Home / Browse projects / Aurangabad, Maharashtra / Maaz Residency 15

Registration lapsed No litigation declared Residential / Group Housing project

Maaz Residency 15

By Mohseen Ali Maqsood Ali Khan

RG-MH-08785 · RERA P51500022038 · Last updated on MahaRERA portal: 12 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 15 months past the filed date
  • Completion date moved by 23 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Jul 2025Possession promised15 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 90%
0Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

Maaz Residency 15 is a Residential / Group Housing project by Mohseen Ali Maqsood Ali Khan in Aurangabad, Maharashtra, registered with MahaRERA as P51500022038 on 25 Aug 2019. Possession was promised by 31 Jul 2025 and is now 15 months past that date. The completion date has moved by 23 months from the original filing.

At a glance

Project

  • NameMaaz Residency 15
  • TypeResidential / Group Housing
  • Location
    • Gut No 15
    • Padegaon
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431005
  • Pincode431005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500022038
  • ReraGenie IDRG-MH-08785

Builder

  • NameMohseen Ali Maqsood Ali Khan
  • Entity typeIndividual

Key dates

15 months past promisethis monthRegisteredAug 2019First promiseAug 2023Revised toJul 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Aug 2019
  • Promised completion31 Jul 2025
  • Revised completionRevised to 31 Jul 2025 (originally 1 Aug 2023)
  • Buildings1 building record
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MAAZ RESIDENCY 15NA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

MAAZ RESIDENCY 15: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 12 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes85%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area729 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Sep 2024
LandownerVillageDistrict
Rafique khan Jabbar KhanAurangabad (M Corp.)Aurangabad
Shaikh Salim Shaikh ManjurAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityAURANGABAD MUNICIPAL CORPORATION AURANGABAD
Permissible FSI918.0
Proposed, not sanctioned622 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchADALAT ROAD AURANGABAD

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAb Samad
EngineerEr SIDDIQUI
Chartered AccountantMAHAVIR PATNI
Chartered AccountantRAMESHWAR RANBHARE
PartnerRole in project
Mohseen Ali Maqsood Ali Khan-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500017874Aug 2023 → Jul 2024

Reason as filed by the promoterDue to pandemic situation of covid work was stopped for almost two year

EXT51500024564Aug 2023 → Jul 2025

Reason as filed by the promoterDUE TO SOME FINANCIAL TECHINCAL CRISIS

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Aug 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Aug 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: FORMAT B.pdf12 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT.pdf12 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf12 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERT.pdf12 Dec 2024
Declaration about Commencement CertificateFile: FORMAT D.pdf12 Dec 2024
CERSAI detailsFile: CERSAI.pdf12 Dec 2024
CERSAI detailsFile: CERSAI DEC.pdf12 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY ASS.pdf12 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf12 Dec 2024
Disclosure of sold/ booked inventoryFile: SOLD MAAZ NEW.pdf25 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arc maaz.pdf5 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2019-20 2a.pdf5 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 20-21 form 2a.pdf5 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21-22 2a.pdf5 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2022-23 FORM 2A.pdf5 Nov 2023
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY MAAZ PDF.pdf5 Nov 2023
Declaration in FORM BFile: FORM B.pdf1 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC CERT.pdf1 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERT.pdf1 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA NEW_compressed.pdf1 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19-20.pdf1 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21.pdf1 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022-23.pdf1 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 21-22.pdf1 Nov 2023
Layout approvalFile: Maaz Residency Layout.pdf8 Aug 2019
Building plan approvalFile: Maaz Submission.pdf8 Aug 2019
PAN CardFile: PAN MOHSEEN.pdf8 Aug 2019
Copy of the legal title reportFile: Maaz Search.pdf8 Aug 2019
Details of encumbrancesFile: Maaz No Encumbrance.pdf8 Aug 2019
Copy of Layout Approval (in case of layout)File: Maaz Residency Layout.pdf8 Aug 2019
Building Plan Approval / NA Order for plotted developmentFile: Maaz Submission.pdf8 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf8 Aug 2019
Declaration in FORM BFile: Maaz Bond 1.pdf8 Aug 2019
Declaration in FORM BFile: Maaz Bond 2.pdf8 Aug 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Maaz CA 1A.pdf8 Aug 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Maaz CA 1B.pdf8 Aug 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Maaz CA 2.pdf8 Aug 2019
Proforma of Allotment letterFile: Sample Sale Deed.pdf8 Aug 2019

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 23 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Maaz Residency 15 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Padegaon1,400+ in Aurangabad

2 kmMaaz Residency 15Completed 6Lapsed / revoked 6Other 7Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: Mohseen Ali Maqsood Ali Khan

Mohseen Ali Maqsood Ali Khan has 1 registration on MahaRERA, including Maaz Residency 15. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that Maaz Residency 15 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Maaz Residency 15 is delayed beyond 31 Jul 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Maaz Residency 15?

The registered promoter entity is Mohseen Ali Maqsood Ali Khan, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Maaz Residency 15?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Maaz Residency 15?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Maaz Residency 15?

The professionals named in the filing: Architect: Ab Samad; Engineer: Er SIDDIQUI; Chartered Accountant: MAHAVIR PATNI; Chartered Accountant: RAMESHWAR RANBHARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Maaz Residency 15?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Maaz Residency 15. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Maaz Residency 15 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.