta Developers

Atlanta Developers has 1 registration on MahaRERA, including Malhar Malti. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Malhar Malti is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Malhar Malti?

The registered promoter entity is Atlanta Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Malhar Malti?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Malhar Malti?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Malhar Malti?

The professionals named in the filing: Architect: Design Crest Axiom; Engineer: R C Tipnis; Engineer: SK Consultants & Engineers; Chartered Accountant: Prachi Sawant and CO; Chartered Accountant: N B Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Malhar Malti?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Malhar Malti. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Malhar Malti to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.