Laxmi Nagar

By RELIABLE CONSTRUCTIONS

RG-MH-84661 · RERA P51800010918 · Last updated on MahaRERA portal: 22 May 2026

Source: official MahaRERA filing

Red flags

  • 16 complaints at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
26 of 66Construction stages doneacross 6 buildings; furthest along: Staircases, 90%
102 of 304Units unsoldnot recorded sold or booked
16Complaints at MahaRERAon this registration
Jump to the 144 documents Report an error

Laxmi Nagar is a Residential / Group Housing project by RELIABLE CONSTRUCTIONS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010918 on 31 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 202 of the 304 units on this registration are recorded sold or booked, and 26 of 66 construction stages are filed complete. 16 complaints are on record with the regulator.

At a glance

Project

  • NameLaxmi Nagar
  • TypeResidential / Group Housing
  • Location
    • Mahakali Mandir Marg
    • Goregaon West
    • Borivali
    • Mumbai Suburban
    • 400090
  • Pincode400090
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800010918
  • ReraGenie IDRG-MH-84661

Builder

  • NameRELIABLE CONSTRUCTIONS
  • Entity typePartnership
  • PartnersHANIF ISMAILBHAI AGWAN, IRSHAD HANIF MULLA, MOHAMMAD MAAZ HANIF AGWAN
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings6 building records
  • Documents filed144 files

Current status

66%202 of 304 units booked

Figures as on 22 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLDG NO 1 RehabNA150000
Bldg No 2 Laxmi Nagar Development CHS - Wing A RehabNA230000
BLDG NO 2 CONFARE HEIGHTS - Wing B and CNA23221700170
BLDG NO 3 - Contare HeightsNA35281340134
BLDG NO 4 - Religious StructureNA00000
BLDG NO 5 - Religious StructureNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 22 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

26 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Staircases, at 90%.

BLDG NO 1 Rehab91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Bldg No 2 Laxmi Nagar Development CHS - Wing A Rehab80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure86%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Sanitary Fittings within the flats / premises86%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks86%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.86%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
BLDG NO 2 CONFARE HEIGHTS - Wing B and C83%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.55%
BLDG NO 3 - Contare Heights92%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
BLDG NO 4 - Religious Structure0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BLDG NO 5 - Religious Structure0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities18

As on 22 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Swimming PoolNoNot applicable
Health ClubNoNot applicable
Fitness CenterNoNot applicable

Parking filed218

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots218
Closed/Covered215
Open Space3
BuildingClosed/CoveredOpen SpaceTotal
BLDG NO 1 Rehab022
Bldg No 2 Laxmi Nagar Development CHS - Wing A Rehab011
BLDG NO 2 CONFARE HEIGHTS - Wing B and C89089
BLDG NO 3 - Contare Heights1260126

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,400 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Aug 2025

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI26761.51
Proposed, not sanctioned26,762 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchARIHANT APPT OPP ST JOHNS HIGH SCHOOL S V ROAD, GOREGAON WEST MUMBAI 400104

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectT N Hasan of Punar Vikas Vastushastra
EngineerSiddique Sunasara of Frame Design
Chartered AccountantH.V. DAVDA & Co.
Chartered AccountantBhavesh C Vithlani
PartnerRole in project
RELIABLE CONSTRUCTIONS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018048Dec 2023 → Dec 2024

Reason as filed by the promoterThe Government Resolution passed by the State Government of Maharashtra, which sanctioned an increase in the minimum carpet area from 269 sq. ft. to 300 sq. ft. for the flats to be provided to the Slum Dwellers. This change has been driven by the genuine requests and aspirations of the Slum Dwellers for larger and more livable spaces. We recognized the importance of accommodating their needs to create a better living environment for them. This change has led to a series of subsequent adjustments, impacting the project's timeline and progress. The delay in the Slum Dwellers' vacation of the plo

EXT51800025275Dec 2023 → Dec 2026

Reason as filed by the promoter1. Adjusting to DCPR 2034 Norms;- 2. Interdependency Between Sale and Rehab Components:- 3. Impact of the COVID-19 Pandemic on Operations The onset of the COVID-19 pandemic brought unprecedented challenges to the real estate and construction sector: 4. Financial Strain During COVID-19:- 5. Government Resolution on Increased Carpet Area for Slum Dwellers:- 6. Challenges with Religious Structures on the Plot:-

Complaints filed with MahaRERA16

Case no.ComplainantRespondentFiled
CC006000000196200Rajiv Prakash and Sonie Rajiv PrakashReliable Constructions27/02/2021
CC006000000196201Rajiv Prakash and Sonie Rajiv PrakashReliable Constructions27/02/2021
CC006000000196202Amit Raj and Meghna RajReliable Constructions27/02/2021
CC006000000241314Bhagwandas Balaram KesarwaniM/s. Reliable Constructions31/05/2022
CC006000000292229Lajwanti Mulchand TanwaniM/s Reliable Constructions08/08/2022
CC006000000303351Viiaan Realty LLPReliable Constructions16/11/2022
CC006000000397178ANUBHAV BANSALM/S. RELIABLE CONSTRUCTIONS23/08/2023
CC006000000480127Shifa Zakir Hussain MullajiReliable Constructions13/05/2024
CC12400711Hembala YadavRELIABLE CONSTRUCTIONS08/11/2024
CC12400760Swasti SinghRELIABLE CONSTRUCTIONS13/11/2024
CC12502280Neha Mahesh JanjirkarRELIABLE CONSTRUCTIONS06/07/2025
CC12502149Angad Nagina GiriRELIABLE CONSTRUCTIONS29/06/2025
CC12502365Kiran Kumar GangapurRELIABLE CONSTRUCTIONS12/07/2025
CC12503590Tarique AnsariRELIABLE CONSTRUCTIONS08/10/2025
CC12504386TRANSGLOCAL EXPRESS FREIGHT PVT LTD TREFLRELIABLE CONSTRUCTIONS09/12/2025
CC12504548RASHID HAMEED KHANRELIABLE CONSTRUCTIONS20/12/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed144

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 144 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 LAXMINAGAR 30062025.pdf22 May 2026
Form 2File: Form 2 laxminagar 30062025.pdf22 May 2026
Form 3File: FORM 3 AS ON 30062025 Signed.pdf22 May 2026
Disclosure of Sold and Booked InventoryFile: DOS 300625.pdf22 May 2026
Form 1File: FORM 1 AS ON 30092025.pdf22 May 2026
Form 2File: Form 2 laxminagar 30092025.pdf22 May 2026
Form 3File: FORM 3 AS ON 30092025.pdf22 May 2026
Disclosure of Sold and Booked InventoryFile: DOS 30925.pdf22 May 2026
Form 5 (FY 2024-2025)File: LAXMINAGAR FORM 5 FY 2024 2025.pdf2 Mar 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ MARCH 25_ RELIABLE CONSTRUCTION_ LAXMI NAGAR.pdf24 Apr 2025
Certificates of CA (Form 3)File: FORM 3_ MARCH 25_ RELIABLE CONSTRUCTION_ LAXMI NAGAR_compressed.pdf24 Apr 2025
Certificates of CA (Form 3)File: FORM 3_ MARCH 25_ RELIABLE CONSTRUCTION_ LAXMI NAGAR_compressed.pdf24 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_ MARCH 25_ RELIABLE CONSTRUCTION_ LAXMI NAGAR_ CONFARE HEIGHTS.pdf24 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ MARCH 25_ RELIABLE CONSTRUCTION_ LAXMI NAGAR.pdf24 Apr 2025
CERSAI detailsFile: GetUserDocumentFileContent (7).pdf6 Feb 2025
Details of encumbrances concerned to FinanceFile: fin.pdf4 Feb 2025
Details of encumbrances concerned to LegalFile: fin.pdf4 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: sec unsec.pdf4 Feb 2025
Disclosure of sold/ booked inventoryFile: IMRAN SOLD UNSOLD.pdf27 Jan 2025
Certificates of CA (Form 3)File: FORM 3_ JUNE 23_compressed.pdf24 Jan 2025
Certificates of CA (Form 3)File: FORM 3_ DEC 24_compressed.pdf24 Jan 2025
Certificates of CA (Form 3)File: FORM 3_ SEP 24.pdf24 Jan 2025
Certificates of CA (Form 3)File: FORM 3_ JUNE 24_compressed.pdf24 Jan 2025
Certificates of CA (Form 3)File: FORM 3_ MARCH 24_compressed.pdf24 Jan 2025
Certificates of CA (Form 3)File: FORM 3_ DEC 23_compressed.pdf24 Jan 2025
Certificates of CA (Form 3)File: FORM 3_ SEP 23.pdf24 Jan 2025
Certificates of CA (Form 3)File: FORM 3_ MARCH 23_compressed.pdf24 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 8.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: 7 SEPT 2024.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: 6 JUNE 2024.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: 5 MARCH 2024.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: 4 DECEMBER 2023.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: 3 SEPTEMBER 2023.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: 2 JUNE 2023.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: 1 MARCH 2023.pdf9 Jan 2025
Declaration in FORM BFile: Form B Affidavit cum Declaration_27112024_P1-P3.pdf13 Dec 2024
Disclosure of sold/ booked inventoryFile: Book2.pdf30 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ SEP 24.pdf29 Nov 2024
Certificates of CA (Form 3)File: FORM 3_ SEP 24_compressed.pdf29 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_ SEP 24.pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: IMRAN SOLD UNSOLD.pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ SEP 24.pdf29 Nov 2024
CERSAI detailsFile: 1 Details of encumbrances.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf16 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 5.pdf16 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf16 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_v1.pdf4 Nov 2024
Certificates of CA (Form 3)File: Form 3 Laxminagar_11zon.pdf4 Nov 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE LAXMINAGAR AS ON 30-06-2024_11zon.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE SOLD AND UNSOLD.pdf5 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Revalidation reciept_Building 2 and 3.pdf26 Dec 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE SOLD UNSOLD.pdf26 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Confare 23 12 2023.pdf23 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Contare 23 12 2023.pdf23 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A_Eng Certf_Confare Sale Bldg No 02_21122023_P1-P2.pdf22 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A_Eng Certf_Contare Sale Bldg No 03_21122023_P1-P2.pdf22 Dec 2023
Certificates of CA (Form 3)File: Form - 3_Laxmi Nagar_20122023_P1-P12_Compressed.pdf21 Dec 2023
Declaration in FORM BFile: 2 Form_B_ Affidavit cum Declaration_Laxmi Nagar_12122023_P1-P3.pdf20 Dec 2023
Building plan approvalFile: IOD_CONFARE HEIGHTS_Compressed.pdf28 Nov 2023
Building plan approvalFile: IOD OF CONATRE HEIGHTS_Compressed.pdf28 Nov 2023
Building Plan Approval (IOD)File: IOD_CONFARE HEIGHTS_Compressed.pdf28 Nov 2023
Building Plan Approval (IOD)File: IOD OF CONATRE HEIGHTS_Compressed.pdf28 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: CC Of Confare_21 and 22 Upper Floor.pdf28 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: CC_CONTARE_34TH UPPER FLOOR.pdf28 Nov 2023

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered late
ProjectLocationFlatsStatusPromisedDelivered
PRABHAT CHS LTD - Phase IBLDG NO 20 SHASTRI NAGAR GOREGAON WEST MUMBAI 400104101CompletedFeb 2017Late, May 2017
VASUNDHARA CHS LTD - Phase I Wing A and BBldg No 6 Road No 1 Shastri Nagar Goregaon west Mumbai - 400 10480CompletedApr 2015Late, Jun 2015
ROHINI CHS LTDBLDG NO 10 JN OF RD NO 1 AND LINK ROAD SHASTRI NAGAR GOREGAON WEST MUMBAI 40010449CompletedDec 2010Late, Feb 2011
KAPIL VASTU CHS LTDBLDG NO 4 SHASTRI NAGAR NR SIDDHARTH HOSPITAL GOREGAON WEST MUMBAI 400 10442CompletedNov 2009Late, Jan 2010
DIVYA JYOTI CHS LTDBLDG NO. 25 SHASTRI NAGAR GOREGAON WEST MUMBAI 40010464CompletedJan 2007Late, Mar 2007

How this compares with Mumbai Suburban

66%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 36 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Laxmi Nagar on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Goregaon West6,700+ in Mumbai Suburban

2 kmLaxmi NagarCompleted 126Lapsed / revoked 57Other 114Dot size: filed unitsN

Filed coordinates, straight-line distance. 297 registered projects within 2 km.

Builder: RELIABLE CONSTRUCTIONS

RELIABLE CONSTRUCTIONS has 4 registrations on MahaRERA, including VASUNDHARA CHS LTD - Phase II - A and B Wing and Laxmi Nagar. Its filings disclose 6 earlier MahaRERA projects: declares 1 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Laxmi Nagar is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Laxmi Nagar?

The registered promoter entity is RELIABLE CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Laxmi Nagar?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Laxmi Nagar?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Laxmi Nagar?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Laxmi Nagar?

The professionals named in the filing: Architect: T N Hasan of Punar Vikas Vastushastra; Engineer: Siddique Sunasara of Frame Design; Chartered Accountant: H.V. DAVDA & Co.; Chartered Accountant: Bhavesh C Vithlani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Laxmi Nagar?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Laxmi Nagar. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Laxmi Nagar to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.