Mahadev Park

By Omkar Developers & Associates

RG-MH-24629 · RERA P52100011290 · Last updated on MahaRERA portal: 2 Oct 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 66 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 66 months from the original
9 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 70%
41 of 172Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Mahadev Park is a Residential / Group Housing project by Omkar Developers & Associates in Pune, Maharashtra, registered with MahaRERA as P52100011290 on 31 Aug 2017. Possession is promised by 31 Mar 2027. The completion date has moved by 66 months from the original filing. 131 of the 172 units on this registration are recorded sold or booked, and 9 of 33 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMahadev Park
  • TypeResidential / Group Housing
  • Location
    • AUNDH-RAVET BRTS ROAD
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411062
  • Pincode411062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100011290
  • ReraGenie IDRG-MH-24629

Builder

  • NameOmkar Developers & Associates
  • Entity typeOthers
  • GSTIN27AAAAO3954G1ZJ
  • Named personsPRAMOD SHITOLE, Manoj Dadade, Dynaneshwar Kute

Key dates

this monthRegisteredAug 2017First promiseSep 2021Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Sep 2021)
  • Buildings3 building records
  • Documents filed56 files

Current status

76%131 of 172 units booked
100.0%Work done, per cost certificate

Figures as on 2 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA121186086
Wing BNA121212012
WING CNA6074074

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 2 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 70%.

Wing A52%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed193

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots193
Closed/Covered53
Open Space140
BuildingClosed/CoveredOpen SpaceTotal
Wing A266086
Wing B266086
WING C12021

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,863 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Chandrakant Mahadev MorePimpri Chinchawad (M Corp.)Pune
Vilas Mahadev MoreChikhali Bk.Pune

Approvals and building plan

Sanctioning authorityPIMPRI CHINHWAD MUNICIPAL CORPORATION
Permissible FSI7862.58
Proposed, not sanctioned6,018 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch8 BC Ground Floor Hiramoti Fortune Chinchwad Pune 411019
Estimated costRs 21.74 cr
Cost incurredRs 21.74 cr
Work done100.0%
BuildingWingEstimatedIncurred
Wing BNARs 10.78 crRs 10.78 cr
Wing ANARs 9.28 crRs 9.28 cr
-NARs 1.68 crRs 1.68 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSantosh Kisanrao Kate
EngineerRamchandra Krihnarao Randhave
Chartered AccountantR DEVENDRA KUMAR AND ASSOCIATES
PartnerRole in project
Omkar Developers & Associates-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009870Sep 2021 → Sep 2022

Reason as filed by the promoterApplication for Extension of Project completion date under section 7(1) of the Real Estate (Regulation and Development) Act, 2016 We have attached Developer self-explanatory letter along with Independent Site engineering Report also Attached Actual site condition photographs for you reference.

EA13082622122Sep 2021 → Mar 2027

Reason as filed by the promoterOur project was completed-Wing A in 2019 and Wing B in 2024-and the completion certificate has been uploaded; we have also handed over possession to all allottees.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000011577Machindra M MoreOmkar Developers & Associates30/05/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Dec 2024

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 1File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 1File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 1File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 1File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 1File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 2File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 2File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 2File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 2File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 2File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 2File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 3File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 3File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 3File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 3File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 3File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Withdrawal Update Form 3File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2017-2018)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2026-2027)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2018-2019)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2019-2020)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2020-2021)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2021-2022)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2022-2023)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2023-2024)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2024-2025)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 2A (FY 2025-2026)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Form 5 (FY 2025-2026)File: Declaration For Non Availability of QPR.pdf2 Oct 2026
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 mahadev park.pdf5 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Mahadev Park A Bld Completion (2).pdf5 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 mahadev park.pdf2 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Chikhali 1651 B Completion.pdf2 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Final RERA Audit Report FY 21-22-Omkar Developers.pdf2 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Audit Report Omkar Developers AOP FY 2020-21.pdf24 Feb 2022
Declaration about Commencement CertificateFile: Commencement Declaration.pdf28 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM -2A 2019_compressed.pdf28 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A 2020_compressed.pdf28 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form -2A 2021_compressed.pdf28 Jun 2021
Disclosure of sold/ booked inventoryFile: Discolsure 2021 (1)_compressed.pdf28 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 2019-20 Signed RERA Audit for uploading.pdf23 Oct 2020
Certificates of CA (Form 5)File: RERA Audit-Omkar.pdf30 Sep 2019
Certificates of CA (Form 5)File: Final CA Certificate-Omkar.pdf29 Sep 2018
Building plan approvalFile: PLAN.pdf31 Jul 2017
Layout approvalFile: PLAN.pdf31 Jul 2017
PAN CardFile: omkar pan.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE.pdf31 Jul 2017
Details of encumbrancesFile: LETTER.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: PLAN.pdf31 Jul 2017
Building Plan Approval (IOD)File: PLAN.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCE.pdf31 Jul 2017
Declaration in FORM BFile: FORM B (2).pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECT.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3.pdf31 Jul 2017
Proforma of Allotment letterFile: Draft Agreement.pdf31 Jul 2017

How this compares with Pune

76%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 66 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mahadev Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pimpri Chinchawad (M Corp.)13,700+ in Pune

2 kmMahadev ParkCompleted 13Lapsed / revoked 6Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: Omkar Developers & Associates

Omkar Developers & Associates has 1 registration on MahaRERA, including Mahadev Park. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Mahadev Park is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mahadev Park?

The registered promoter entity is Omkar Developers & Associates, an others as per the filing. Its GSTIN 27AAAAO3954G1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mahadev Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mahadev Park?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Mahadev Park?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mahadev Park?

The professionals named in the filing: Architect: Santosh Kisanrao Kate; Engineer: Ramchandra Krihnarao Randhave; Chartered Accountant: R DEVENDRA KUMAR AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mahadev Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mahadev Park. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mahadev Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.