Home / Browse projects / Pune, Maharashtra / LAVENTANA PHASE I

Registration lapsed No litigation declared Residential / Group Housing project

LAVENTANA PHASE I

By LAVENTANA LLP

RG-MH-24706 · RERA P52100009383 · Last updated on MahaRERA portal: 21 Apr 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 55 months past the filed date
  • 6 complaints at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2022Possession promised55 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
6Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

LAVENTANA PHASE I is a Residential / Group Housing project by LAVENTANA LLP in Pune, Maharashtra, registered with MahaRERA as P52100009383 on 22 Aug 2017. Possession was promised by 30 Mar 2022 and is now 55 months past that date. The completion date has moved by 36 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameLAVENTANA PHASE I
  • TypeResidential / Group Housing
  • Location
    • NIBM Post Office Road
    • Kondhwa
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100009383
  • ReraGenie IDRG-MH-24706

Builder

  • NameLAVENTANA LLP
  • Entity typePartnership
  • PartnerRAJESHKUMAR NAUPATLAL SAKLA
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

55 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toMar 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion30 Mar 2022
  • Revised completionRevised to 30 Mar 2022 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LAVENTANANA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

LAVENTANA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 21 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes40%
Street LightingYes40%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes10%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes60%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes10%
Open ParkingNoNot applicable
Swimming PoolNoNot applicable

Parking filed96

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots96
Closed/Covered96

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,284 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5700.69
Proposed, not sanctioned5,701 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHADKI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR RAMESH TEPAN
EngineerSTURDCOM CONSULTANTS
PartnerRole in project
LAVENTANA LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005440Mar 2019 → Mar 2021

Reason as filed by the promoterDue delay in the approvals from municipal corporation, delay of payments from customers and hence we are unable to complete the project in the prescribed extended date for completion, we would further request you to grant an extension until 31sI March 2021.

EXT52100001631Mar 2019 → Mar 2021

Reason as filed by the promoterDelay has occurred because of delay in sanction of plans

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC005000000106392Mr. Mitul Narendrakumar ModiSiddhivinayak Kundan Rathod Associates07/02/2022
CC005000000106445Mr. Kirtan Narendrakumar ModiSiddhivinayak Kundan Rathod Associates07/02/2022
CC005000000310331LAVENTANA LLPMrs. MuneerahMalik Merchant and Mr.Malik Nuruddin Merchant13/02/2024
CC005000000310341LAVENTANA LLPMrs. Daulat Nurrudin Merchant and Mr. Nadir Nurruddin Merchant13/02/2024
CC005000000381064Daulat Nuruddin MerchantSiddhivinayak-Kundan Rathod Associates21/06/2024
CC005000000471155Malik Nuruddin MerchantSiddhivinayak-Kundan Rathod Associate21/06/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Oct 2022

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Laventana.pdf21 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Laventana Phase 1 - Form 1 - Mar 2021.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 1 - Form 1 - Mar2022.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Laventana Form 1 - 30-09-2021.pdf26 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Laventana Form 1 - 31-12-2021.pdf26 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 31-03-2022.pdf25 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Laventana Phase 1_31st March 2022_8_11zon.pdf30 Dec 2022
Disclosure of sold/ booked inventoryFile: Sold and Unsold_Laventana Phase 1_30-09-2022_Compressed.pdf10 Oct 2022
Certificates of CA (Form 3)File: Form 3-Laventana Phase 1_02-07-2021_11zon.pdf7 Oct 2022
Certificates of CA (Form 3)File: Form 3-Laventana Phase 1_07-10-2021_11zon.pdf7 Oct 2022
Certificates of CA (Form 3)File: Form 3-Laventana Phase 1_06-01-2022_11zon.pdf7 Oct 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: I Part Completion.PDF4 Oct 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part II Completion 18-01-2022.PDF4 Oct 2022
Disclosure of sold/ booked inventoryFile: Laventana Phase 1 Sold Unsold units Dec 2021.pdf26 Jul 2022
Disclosure of sold/ booked inventoryFile: Laventana Phase 1 Sold Unsold units March 2022.pdf26 Jul 2022
Disclosure of sold/ booked inventoryFile: Laventana Phase 1 Sold Unsold units June 2022.pdf26 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate Laventana Phase 1 Q1 2021_Compressed.pdf11 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate Laventana Phase 1 Q2 2021_Compressed.pdf11 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate Laventana Phase 1 Q3 2021_Compressed.pdf11 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Laventa Phase - 1 FY 2020-21.pdf5 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Laventana Phase I 30 09 2021.PDF9 Oct 2021
Disclosure of sold/ booked inventoryFile: Laventana Phase I Sold Unsold 30 09 2021.PDF9 Oct 2021
Disclosure of sold/ booked inventoryFile: Laventana Phase I Sold Unsold 30 09 2021.PDF9 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Laventana Phase 1.PDF17 Sep 2021
Disclosure of sold/ booked inventoryFile: LAVENTANA 1 SOLD UNSOLD.PDF17 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Laventana Phase I 31 03 2021.PDF14 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Laventana Phase I 30 06 2021.PDF14 Sep 2021
Declaration about Commencement CertificateFile: Decl about commencement Laventana Phase I 31 03 2021.PDF13 Sep 2021
Declaration about Commencement CertificateFile: Decl about commencement Laventana Phase I 30 06 2021.PDF13 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Siddhivinayak Phase 1.pdf31 Mar 2021
Certificates of CA (Form 5)File: FORM 5 - Laventana.pdf2 Oct 2019
Certificates of CA (Form 5)File: Siddhivinayak.pdf15 Oct 2018
Details of encumbrancesFile: Encumbrance Letter La Ventana.pdf11 Jan 2018
Building plan approvalFile: Layout Copy Colour.pdf31 Jul 2017
Layout approvalFile: Layout Copy Colour.pdf31 Jul 2017
PAN CardFile: PAN LAVENTANA.pdf31 Jul 2017
Copy of the legal title reportFile: legal title report.pdf31 Jul 2017
Details of encumbrancesFile: Encumbrances Letter pdf.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Copy Colour.pdf31 Jul 2017
Building Plan Approval (IOD)File: Layout Copy Colour.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC La Ventana.pdf31 Jul 2017
Declaration in FORM BFile: declaration of Promoter.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect cert laventana.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer laventna.pdf31 Jul 2017
Certificates of CA (Form 3)File: ca laventna.pdf31 Jul 2017
Proforma of Allotment letterFile: DECLARATION for agreement for sale laventana.pdf31 Jul 2017
Proforma of Allotment letterFile: Allotment la ventana.pdf31 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LAVENTANA PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kondhwa13,700+ in Pune

2 kmLAVENTANA PHASE ICompleted 55Lapsed / revoked 24Other 86Dot size: filed unitsN

Filed coordinates, straight-line distance. 165 registered projects within 2 km.

Builder: LAVENTANA LLP

LAVENTANA LLP has 2 registrations on MahaRERA, including LAVENTANA PHASE I and La Ventana Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that LAVENTANA PHASE I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if LAVENTANA PHASE I is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LAVENTANA PHASE I?

The registered promoter entity is LAVENTANA LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LAVENTANA PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LAVENTANA PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for LAVENTANA PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LAVENTANA PHASE I?

The professionals named in the filing: Architect: AR RAMESH TEPAN; Engineer: STURDCOM CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAVENTANA PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAVENTANA PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAVENTANA PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.