Home / Browse projects / Thane, Maharashtra / MAHALAXMI ASHISH D WING

Registered No litigation declared Residential / Group Housing project

MAHALAXMI ASHISH D WING

By SWASTIK ENTERPRISES

RG-MH-02771 · RERA P51700020000 · Last updated on MahaRERA portal: 22 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 33 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
63 of 156Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 202 documents Report an error

MAHALAXMI ASHISH D WING is a Residential / Group Housing project by SWASTIK ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700020000 on 18 Mar 2019. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 33 months from the original filing. 93 of the 156 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameMAHALAXMI ASHISH D WING
  • TypeResidential / Group Housing
  • Location
    • 90 FEET ROAD
    • THAKURLI EAST
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700020000
  • ReraGenie IDRG-MH-02771

Builder

  • NameSWASTIK ENTERPRISES
  • Entity typePartnership
  • PartnersAKASH VINAYAK PATIL, SAHIL VINAYAK PATIL, VINAYAK DEVRAM PATIL, ADITYA PRABHAKAR PATIL, HARSHADBHAI ARJANBHAI WAGHELA, CHANDUBHAI ARJANBHAI WAGHELA, DOLLAR SHIVJI THAKKAR, RITESH HARILAL SANGHANI
  • Other registrations8 more →
  • Completed2 of 9
  • No longer live5 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

1 months past promisethis monthRegisteredMar 2019First promiseDec 2023Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Mar 2019
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed202 files

Current status

60%93 of 156 units booked
91.5%Work done, per cost certificate

Figures as on 22 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MAHALAXMI ASHISH D WINGNA19191560156

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

MAHALAXMI ASHISH D WING: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes70%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered18
Open Space21

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,460 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2025
LandownerVillageDistrict
VINAYAK DEORAM PATILDOMBIVLIThane

Approvals and building plan

Sanctioning authorityKalyan Dombivali Municipal Corporation, Kalyan
Permissible FSI7238.45
Proposed, not sanctioned5,888 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCOMMERCE CENTRE, TANDON ROAD, RAMANGAR, DOMBIVLI EAST
Estimated costRs 36.92 cr
Cost incurredRs 33.79 cr
Work done91.53%
BuildingWingEstimatedIncurred
MAHALAXMI ASHISH D WINGNARs 36.92 crRs 33.79 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTUSHILP
EngineerRAJESH THAKARE & ASSOCIATES
Chartered AccountantDINESH J POKAR & CO
Chartered AccountantR H Pothiwal & Associates
Chartered AccountantAmogh Ghule & Associates
PartnerRole in project
SWASTIK ENTERPRISES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018467Dec 2023 → Dec 2024

Reason as filed by the promoterWe are applying for extension since construction work is in process and completion certificate from local authority is yet to obtain due to following reasons: a) Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis. b) Appx 80% project is completed. We request you to kindly extend the project completion date to 29/12/2024.

EA02102518004Dec 2023 → Sep 2026

Reason as filed by the promoterThe project is delayed due to Covid- 19 issue that halted construction activities. Further, temporary liquidity issues or delays in funding. Labour or material shortages Disruptions in supply chains or workforce availability are impacting construction timelines.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed202

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 202 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate SWASTIK ENTERPRISES jun 26.pdf22 Jul 2026
Withdrawal Update Form 1File: Architect Certificate SWASTIK ENTERPRISES jun 26.pdf22 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate - Swastik Enterprises -June 26.pdf22 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate - Swastik Enterprises -June 26.pdf22 Jul 2026
Withdrawal Update Form 3File: CA Certificate_Jun 2026_Swastik Enterprises.pdf22 Jul 2026
Withdrawal Update Form 3File: CA Certificate_Jun 2026_Swastik Enterprises.pdf22 Jul 2026
Withdrawal Update Form 1File: Architect Certificate SWASTIK ENTERPRISES MARCH 26.pdf29 Apr 2026
Withdrawal Update Form 2File: Engineer Certificate - Swastik Enterprises -Mar 26.pdf29 Apr 2026
Withdrawal Update Form 3File: CA Certificate Mahalaxmi Ashish Mar 26.pdf29 Apr 2026
Withdrawal Update Form 1File: Architect Certificate Swastik Dec 25.pdf20 Feb 2026
Withdrawal Update Form 2File: Engineer Certificate Swastik Dec 25.pdf20 Feb 2026
Withdrawal Update Form 3File: CA Certificate Swastik Dec 25.pdf20 Feb 2026
Withdrawal Update Form 1File: Architect Certificate Sep 25.pdf24 Dec 2025
Withdrawal Update Form 2File: Form 2 Sep 25.pdf24 Dec 2025
Withdrawal Update Form 3File: Form 3_Sep 25.pdf24 Dec 2025
Withdrawal Update Form 1File: Architect Certificate June 25.pdf22 Dec 2025
Withdrawal Update Form 2File: Engineer Certificate June 25.pdf22 Dec 2025
Withdrawal Update Form 3File: CA Certificate June 25.pdf22 Dec 2025
Form 2A (FY 2024-2025)File: Form 2A.pdf31 Oct 2025
Form 5 (FY 2024-2025)File: RERA Audit Report_24-25.pdf31 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025
Form 2File: Engineer Certificate.pdf8 Oct 2025
Form 3File: CA Certificate.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration.pdf8 Oct 2025
Form 1File: Architect Certificate.pdf8 Oct 2025

How this compares with Thane

60%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 33 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAHALAXMI ASHISH D WING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near THAKURLI EAST7,600+ in Thane

2 kmMAHALAXMI ASHISH D WINGCompleted 41Lapsed / revoked 38Other 70Dot size: filed unitsN

Filed coordinates, straight-line distance. 149 registered projects within 2 km.

Builder: SWASTIK ENTERPRISES

SWASTIK ENTERPRISES has 9 registrations on MahaRERA, including SHREE SHAMBHAV DARSHAN and SWASTIK PLAZA. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if MAHALAXMI ASHISH D WING is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAHALAXMI ASHISH D WING?

The registered promoter entity is SWASTIK ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAHALAXMI ASHISH D WING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MAHALAXMI ASHISH D WING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAHALAXMI ASHISH D WING?

The professionals named in the filing: Architect: VASTUSHILP; Engineer: RAJESH THAKARE & ASSOCIATES; Chartered Accountant: DINESH J POKAR & CO; Chartered Accountant: R H Pothiwal & Associates; Chartered Accountant: Amogh Ghule & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHALAXMI ASHISH D WING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHALAXMI ASHISH D WING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHALAXMI ASHISH D WING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.