Registered No litigation declared Residential / Group Housing project

LUMBINI TOWER

By RAJKALA DEVELOPERS

RG-MH-07646 · RERA P50500034928 · Last updated on MahaRERA portal: 17 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 88%
19 of 66Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 149 documents Report an error

LUMBINI TOWER is a Residential / Group Housing project by RAJKALA DEVELOPERS in Nagpur, Maharashtra, registered with MahaRERA as P50500034928 on 28 Apr 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 47 of the 66 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameLUMBINI TOWER
  • TypeResidential / Group Housing
  • Location
    • LASHKAREBAGH
    • HANSAPURI LASHKAREBAGH
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440018
  • Pincode440018
  • RERA no.P50500034928
  • ReraGenie IDRG-MH-07646

Builder

  • NameRAJKALA DEVELOPERS
  • Entity typePartnership
  • PartnersANIL UKEY, Sushank Anil Ukey, Dilip Ramdas Ukey

Key dates

this monthRegisteredApr 2022First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed149 files

Current status

71%47 of 66 units booked
91.5%Work done, per cost certificate

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LUMBINI TOWERNA181660666

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 88%.

LUMBINI TOWER: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises88%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.59%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.48%

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes56%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes81%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYesNot applicable
Water conservation /Rain water harvestingYes78%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes53%
Electrical meter room, sub-station, receiving stationYes49%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed156

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots156
Closed/Covered156

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,334 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Dec 2025

Approvals and building plan

Sanctioning authorityNAGPUR MUNICIPAL CORPORATION
Permissible FSI7406.88
Proposed, not sanctioned7,407 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSADAR NAGPUR
Estimated costRs 23.28 cr
Cost incurredRs 21.30 cr
Work done91.5%
BuildingWingEstimatedIncurred
LUMBINI TOWERNARs 23.28 crRs 21.30 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEMANATE DESIGN
EngineerANIL UKEY
EngineerAMIT BHIMRAO PATANKAR
EngineerHEMANT MOHAD
Chartered AccountantANKIT TALREJA G & D ASSOCIATES
Chartered AccountantM/S GAD & ASSOCIATES
Chartered AccountantUTSAV SUMIT & ASSOCIATES
Chartered AccountantSUMIT SANTOSH AGRAWAL & ASSOCIATES
PartnerRole in project
RAJKALA DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA17122518725Dec 2025 → Dec 2026

Reason as filed by the promoterWe, RAJKALA DEVELOPERS, Promoter of the real estate project “LUMBINI TOWER”, bearing MahaRERA Registration No. P50500034928, hereby submit this application seeking an extension of twelve (12) months for completion of the said project. The project progress has been affected due to unavoidable delays in obtaining statutory approvals, shortage of skilled and semi-skilled labour, disruptions in procurement and supply of construction materials, and additional time required for execution of infrastructure, amenities, and essential services in compliance with approved plans and applicable norms. Furt

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed149

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 MARCH 2026.pdf17 Jul 2026
Withdrawal Update Form 2File: FORM 2 MARCH 2026 LUMBINI.pdf17 Jul 2026
Withdrawal Update Form 3File: FORM 3.pdf17 Jul 2026
Form 2A (FY 2025-2026)File: FORM-2A MARCH-2026 SCANNED.pdf17 Jul 2026
Form 5 (FY 2025-2026)File: FORM-5_MAR-26_LUMBINI TOWER.pdf17 Jul 2026
Withdrawal Update Form 1File: FORM 1 MARCH 2026.pdf20 Jun 2026
Withdrawal Update Form 2File: FORM 2 MARCH 2026 LUMBINI.pdf20 Jun 2026
Withdrawal Update Form 3File: FORM 3.pdf20 Jun 2026
Withdrawal Update Form 1File: FORM-1 JUNE-2025.pdf18 Jun 2026
Withdrawal Update Form 2File: FORM 2 LUMBINI TOWER JUNE 2025.pdf18 Jun 2026
Withdrawal Update Form 3File: form 3 lumbini tower june 2025 (1)_compressed.pdf18 Jun 2026
Withdrawal Update Form 1File: FORM-1 JUNE-2025.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2 LUMBINI TOWER JUNE 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: form 3 lumbini tower june 2025 (1)_compressed.pdf20 Jan 2026
Form 1File: FORM 1 JUNE 2022_page-0001.pdf17 Dec 2025
Form 2File: FORM 2 JUNE 2022.pdf17 Dec 2025
Form 3File: FORM 3 JUNE 2022.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD JUNE-2022.pdf17 Dec 2025
Form 1File: FORM 1 SEP 2022.pdf17 Dec 2025
Form 2File: FORM 2 SEP 2022.pdf17 Dec 2025
Form 3File: FORM 3 SEP 2022.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD SEPT-2022.pdf17 Dec 2025
Form 1File: FORM 1 DEC 2022.pdf17 Dec 2025
Form 2File: FORM 2 DEC 2022.pdf17 Dec 2025
Form 3File: FORM 3 DEC 2022.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD DEC-2022.pdf17 Dec 2025
Form 1File: FORM 1 MARCH 2023.pdf17 Dec 2025
Form 2File: FORM 2 MARCH 2023.pdf17 Dec 2025
Form 3File: FORM-3 MARCH-2023.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD MAR-2023.pdf17 Dec 2025
Form 1File: FORM 1 JUNE 2023.pdf17 Dec 2025
Form 2File: FORM-2 JUN-2023.pdf17 Dec 2025
Form 3File: FORM-3 JUN-2023.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD JUNE-2023.pdf17 Dec 2025
Form 1File: FORM 1 SEP 2023.pdf17 Dec 2025
Form 2File: FORM-2 SEPT-2023.pdf17 Dec 2025
Form 3File: FORM-3 SEPT-2023.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD SEPT-2023.pdf17 Dec 2025
Form 1File: FORM 1 DEC 2023.pdf17 Dec 2025
Form 2File: FORM 2 DEC 2023.pdf17 Dec 2025
Form 3File: FORM 3 31st December 2023.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD DEC-2023.pdf17 Dec 2025
Form 1File: FORM 1 MARCH 2024.pdf17 Dec 2025
Form 2File: FORM 2 MARCH 2024.pdf17 Dec 2025
Form 3File: FORM 3 MARCH 24.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD MARCH-2024.pdf17 Dec 2025
Form 1File: FORM 1 JUNE 2024.pdf17 Dec 2025
Form 2File: FORM 2 JUNE 2024.pdf17 Dec 2025
Form 3File: FORM 3 JUNE 24.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD JUNE-2024.pdf17 Dec 2025
Form 1File: FORM 1 SEP 2024.pdf17 Dec 2025
Form 2File: FORM 2 SEP 2024.pdf17 Dec 2025
Form 3File: FORM 3 SEP 24.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD SEP-2024.pdf17 Dec 2025
Form 1File: FORM 1 DEC 24.pdf17 Dec 2025
Form 2File: FORM-2 DEC-2024.pdf17 Dec 2025
Form 3File: FORM-3 DEC-24.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD DEC-2024.pdf17 Dec 2025
Form 1File: FORM 1 MARCH 2025.pdf17 Dec 2025
Form 2File: FORM-2 MARCH-2025.pdf17 Dec 2025
Form 3File: FORM-3 MARCH-2025.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD MAR-2025.pdf17 Dec 2025
Withdrawal Update Form 1File: FORM-1 SEPT-2025.pdf17 Dec 2025
Withdrawal Update Form 1File: FORM-1 JUNE-2025.pdf17 Dec 2025
Withdrawal Update Form 2File: FORM 2 LUMBINI TOWER SEP 2025.pdf17 Dec 2025
Withdrawal Update Form 2File: FORM 2 LUMBINI TOWER JUNE 2025.pdf17 Dec 2025
Withdrawal Update Form 3File: Form 3 lumbini tower sep 2025_compressed.pdf17 Dec 2025
Withdrawal Update Form 3File: form 3 lumbini tower june 2025 (1)_compressed.pdf17 Dec 2025
Form 2A (FY 2024-2025)File: FORM-2A MARCH-2025 SCANNED.pdf17 Dec 2025
Withdrawal Update Form 1File: FORM-1 JUNE-2025.pdf16 Dec 2025
Withdrawal Update Form 1File: FORM-1 SEPT-2025.pdf16 Dec 2025
Withdrawal Update Form 2File: FORM 2 LUMBINI TOWER JUNE 2025.pdf16 Dec 2025
Withdrawal Update Form 2File: FORM-1 SEPT-2025.pdf16 Dec 2025
Withdrawal Update Form 3File: Form 3 June 2024.pdf16 Dec 2025
Withdrawal Update Form 3File: Form 3 lumbini tower sep 2025_compressed.pdf16 Dec 2025
Form 2A (FY 2022-2023)File: FORM-2A_MAR-23.pdf16 Dec 2025
Form 2A (FY 2023-2024)File: FORM-2A_MAR-24.pdf16 Dec 2025
Form 5 (FY 2024-2025)File: FORM-5 MARCH-25 LUMBINI TOWER.pdf16 Dec 2025
Form 5 (FY 2022-2023)File: FORM-5 MARCH-2023.pdf16 Dec 2025
Form 5 (FY 2023-2024)File: FORM-5 MARCH-2024.pdf16 Dec 2025

How this compares with Nagpur

71%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 12 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LUMBINI TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HANSAPURI LASHKAREBAGH2,800+ in Nagpur

Builder: RAJKALA DEVELOPERS

RAJKALA DEVELOPERS has 1 registration on MahaRERA, including LUMBINI TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if LUMBINI TOWER is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LUMBINI TOWER?

The registered promoter entity is RAJKALA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LUMBINI TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LUMBINI TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LUMBINI TOWER?

The professionals named in the filing: Architect: EMANATE DESIGN; Engineer: ANIL UKEY; Engineer: AMIT BHIMRAO PATANKAR; Engineer: HEMANT MOHAD; Chartered Accountant: ANKIT TALREJA G & D ASSOCIATES; Chartered Accountant: M/S GAD & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LUMBINI TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LUMBINI TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LUMBINI TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.