Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
11 of 11Construction stages doneevery applicable stage filed complete
8 of 65Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

LUXURY CHSL LTD is a Residential / Group Housing project by LAXMIDEVI DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800050568 on 21 Apr 2023. Possession was promised by 14 Sep 2026 and is now 1 months past that date. The completion date has moved by 15 months from the original filing. 57 of the 65 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameLUXURY CHSL LTD
  • TypeResidential / Group Housing
  • Location
    • UNNAT NAGAR GOREGAON WEST MUMBAI
    • BEHIND FILMISTAN
    • Goregaon
    • Borivali
    • Mumbai Suburban
    • 400104
  • Pincode400104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800050568
  • ReraGenie IDRG-MH-76807

Builder

  • NameLAXMIDEVI DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAEFL2308J1ZF
  • PartnersBharat Ashulal Kothari, Rakesh Ashulal Kothari, Gunvant Ashulal Kothari
  • Other registrations6 more →
  • Completed5 of 7
  • Past their filed date1
  • Declared earlier projects7 →

Key dates

1 months past promisethis monthRegisteredApr 2023First promiseJun 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Apr 2023
  • Promised completion14 Sep 2026
  • Revised completionRevised to 14 Sep 2026 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed54 files

Current status

88%57 of 65 units booked
139.7%Work done, per cost certificate

Figures as on 24 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LAXMI NAMAHNA181865065

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

LAXMI NAMAH: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Closed/Covered50

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area588 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Jun 2026
LandownerVillageDistrict
LAXMIDEVI DEVELOPERSGoregaonMumbai Suburban
LUXURY CHSL LTDGoregaonMumbai Suburban

Approvals and building plan

Sanctioning authorityMumbai Housing and Area Development Board
Permissible FSI3605.48
Proposed, not sanctioned2,784 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEVERSHINE AANGAN PLOT NO 4 JAWAHAR NAGAR MUMBAI-400062
Estimated costRs 35.27 cr
Cost incurredRs 49.26 cr
Work done139.67%
BuildingWingEstimatedIncurred
LAXMI NAMAHNARs 21.40 crRs 25.46 cr
-NARs 13.87 crRs 23.80 cr

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDaksh Hirani and Associates
ArchitectARCHVIEW ASSOCIATES ENGINEERS AND ARCHITECTS
EngineerDIVYESH N KOTHARI
EngineerDINESH MEHTA
Chartered AccountantAkshay & Co
Chartered AccountantAMPAC & ASSOCIATES
Chartered AccountantPIYUSH SHETH
Chartered AccountantZUBIN HARIA AND ASSOCIATES
Chartered AccountantJAIN ANIL & ASSOCIATES
Chartered Accountantpranay punamiya & co.
PartnerRole in project
LAXMIDEVI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA19062621442Jun 2025 → Sep 2026

Reason as filed by the promoterSubject: Submission of Technical Reasons for Delay in Completion of the Project - Luxury Chsl, Maha RERA Reg. No. P51800050568 Respected Sir. 1. Pravin Kothari, are the promoters of the real estate project known as "Luxury Chsl bearing Maha RERA Registration No. P51800050568 our project plan wise data is this: 1. Total Built up area and permissible built up-3848.05 2. Total unit-65 and parking- 60 and this data is not mentioned in rera side. So I applied for an extension for 3 months. once clear extension process then I will apply for correction and that time submit all data latest plan wise T

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1_Architect Certificate_Laxmi Namah_Q1_2026-2027.pdf24 Aug 2026
Withdrawal Update Form 2File: Form 2_Engineer Certificate_Laxmi Namah_Q1_2026-27.pdf24 Aug 2026
Withdrawal Update Form 3File: Form 3_C A Certificate_Laxmi Namah_Q1_2026-27.pdf24 Aug 2026
Form 2A (FY 2025-2026)File: FORM 2A.pdf24 Aug 2026
Withdrawal Update Form 1File: FORM 1_ARCHITECT CERTIFICATE_LAXMI NAMAH_Q3_2025-26.pdf19 Aug 2026
Withdrawal Update Form 1File: form 1.pdf19 Aug 2026
Withdrawal Update Form 2File: FORM 2_ENGINEER CERTIFICATE_LAXMI NAMAH_Q3_2025-26.pdf19 Aug 2026
Withdrawal Update Form 2File: form 2.pdf19 Aug 2026
Withdrawal Update Form 3File: Form 3_C A certificate_Laxmi Namah_Q3_2025-26.pdf19 Aug 2026
Withdrawal Update Form 3File: form 3.pdf19 Aug 2026
Withdrawal Update Form 1File: FORM 1_ARCHITECT CERTIFICATE_LAXMI NAMAH_Q2_2025-26.pdf18 Aug 2026
Withdrawal Update Form 2File: FORM 2_ENGINEER CERTIFICATE_LAXMI NAMAH_Q2_2025-26.pdf18 Aug 2026
Withdrawal Update Form 3File: FORM 3_C A CERTIFICATE_LAXMI NAMAH_Q2_2025-26_compressed.pdf18 Aug 2026
Withdrawal Update Form 1File: Form 1_Architect Certificate_Laxmi Namah_Q1_2025-26.pdf11 Jun 2026
Withdrawal Update Form 2File: FORM 2_ENGINEER CERTIFICATE_LAXMI NAMAH_Q1_2025-26.pdf11 Jun 2026
Withdrawal Update Form 3File: FORM 3_C A CERTIFICATE_LAXMI NAMAH_Q1_2025-26_compressed.pdf11 Jun 2026
Commencement Certificates / NA Order for plotted developmentFile: FCC.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's Certificate.pdf5 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Luxury mar 23.pdf5 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Luxury MARCH 23.pdf5 Jul 2023
Proforma of Agreement for saleFile: final draft agreement for sale - luxury - RERA NEW.pdf6 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PAGE COMPRESS NEW.pdf11 Apr 2023
Proforma of Agreement for saleFile: FINAL DRAFT AGREEMENT FOR SALE - LUXURY - RERA.pdf11 Apr 2023
Details of encumbrances concerned to FinanceFile: Self Declaration Regarding Financial Encumberance.pdf10 Apr 2023
Details of encumbrances concerned to LegalFile: Self Declaration Regarding Financial Encumberance.pdf10 Apr 2023
CERSAI detailsFile: CERSAI_Search_Report_200265740352_For_Asset_Based_Search_10_04_2023_15_26_51_998.pdf10 Apr 2023
Deviation Report with respect to Allotment letterFile: Deviation Report in respect of allotment letter new.pdf3 Apr 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT AS PER AGREEMENT.pdf3 Apr 2023
Proforma of Allotment letterFile: MODEL FORM OF ALLOTMENT LETTER NEW.pdf1 Apr 2023
Details of encumbrances concerned to FinanceFile: FINANCE ENCUMBRANCE RERA.pdf1 Mar 2023
Details of encumbrances concerned to LegalFile: FINANCE ENCUMBRANCE RERA.pdf1 Mar 2023
Declaration about Commencement CertificateFile: Format d.pdf28 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account Format A.pdf28 Feb 2023
Building plan approvalFile: IOA.pdf27 Feb 2023
Building plan approvalFile: Plan.pdf27 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: IOA.pdf27 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan.pdf27 Feb 2023
Declaration in FORM BFile: Form B luxury001 (2).pdf24 Feb 2023
Layout approvalFile: Plan.pdf20 Feb 2023
Copy of Layout Approval (in case of layout)File: Plan.pdf20 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: int in other real estate org rk.pdf18 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: int in other real estate org gk.pdf18 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: int in other real estate org bk.pdf18 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Other Realstate Project.pdf16 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A Engineer Certificate Quality Assu COMPRES.pdf15 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf14 Feb 2023
Disclosure of sold/ booked inventoryFile: Sold - Unsold.pdf9 Feb 2023
Details of encumbrances concerned to FinanceFile: finance encumbrances luxury.pdf3 Feb 2023
Details of encumbrances concerned to LegalFile: finance encumbrances luxury.pdf3 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf3 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Cost incured (Luxury)001.pdf2 Feb 2023
Copy of the legal title reportFile: Title Certificate for RERA ( Luxury CHSL)-min.pdf31 Jan 2023
PAN CardFile: LD PAN CARD.pdf7 Jan 2023
Copy of the legal title reportFile: Title Certificate ( Luxury CHSL) NEW.pdf7 Jan 2023

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise1 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
LAXMI SHRUSHTI - WING BP51800030965GOREGAON WEST, Mumbai Suburban136Sep 2021OngoingAug 2025Not delivered
LAXMI ANNEXP51800026325JAWAHAR NAGAR GOREGAON WEST, Mumbai Suburban21Sep 2020CompletedJun 2023Jul 2022
LAXMI CALLISTAP51800010929Goregaon West, Mumbai Suburban90Aug 2017CompletedSep 2019Late, Dec 2020
Laxmi HeightsJawhar Nagar Road No 16 Goregaon west35-CompletedDec 2018Nov 2018
Laxmi EnclaveNadaidwala compound SV Road Malad west24-CompletedJun 2018Mar 2018
laxmi VillaJawahr Nagar Road No. 0337-CompletedJun 2018May 2018

How this compares with Mumbai Suburban

88%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 15 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LUXURY CHSL LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BEHIND FILMISTAN6,700+ in Mumbai Suburban

2 kmLUXURY CHSL LTDCompleted 147Lapsed / revoked 67Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 366 registered projects within 2 km.

Builder: LAXMIDEVI DEVELOPERS

LAXMIDEVI DEVELOPERS has 7 registrations on MahaRERA, including LAXMI HEIGHTS and LAXMI CALLISTA. Its filings disclose 7 earlier MahaRERA projects: declares 4 of 5 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if LUXURY CHSL LTD is delayed beyond 14 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LUXURY CHSL LTD?

The registered promoter entity is LAXMIDEVI DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAEFL2308J1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LUXURY CHSL LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LUXURY CHSL LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LUXURY CHSL LTD?

The professionals named in the filing: Architect: Daksh Hirani and Associates; Architect: ARCHVIEW ASSOCIATES ENGINEERS AND ARCHITECTS; Engineer: DIVYESH N KOTHARI; Engineer: DINESH MEHTA; Chartered Accountant: Akshay & Co; Chartered Accountant: AMPAC & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LUXURY CHSL LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LUXURY CHSL LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LUXURY CHSL LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.