RELIABLE CONSTRUCTIONS: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

RELIABLE CONSTRUCTIONS has 4 registrations in this build, including VASUNDHARA CHS LTD - Phase II - A and B Wing and Laxmi Nagar. Its filings disclose 6 earlier MahaRERA projects: 1 of 6 past projects completed on time.

4Registrations in this build
6Past projects disclosed
+2 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
VASUNDHARA CHS LTD - Phase II - A and B WingMumbai Suburban, Maharashtra--Completed
Laxmi NagarMumbai Suburban, Maharashtra30466%Registered
SHASTRI NAGAR PRABHAT CHSL PHASE II A AND B WINGMumbai Suburban, Maharashtra2580%Registration lapsed
ANANDI MALHARPune, Maharashtra3811%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
DIVYA JYOTI CHS LTD
31 Jan 200715 Mar 2007+1 months
KAPIL VASTU CHS LTD
30 Nov 200920 Jan 2010+2 months
ROHINI CHS LTD
25 Dec 201028 Feb 2011+2 months
VASUNDHARA CHS LTD - Phase I Wing A and B
30 Apr 201530 Jun 2015+2 months
PRABHAT CHS LTD - Phase I
28 Feb 201731 May 2017+3 months
LALBAG PRESTIGE BUILDING B
P52100010952
30 Dec 202115 Jun 2021On time

Frequently asked questions

How do I verify RELIABLE CONSTRUCTIONS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with RELIABLE CONSTRUCTIONS?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.