ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / LAKHANI ROYALE

Completed No litigation declared Residential / Group Housing project

LAKHANI ROYALE

By LAKHANI BUILDERS PVT LTD

RG-MH-70992 · RERA P52000014323 · Last updated on MahaRERA portal: 9 Sep 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 10 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Aug 2023Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

LAKHANI ROYALE is a Residential / Group Housing project by LAKHANI BUILDERS PVT LTD in Raigarh, Maharashtra, registered with MahaRERA as P52000014323 on 23 Nov 2017. The registration is recorded completed; possession was promised by 28 Aug 2023.

At a glance

Project

  • NameLAKHANI ROYALE
  • TypeResidential / Group Housing
  • Location
    • 11 M WIDE ROAD
    • ULWE
    • Ulawe
    • Panvel
    • Raigarh
    • 400707
  • Pincode400707
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000014323
  • ReraGenie IDRG-MH-70992

Builder

  • NameLAKHANI BUILDERS PVT LTD
  • Entity typeCompany
  • Managing DirectorVISHANDAS SATRAMDAS LAKHANI
  • Other registrations10 more →
  • Completed4 of 11
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects10 →

Key dates

this monthRegisteredNov 2017PromisedAug 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Nov 2017
  • Promised completion28 Aug 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed99 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LAKHANI ROYALENA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

LAKHANI ROYALE: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered22
Open Space2

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,650 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
S R K ASSOCIATESNavi Mumbai (M Corp.)Thane

Approvals and building plan

Permissible FSI2475.0
Proposed, not sanctioned2,475 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor Shubham Palace Main Road Sector 15 Kopar Khairane Navi Mumbai 400709

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAUL PATEL ATCHITECTS
EngineerMAHIMTURA CONSULTANTS PVT LTD.
PartnerRole in project
LAKHANI BUILDERS PVT LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Nov 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Nov 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Nov 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Aug 2023

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate - Royale - June 2023.pdf9 Sep 2023
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 07 09 23.pdf7 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 33-18-ULWE RERA (2023 JUNE).pdf25 Aug 2023
Certificates of CA (Form 3)File: Form_3_-_June_2023_-_Royale_compressed.pdf25 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 33-18-ULWE OC.pdf25 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 33-18-ULWE-OC DRG-1.pdf25 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 33-18-ULWE-OC DRG-2_compressed (2).pdf25 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 33-18-ULWE-OC DRG-3.pdf25 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 33-18-ULWE-OC DRG-4.pdf25 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate - Royale - March 2023.pdf24 Aug 2023
Certificates of CA (Form 3)File: Form_3_-_March_2023_-_Royale.pdf22 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 33-18-ULWE RERA (2023 MARCH)_compressed (1).pdf9 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate - Royale - Dec 2022.pdf9 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Royale FY 2021-22.pdf1 Apr 2023
Proforma of Agreement for saleFile: 1 Proforma of Allotment letter.pdf1 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate RERA DEC 22 COMPRESSED.pdf29 Mar 2023
Certificates of CA (Form 3)File: FORM 3 31 12 23.pdf17 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate - Grandeur - Sept 2022.pdf10 Jan 2023
Certificates of CA (Form 3)File: Form 3 RERA Sept 2022 COMP.pdf15 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Lakhani Royale_Form 5_31 03 2021.pdf7 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate Sep 22.pdf20 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA - Royale - March 2022.pdf8 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA - Royale - June 2022.pdf8 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Royale - June 21.pdf22 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Royale - Sept 21.pdf22 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Royale - Dec 21.pdf22 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate dec 21.pdf21 Jul 2022
Certificates of CA (Form 3)File: CA June 21.pdf16 Mar 2022
Certificates of CA (Form 3)File: CA September 21.pdf16 Mar 2022
Certificates of CA (Form 3)File: CA December 21.pdf16 Mar 2022
Certificates of CA (Form 3)File: CA June 21.pdf7 Mar 2022
Certificates of CA (Form 3)File: CA September 21.pdf7 Mar 2022
Certificates of CA (Form 3)File: CA December 21.pdf7 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 73-5-UL RERA (JUNE 2021).pdf26 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 73-5-UL RERA (SEP 2021).pdf26 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Royale form 5 compressed.pdf9 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cert 310321.pdf18 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Royale -Engi certif10012021.pdf6 Jul 2021
Certificates of CA (Form 3)File: Form 3 - Dec 2020 - Royale CA Signed_compressed (1).pdf4 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 33-18 ULWE-31 MARCH 21-Architect Certificate -Compress for RERA.pdf29 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf9 Dec 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf9 Dec 2020
Certificates of CA (Form 3)File: CA Certificate.pdf9 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf29 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf29 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf29 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf29 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf29 Sep 2020
Certificates of CA (Form 3)File: CA Certificate.pdf29 Sep 2020
Certificates of CA (Form 3)File: CA Certificate.pdf29 Sep 2020
Certificates of CA (Form 3)File: CA Certificate.pdf29 Sep 2020
Certificates of CA (Form 3)File: CA Certificate.pdf29 Sep 2020
Certificates of CA (Form 5)File: Royale - Form 5 (2019).pdf7 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf22 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf22 Oct 2019
Certificates of CA (Form 3)File: CA Certificate.pdf22 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf17 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Cerificate.pdf17 Aug 2019
Certificates of CA (Form 3)File: CA Certificate.pdf17 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf7 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Cerificate.pdf7 May 2019
Certificates of CA (Form 3)File: CA Certificate.pdf7 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf1 Feb 2019
Certificates of CA (Form 3)File: CA Certificate.pdf1 Feb 2019
Certificates of CA (Form 5)File: Royale - Form 5.pdf13 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Cerificate.pdf5 Nov 2018
Certificates of CA (Form 3)File: CA Certificate.pdf5 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf3 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Cerificate.pdf3 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Cerificate.pdf21 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf20 Jul 2018
Certificates of CA (Form 3)File: CA Certificate.pdf20 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf24 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Cerificate.pdf24 Apr 2018
Certificates of CA (Form 3)File: CA Certificate - APRIL.pdf24 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf12 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer.pdf12 Feb 2018
Certificates of CA (Form 3)File: CA Certificate.pdf12 Feb 2018
Building plan approvalFile: MYSCAN_20170826_0001.pdf6 Nov 2017
Building plan approvalFile: MYSCAN_20170826_0002.pdf6 Nov 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
WHITE CASTLEULWE NAVI MUMBAI71CompletedFeb 2015Late, Feb 2015
BLUE WAVESULWE NAVI MUMBAI54CompletedJan 2014Late, Jan 2014

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LAKHANI ROYALE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ULWE5,900+ in Raigarh

2 kmLAKHANI ROYALECompleted 20Lapsed / revoked 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: LAKHANI BUILDERS PVT LTD

LAKHANI BUILDERS PVT LTD has 11 registrations on MahaRERA, including SIGNATURE and LA RIVERIA. Its filings disclose 10 earlier MahaRERA projects: declares 4 of 10 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if LAKHANI ROYALE is delayed beyond 28 Aug 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LAKHANI ROYALE?

The registered promoter entity is LAKHANI BUILDERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LAKHANI ROYALE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LAKHANI ROYALE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LAKHANI ROYALE?

The professionals named in the filing: Architect: AUL PATEL ATCHITECTS; Engineer: MAHIMTURA CONSULTANTS PVT LTD.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAKHANI ROYALE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAKHANI ROYALE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAKHANI ROYALE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.