ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / Leela Kutir

Registered No litigation declared Residential / Group Housing project

Leela Kutir

By INSPIRA REALTY LLP

RG-MH-13410 · RERA P51500047125 · Last updated on MahaRERA portal: 17 Apr 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Rs 30.00 crore secured on the land, in favour of Aditya Birla Capital Limited

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 50%
52 of 103Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 111 documents Report an error

Leela Kutir is a Residential / Group Housing project by INSPIRA REALTY LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500047125 on 10 Oct 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. 51 of the 103 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameLeela Kutir
  • TypeResidential / Group Housing
  • Location
    • Aurangabad Paithan Road
    • Nakshatrawadi
    • Aurangabad
    • 431002
  • Pincode431002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500047125
  • ReraGenie IDRG-MH-13410

Builder

  • NameINSPIRA REALTY LLP
  • Entity typeCompany
  • PartnerAayush Agrawal
  • DirectorMadhusudan Agrawal
  • Other registrations1 more →
  • Completed1 of 2
  • Past their filed date1

Key dates

1 months past promisethis monthRegisteredOct 2022PromisedSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Oct 2022
  • Promised completion30 Sep 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed111 files

Current status

50%51 of 103 units booked

Figures as on 17 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Leelakunj Wing ANA111043043
Leelakunj Wing BNA1110451560

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 17 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

Leelakunj Wing A33%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises4%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks12%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Leelakunj Wing B31%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure27%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises3%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed191

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots191
Closed/Covered88
Open Space103
BuildingClosed/CoveredOpen SpaceTotal
Leelakunj Wing A5150101
Leelakunj Wing B375390

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,680 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Capital Limited
Secured amountRs 30.00 crore
CERSAI search filedYes
Declared on23 Jun 2026

Approvals and building plan

Permissible FSI8637.77
Proposed, not sanctioned4,957 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSatellite Silver, Andheri Kurla Road, Andheri East, Mumbai 400059

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSharad Mahajan
EngineerMR. MILIND RATHI
EngineerMayur badgujar
Chartered AccountantRupal Motani
Chartered AccountantR M A and Co LLP
PartnerRole in project
INSPIRA REALTY LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Sep 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed111

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 31032026 LeelaKutir.pdf17 Apr 2026
Form 2File: Form 2 31032026 LeelaKutir.pdf17 Apr 2026
Form 3File: Form 3 31032026 LeelaKutir.pdf17 Apr 2026
Disclosure of Sold and Booked InventoryFile: Soldunsold 31032026 LeelaKutir.pdf17 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A 31032026 LeelaKutir.pdf17 Apr 2026
Form 3File: Form 3 Dec 2025 CA Certificate LK.pdf20 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold inventory Dec 2025 LK.pdf20 Jan 2026
Form 1File: Form 1 Architect certificate 31122025 LK.pdf20 Jan 2026
Form 2File: Form 2 Eng certificate 31122025 LK.pdf20 Jan 2026
Form 5 (FY 2022-2023)File: Leela kutir form 5 2022-23.pdf12 Nov 2025
Form 5 (FY 2023-2024)File: Leela Kutir RERA Form 5 FY 2023 24.pdf12 Nov 2025
Form 5 (FY 2024-2025)File: Form-5 Inspira Aura_Sep-2025.pdf12 Nov 2025
Form 1File: Form 1 Leela Kutir sept2025.pdf15 Oct 2025
Form 2File: Form 2_Leela Kutir_sept2025.pdf15 Oct 2025
Form 3File: Form 3_Leela Kutir_sept2025.pdf15 Oct 2025
Disclosure of Sold and Booked InventoryFile: Leela Kutir sold unsold sept 2025.pdf15 Oct 2025
Form 1File: LK Form 1_June 2025.pdf18 Jul 2025
Form 2File: LK_Form 2_June 2025.pdf18 Jul 2025
Form 3File: LK Form 3_June 2025 compressed.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Leela Kutir Sold-Unsold Data-30-06-2025.pdf18 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LK Form 3 31032025.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LK Form 1 31032025.pdf14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LK Form 2 31032025.pdf14 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Data till 31032025 LK.pdf14 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: LK FORM 2A 31032025.pdf14 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LK Dec 2024 Form 1.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Leela Kutir _Dec24 FORM 2.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LK_Dec 2024 Form 3.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LK Dec 2024 Form 1.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Leela Kutir _Dec24 FORM 2.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LK_Dec 2024 Form 3.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LK Dec 2024 Form 1.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LK_Dec 2024 Form 3.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Leela Kutir _Dec24 FORM 2.pdf16 Jan 2025
Proforma of Agreement for saleFile: AFS Leela Kutir - Revised for RERA upload - 08112024.pdf12 Nov 2024
Proforma of Agreement for saleFile: AFS Leela Kutir - Revised for RERA upload - 08112024.pdf12 Nov 2024
Proforma of Agreement for saleFile: AFS Leela Kutir - Revised for RERA upload - 08112024.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Leela Kutir form 3 sept 2024.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Leela Kutir form 3 sept 2024.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Leela Kutir form 3 sept 2024.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE Leela Kutir Sept 2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Leela Kutir_Sept 2024 form2.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Leela Kutir Sold Unsold 30 09 2024.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE Leela Kutir Sept 2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Leela Kutir_Sept 2024 form2.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Leela Kutir Sold Unsold 30 09 2024.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE Leela Kutir Sept 2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Leela Kutir_Sept 2024 form2.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Leela Kutir Sold Unsold 30 09 2024.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Leela Kutir RERA Form 5 FY 2023 24.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Leela Kutir RERA Form 5 FY 2023 24.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Leela Kutir RERA Form 5 FY 2023 24.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LK Form1 June 2024.pdf23 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2024 LK.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Leela Kutir Form 1 June 2024.pdf10 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 121023 R1 GK Amenities Spects.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Leela Kutir_Form 2A - Signed.pdf1 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: NEW CC.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: LK Sold Unsold.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Leela Kutir - Form_3 - CA Certificate - 31st Mar 2024 (signed)_compressed.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate LK.pdf12 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_Engineer_Certificate LK.pdf12 Apr 2024
Disclosure of sold/ booked inventoryFile: LK Sold Unsold Disclosure DEC 31 2023.pdf24 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1Leela Kutir.pdf15 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2Leela Kutir.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3LKcompressed.pdf15 Jan 2024
Proforma of Agreement for saleFile: Revised LK AFS dt 08112023.pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LK Form 3 30092023.pdf23 Oct 2023
Disclosure of sold/ booked inventoryFile: LK Inventory list .pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SIGNED CERTIFICATE-INSPIRA REALTY LLP (LEELA KUTIR).pdf4 Oct 2023
Disclosure of sold/ booked inventoryFile: LK_Sold Unsold_Inv_30032023.pdf21 Jul 2023
Disclosure of sold/ booked inventoryFile: LK_Sold Unsold Inv_30062023.pdf21 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Leela Kutil June'23_compressed.pdf21 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1_compressed (1).pdf14 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_compressed (1)_rotated.pdf14 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 - Leela Kutir - March 2023.pdf2 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31032023_LK_Form_2.pdf10 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 31032023_LK_Form_2A.pdf10 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032023 LK Form 1.pdf5 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Leela Kutir.pdf20 Jan 2023

How this compares with Aurangabad

50%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Leela Kutir on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nakshatrawadi1,400+ in Aurangabad

2 kmLeela KutirCompleted 4Lapsed / revoked 7Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: INSPIRA REALTY LLP

INSPIRA REALTY LLP has 2 registrations on MahaRERA, including GANGOTRI VIHAR PHASE I and Leela Kutir. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if Leela Kutir is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Leela Kutir?

The registered promoter entity is INSPIRA REALTY LLP, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Leela Kutir?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Leela Kutir?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Leela Kutir?

The professionals named in the filing: Architect: Sharad Mahajan; Engineer: MR. MILIND RATHI; Engineer: Mayur badgujar; Chartered Accountant: Rupal Motani; Chartered Accountant: R M A and Co LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Leela Kutir?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Leela Kutir. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Leela Kutir to a free account