Home / Browse projects / Thane, Maharashtra / Mahindra Happinest Kalyan Project A

Completed No litigation declared Residential / Group Housing project

Mahindra Happinest Kalyan Project A

By MAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD)

RG-MH-14413 · RERA P51700022981 · Last updated on MahaRERA portal: 8 Oct 2024

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
27 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
4Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

Mahindra Happinest Kalyan Project A is a Residential / Group Housing project by MAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD) in Thane, Maharashtra, registered with MahaRERA as P51700022981 on 8 Nov 2019. The registration is recorded completed; possession was promised by 30 Dec 2024. 4 complaints are on record with the regulator.

At a glance

Project

  • NameMahindra Happinest Kalyan Project A
  • TypeResidential / Group Housing
  • Location
    • Kalyan Bhiwandi Road
    • Bhiwandi Kalyan Junction
    • Ranjnoli
    • Bhiwandi
    • Thane
    • 421311
  • Pincode421311
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700022981
  • ReraGenie IDRG-MH-14413

Builder

  • NameMAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD)
  • Entity typeCompany
  • DirectorsArvind Subramanian, Ameet Hariani, Dr Anish Shah, Ms Amrita Chowdhury, Mr Anuj Puri, Ms Asha Kharga, Ms Asha Kharga, Ms Rucha Nanavati, Ms Asha Kharga, Ms Amrita Chowdhury, Ms Rucha Nanavati, Arvind Subramanian and 4 more
  • Other registrations8 more →
  • Completed6 of 9
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2019PromisedDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Nov 2019
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings3 building records
  • Documents filed93 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1NA150000
Tower 2NA150000
Tower 6NA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 8 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

Tower 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,645 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI22246.68
Proposed, not sanctioned22,247 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMumbai

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSandeep Shikre & Associates
EngineerDiga Consultant and Valuers LLP
EngineerK C Shah Consultants
Chartered AccountantA B D AND CO LLP
Chartered AccountantP G BHAGWAT LLP
PartnerRole in project
MAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD)-

Litigation declared4

CaseCourtStatus
247/2020Civil Court Junior Division BhiwandiPending
29/2021Court of District Judge at ThanePending
2/2021Civil Judge Senior Division Thane Link Court BhiwandiPending
443/2021Tahsildar and Magistrate Office BhiwandiPending

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000195016M/s Swastik Real Estate DevelopersMahindra HappinestDevelopers Limited25/11/2020
CC006000000196458MUSADDIQUE ISMAIL POKARMahindra Happinest Developers Limited23/03/2021
CC006000000197461Mr. Pratik Ramanand ShettyMahindra Happinest Developers Limited02/07/2021
CC006000000199030Ashutosh Subhash GuptaMAHINDRA HAPPINEST KALYAN13/11/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jan 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jan 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Nov 2023

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Kalyan 1 Project A.pdf8 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Kalyan 1 Project A.pdf8 Oct 2024
OtherFile: MHDL - Letter to MahaRERA relates to Authorised Signatories.pdf31 Jul 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 HK-1 A - FY24-Q1 170823.pdf1 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: HK1 - Phase A OC.pdf28 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: HK A_Aug 23_RERA_Ar Certificate-T01,02,06.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: HK A_Aug 23_RERA_Ar Certificate-T01,02,06.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: HK A_Aug 23_RERA_Ar Certificate-T01,02,06_signed.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 HK-1 A - FY24-Q2_signed.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 HK-1 A - FY24-Q2_signed.pdf17 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate Kalyan A Sept 23_signed.pdf17 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate Kalyan A Sept 23_signed.pdf17 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 HK A MHDL Final.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: HK A_June23_RERA_Ar Certificate-T01,02,06_signed.pdf18 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 HK-1 - FY24-Q1_signed.pdf18 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan_A_Certificate_Jun_23_signed-compressed.pdf18 Jul 2023
Other - FinanceFile: PGB_MLDL RERA letter.pdf18 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15_HK A_Mar 23_RERA_Ar Certificate-T01,02,06_signed.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 HK-1 - FY23-Q4_signed.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 HK-1 - FY23-Q4_signed.pdf17 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer's Certificate for Quality and Assurance signed - HK-1 Q4 -FY23.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: kalyan A Cert Mar23_signed_11zon.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 HK PrA PrB - Dec'22_signed.pdf18 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KALYAN A_dec22_signed.pdf18 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: HK A_December 22_RERA_Ar Certificate-T01,02,06_signed.pdf17 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13_HK A_Sept 22_RERA_Ar Certificate-T01,02,06-signed_compressed.pdf18 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 001 Kalyan Revise _Form 2 Engg Certificate HK RERA Project A Project B_Sep'22-signed.pdf18 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificate HK PA _Sep22-signed_compressed.pdf18 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Kalyan Project A.pdf30 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12_HK A_June 22_RERA_Ar Certificate-T01,02,06 (1)-signed.pdf20 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 HK RERA Project A Project B - Jun'2022 R2-signed.pdf20 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan A Cer Jun2022-signed_compressed.pdf20 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 HK - Jun'22.pdf19 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 2 HK RERA Project A Project B - Mar'2022-signed.pdf18 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2 HK_compressed.pdf18 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 HK RERA Project A Project B - Mar'2022-signed.pdf18 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12_HK A_June 22_RERA_Ar Certificate-T01,02,06 (1)-signed.pdf7 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan Project A Form 3-Mar'22 - Name changed-Promotor signed 1mb.pdf12 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11_HK A_Mar 22_RERA_Ar Certificate-T01,02,06-Promotors signed-1mb.pdf9 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Quality CERTIFICATE FOR QUATITY ASSURANCE_MAR-22-signed.pdf9 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 09_HK A_Dec_RERA_Ar Certificate-T01,02,06-PROMOTORS SIGN.pdf23 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate Kalyan Project A Form 3-Dec'21 v1-signed_Promotor Sign (1).pdf23 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: HK - A.pdf12 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality CERTIFICATE FOR QUATITY ASSURANCE_DEC-21.pdf12 Jan 2022
Declaration about Commencement CertificateFile: CC Declar HK.pdf21 Dec 2021
Disclosure of sold/ booked inventoryFile: HK - Project A -1_merged.pdf21 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: HK - A - Form 5.pdf21 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: HK - A - Form 5.pdf21 Dec 2021
CERSAI detailsFile: CERSAI Details.pdf18 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10_HK A_Sept 21_RERA_Ar Certificate-T01,02,06_compressed.pdf29 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: HK - Sep'21.pdf29 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan Project-A Sept-21_compressed.pdf29 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalyan Happinest Project-A_compressed.pdf30 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 01 Kalyan A Report_compressed.pdf30 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate HK RERA Project A - Mar-21.pdf1 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER'S CERTIFICATE FOR QUATITY ASSURANCE_Mar-21.pdf1 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan Happinest Project-A.pdf1 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Engineers certificate HK RERA Project A - Mar-21.pdf1 Jun 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate HK RERA Project A - Dec-20.pdf30 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan A Dec'20 Certificate-min.pdf30 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan A Dec'20 Certificate-min.pdf30 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan A Dec'20 Certificate-min.pdf30 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan A Dec'20 Certificate-min.pdf30 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan A Dec'20 Certificate-min.pdf30 Jan 2021
Proforma of Allotment letterFile: Revised AFS Happinest Kalyan Project A.pdf25 Jan 2021
Layout approvalFile: Master Layout.pdf10 Jan 2021
Building plan approvalFile: Master Layout.pdf10 Jan 2021
Copy of Layout Approval (in case of layout)File: Master Layout.pdf10 Jan 2021
Building Plan Approval / NA Order for plotted developmentFile: Master Layout.pdf10 Jan 2021
Commencement Certificates / NA Order for plotted developmentFile: Final CC in MHDL's Name.pdf10 Jan 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Kalyan Project A compressed.pdf8 Dec 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05_HK A_RERA_Ar Certificate-T01,02,06_compressed.pdf4 Dec 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate HK RERA Project A - Sep-20.pdf1 Dec 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineers certificate HK RERA Project A - Sep-20.pdf10 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan Happinest Sept20_ A.pdf10 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kalyan_Happinest_Project A(1).pdf5 Aug 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Project A.pdf21 May 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: certificate_Project A.pdf3 Feb 2020
OtherFile: MHDL DECLARATION.pdf6 Nov 2019
Copy of the legal title reportFile: Legal Title Report.pdf4 Nov 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Happinest Palghar Project - 1Mahindra Happinest Developers Ltd Village Nandore Gut No 158 183 P 183P plot 1 Pin 401404293CompletedDec 2020Dec 2020

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mahindra Happinest Kalyan Project A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhiwandi Kalyan Junction7,600+ in Thane

2 kmMahindra Happinest KalyaCompleted 10Lapsed / revoked 11Other 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 36 registered projects within 2 km.

Builder: MAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD)

MAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD) has 9 registrations on MahaRERA, including Mahindra Happinest Palghar Phase - I and Mahindra Happinest Palghar Phase - II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Mahindra Happinest Kalyan Project A is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mahindra Happinest Kalyan Project A?

The registered promoter entity is MAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD), a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mahindra Happinest Kalyan Project A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mahindra Happinest Kalyan Project A?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Mahindra Happinest Kalyan Project A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mahindra Happinest Kalyan Project A?

The professionals named in the filing: Architect: Sandeep Shikre & Associates; Engineer: Diga Consultant and Valuers LLP; Engineer: K C Shah Consultants; Chartered Accountant: A B D AND CO LLP; Chartered Accountant: P G BHAGWAT LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mahindra Happinest Kalyan Project A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mahindra Happinest Kalyan Project A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mahindra Happinest Kalyan Project A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.