Home / Developers / LAKHANI BUILDERS PVT LTD
LAKHANI BUILDERS PVT LTD: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
LAKHANI BUILDERS PVT LTD has 11 registrations in this build, including SIGNATURE and LA RIVERIA. Its filings disclose 10 earlier MahaRERA projects: 4 of 10 past projects completed on time. Litigation is declared on 2 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| SIGNATURE | Mumbai Suburban, Maharashtra | - | - | Completed |
| LA RIVERIA | Raigarh, Maharashtra | - | - | Completed |
| LAKHANI PANACHE | Pune, Maharashtra | - | - | Registration lapsed |
| LAKHANI SKYWAYS | Raigarh, Maharashtra | - | - | Completed |
| LAKHANI ROYALE | Raigarh, Maharashtra | - | - | Completed |
| LAKHANI GRANDEUR | Raigarh, Maharashtra | 73 | 36% | Registration lapsed |
| EMPIRE HERITAGE | Thane, Maharashtra | 85 | 35% | Registered |
| EMPIRE PRESIDENCY | Thane, Maharashtra | 46 | 50% | Registered |
| COURTYARD | Raigarh, Maharashtra | 84 | 54% | Registered |
| EMPIRE DYNASTY | Thane, Maharashtra | 257 | 16% | Registered |
| LAKHANIS BLISS | Raigarh, Maharashtra | 16 | 0% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| BLUE WAVES | 1 Jan 2014 | 8 Jan 2014 | On time |
| LAKHANI BLUE WAVES | 2 Jan 2014 | 8 Jan 2014 | On time |
| Lakhani Blue Waves | 1 Feb 2014 | 1 Aug 2014 | +6 months |
| LAKHANI WHITE CASTLE | 2 Feb 2015 | 6 Feb 2015 | On time |
| WHITE CASTLE | 2 Feb 2015 | 6 Feb 2015 | On time |
| Lakhani White Castle | 2 Feb 2015 | 2 Jun 2015 | +4 months |
| LAKHANI SIGNATURE | 31 Jul 2018 | 20 Apr 2018 | On time |
| LAKHANI PRESTIGE P52000002781 | 31 Jul 2019 | 30 Jul 2019 | On time |
| SKYWAYS | 31 Jul 2019 | 31 Jul 2019 | On time |
| Lakhanis Royale | 31 Aug 2023 | 31 Aug 2023 | On time |
Frequently asked questions
How do I verify LAKHANI BUILDERS PVT LTD as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with LAKHANI BUILDERS PVT LTD?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make LAKHANI BUILDERS PVT LTD unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.