Home / Developers / LAXMIDEVI DEVELOPERS
LAXMIDEVI DEVELOPERS: RERA track record
GSTIN 27AAEFL2308J1ZF · Partnership · attribution by exact filing name, entity resolution in progress
LAXMIDEVI DEVELOPERS has 7 registrations on MahaRERA, including LAXMI HEIGHTS and LAXMI CALLISTA. Its filings disclose 7 earlier MahaRERA projects: declares 4 of 5 past projects completed on time.
Projects by this developer
Showing all 7 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| LAXMI SHRUSHTI - WING BP51800030965 | GOREGAON WEST, Mumbai Suburban, 400090 | 129 | 100% | 29 Sep 2021 | Registered |
| LUXURY CHSL LTDP51800050568 | BEHIND FILMISTAN, Mumbai Suburban, 400104 | 65 | 88% | 21 Apr 2023 | Registered |
| LAXMI ANNEXP51800026325 | JAWAHAR NAGAR GOREGAON WEST, Mumbai Suburban, 400104 | 20 | 75% | 8 Sep 2020 | Completed |
| LAXMI CALLISTAP51800010929 | Goregaon West, Mumbai Suburban, 400062 | - | - | 31 Aug 2017 | Completed |
| LAXMI HEIGHTSP51800006754 | Goregaon, Mumbai Suburban, 400062 | - | - | 16 Aug 2017 | Completed |
| Laxmi SanskrutiP51800034219 | Jawahar Nagar, Goregaon West, Mumbai Suburban, 400104 | - | - | 25 Mar 2022 | Completed |
| LAXMI VILLAP51800002675 | Borivali, Mumbai Suburban, 400064 | - | - | 2 Aug 2017 | Completed |
What this promoter declares as its own experience
LAXMIDEVI DEVELOPERS declares experience on 7 earlier projects. 4 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
4 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| laxmi Villa | 1 Jun 2018 | 23 May 2018 | On time |
| Laxmi Enclave | 30 Jun 2018 | 21 Mar 2018 | On time |
| Laxmi Heights | 31 Dec 2018 | 17 Nov 2018 | On time |
| LAXMI CALLISTA P51800010929 | 1 Sep 2019 | 17 Dec 2020 | +16 months |
| LAXMI ANNEX P51800026325 | 30 Jun 2023 | 29 Jul 2022 | On time |
| LUXURY CHSL LTD P51800050568 | 30 Jun 2025 | Not completed yet | Ongoing |
| LAXMI SHRUSHTI - WING B P51800030965 | 31 Aug 2025 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify LAXMIDEVI DEVELOPERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAEFL2308J1ZF on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with LAXMIDEVI DEVELOPERS?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.