ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Lodha Woods - Tower 6

Registered No litigation declared Residential / Group Housing project

Lodha Woods - Tower 6

By Macrotech Developers Limited

RG-MH-92346 · RERA P51800046327 · Last updated on MahaRERA portal: 8 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2027Possession promisedmoved 12 months from the original
4 of 11Construction stages donefurthest along: Staircases, 85%
2 of 111Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

Lodha Woods - Tower 6 is a Residential / Group Housing project by Macrotech Developers Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046327 on 22 Jun 2022. Possession is promised by 30 Nov 2027. The completion date has moved by 12 months from the original filing. 109 of the 111 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameLodha Woods - Tower 6
  • TypeResidential / Group Housing
  • Location
    • Akurli Road
    • Kandivali
    • Borivali
    • Mumbai Suburban
    • 400101
  • Pincode400101
  • RERA no.P51800046327
  • ReraGenie IDRG-MH-92346

Builder

  • NameMacrotech Developers Limited
  • Entity typeCompany
  • CINL45200MH1995PLC093041
  • GSTIN27AAACL1490J1ZG
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • MdAbhishek Mangalprabhat Lodha
  • Other registrations140 more →
  • Completed126 of 141
  • No longer live13 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

this monthRegisteredJun 2022First promiseNov 2026Revised toNov 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Jun 2022
  • Promised completion30 Nov 2027
  • Revised completionRevised to 30 Nov 2027 (originally 30 Nov 2026)
  • Buildings1 building record
  • Documents filed71 files

Current status

98%109 of 111 units booked
88.0%Work done, per cost certificate

Figures as on 8 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing 6NA23231110111

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 85%.

Wing 6: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 8 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes55%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes85%
Street LightingYes70%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes60%
Solid Waste Management And DisposalYes60%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes55%
Aggregate area of recreational Open SpaceYes65%
Open ParkingYes0%

Parking filed61

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots61
Closed/Covered61

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,238 sq m
Land owned byNot the promoter
Named landowners1
Declared on16 Jun 2025
LandownerVillageDistrict
Rajesh Real Estate Pvt LtdMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI7654.37
Proposed, not sanctioned7,654 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWorli Mumbai - 400018
Estimated costRs 108.59 cr
Cost incurredRs 95.53 cr
Work done87.98%
BuildingWingEstimatedIncurred
Wing 6NARs 70.58 crRs 62.10 cr
-NARs 38.01 crRs 33.44 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVilas Desai & Associate
ArchitectPradeep M Kamble
EngineerK C Shah Consultants
EngineerSuresh Yelkar
Chartered AccountantChirag Sarvaiya & Co
Chartered AccountantM S K A & Associates
PartnerRole in project
Lodha Developers Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA17032620247Nov 2026 → Nov 2027

Reason as filed by the promoterNGT Issue - the project has been delayed due to circumstances beyond the control of the promoter, primarily relating to issues concerning the requirement of Environmental Clearance (EC) and jurisdictional ambiguity between the Central and State authorities for granting such clearance

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12504314Soven ChatterjeeLodha Developers Limited06/12/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jul 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jul 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Nov 2027

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: 1_updated_20250307-KWC-10th Amend Drawing 01-12.pdf8 Jul 2026
Building plan approvalFile: 3_updated_20250307-KWC-10th Amend Drawing 25-36.pdf8 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A - Lodha Woods - Tower 6 - P51800046327.pdf23 Jun 2026
Layout approvalFile: Layout.pdf27 May 2026
Building plan approvalFile: 03 - Wing 1 to 9.pdf27 May 2026
Building plan approvalFile: 03 - Wing 6.pdf27 May 2026
Building plan approvalFile: 04 - Wing 6.pdf27 May 2026
Building plan approvalFile: 05 - Wing 6.pdf27 May 2026
Withdrawal Update Form 1File: Form1 - Lodha Woods -Tower 6 - P51800046327.pdf20 Apr 2026
Withdrawal Update Form 2File: Woods Tower 6 Form 2.pdf20 Apr 2026
Withdrawal Update Form 3File: Woods Tower 6 Form-3.pdf20 Apr 2026
Withdrawal Update Form 1File: Form-1 Wood T-6- Dec-25.pdf24 Jan 2026
Withdrawal Update Form 2File: Lodha Woods -Tower 6 Form 2.pdf24 Jan 2026
Withdrawal Update Form 3File: Woods Tower 6 Form-3.pdf24 Jan 2026
Withdrawal Update Form 1File: Form- 1 Lodha Woods -Tower 6-P51800046327 Sep-25.pdf25 Oct 2025
Withdrawal Update Form 2File: Form-2 Lodha Woods -Tower 6 - P51800046327.pdf25 Oct 2025
Withdrawal Update Form 3File: Lodha Woods -Tower 6 - Form 3.pdf25 Oct 2025
Form 5 (FY 2024-2025)File: Lodha Woods Tower 6.pdf14 Oct 2025
Form 2A (FY 2024-2025)File: Lodha Woods -Tower 6 - P51800046327 - Form 2A.pdf25 Jul 2025
Layout approvalFile: Layout Tower 6.pdf19 Jul 2025
Commencement certificateFile: Latest CC.pdf19 Jul 2025
Form 1File: Form 1 - Lodha Woods Tower 6.pdf20 Jun 2025
Form 2File: Form 2 - Lodha Kandivali Project - Tower 6 - Mar 25.pdf20 Jun 2025
Form 3File: Form 3 - Kandivali T-6 ( Mar-25).pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold (Lodha Kandivali Tower -6) - Mar 25.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Lodha Woods Tower 6.pdf2 May 2025
Layout approvalFile: Tower 6.pdf28 Mar 2025
Copy of Layout Approval (in case of layout)File: Tower 6.pdf28 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Woods T-6 Form-3 Dec-24 Signed.pdf28 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Lodha Woods -Tower 6 - Dec 24 Signed.pdf28 Feb 2025
Disclosure of sold/ booked inventoryFile: Kandivali T-6 Sold Unsold Signed.pdf28 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Lodha Woods Tower 6.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Woods tower 6 - Bank correction.pdf8 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: kandivali 6.pdf8 Nov 2024
Disclosure of sold/ booked inventoryFile: Lodha Woods - Tower 6.pdf8 Nov 2024
Disclosure of sold/ booked inventoryFile: Woods tower 6 - sold unsold.pdf8 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Woods Tower 6.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: P51800046327 - Lodha Woods -Tower 6.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Lodha Woods -Tower 6 - P51800046327.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Lodha Woods -Tower 6 - P51800046327 - June24.pdf10 Aug 2024
Disclosure of sold/ booked inventoryFile: Lodha Woods -Tower 6 - P51800046327 - June24.pdf7 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf7 Jun 2024
Declaration about Commencement CertificateFile: Wing 6.pdf7 Jun 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold - Lodha Woods -Tower 6 - P51800046327 - March 24.pdf16 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Lodha Woods -Tower 6 - P51800046327 - March 24.pdf7 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 - Lodha Woods -Tower 6 - P51800046327 - Dec23.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold - Lodha Woods -Tower 6 - P51800046327 - Dec23.pdf26 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: 20231218Wing 5 Full CC.pdf21 Dec 2023
Disclosure of sold/ booked inventoryFile: Kharadi Pune Phase II Tower 6 - Sold Unsold - Sep23.pdf24 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Lodha Woods Tower 6 - Form1 - Sep23.pdf21 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Lodha Woods -Tower 6.pdf17 Oct 2023
Disclosure of sold/ booked inventoryFile: Lodha kandivali Project Tower 6 March 23.pdf21 Jul 2023
Disclosure of sold/ booked inventoryFile: Lodha kandivali Project Tower 6 June 23.pdf21 Jul 2023
Disclosure of sold/ booked inventoryFile: Lodha Woods T6.pdf25 May 2023
Commencement Certificates / NA Order for plotted developmentFile: New CC.pdf6 Dec 2022
Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (2).pdf17 Jun 2022
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development (1).pdf17 Jun 2022
Building plan approvalFile: 2 Building Plan Approval _ NA Order for plotted development.pdf17 Jun 2022
PAN CardFile: Macrotech Developers Ltd PAN CARD.pdf17 Jun 2022
Copy of the legal title reportFile: Title Report.PDF17 Jun 2022
Details of encumbrancesFile: Encumbrances- Lodha Woods Tower 6.pdf17 Jun 2022
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (2).pdf17 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development (1).pdf17 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: 2 Building Plan Approval _ NA Order for plotted development.pdf17 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: CC for Kandivali.pdf17 Jun 2022
Declaration about Commencement CertificateFile: CC Dec T 6.pdf17 Jun 2022
Declaration in FORM BFile: Form B -T6_compressed.pdf17 Jun 2022
CERSAI detailsFile: 1 CERSAI details.pdf17 Jun 2022
CERSAI detailsFile: 2 CERSAI details.pdf17 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Tower 6.pdf17 Jun 2022
Proforma of Allotment letterFile: Sale Agreement and Allotment Letter.pdf17 Jun 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Liana BP51700033964Dombivali, Thane140Mar 2022CompletedFeb 2026Jun 2024

How this compares with Mumbai Suburban

98%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Lodha Woods - Tower 6 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kandivali6,700+ in Mumbai Suburban

Builder: Macrotech Developers Limited

Macrotech Developers Limited has 141 registrations on MahaRERA, including LODHA BELMONDO ASHBRIDGE D, E and LODHA BELMONDO AUGUSTA B. Its filings disclose 6 earlier MahaRERA projects: declares 5 of 6 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Lodha Woods - Tower 6 is delayed beyond 30 Nov 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Lodha Woods - Tower 6?

The registered promoter entity is Macrotech Developers Limited, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 27AAACL1490J1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Lodha Woods - Tower 6?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Lodha Woods - Tower 6?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Lodha Woods - Tower 6?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Lodha Woods - Tower 6?

The professionals named in the filing: Architect: Vilas Desai & Associate; Architect: Pradeep M Kamble; Engineer: K C Shah Consultants; Engineer: Suresh Yelkar; Chartered Accountant: Chirag Sarvaiya & Co; Chartered Accountant: M S K A & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Lodha Woods - Tower 6?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Lodha Woods - Tower 6. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Lodha Woods - Tower 6 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one