Kumar Primeview E1
By Kumar Properties & Promoters Private Limited
RG-MH-86924 · RERA P52100052845 · Last updated on MahaRERA portal: 21 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Encumbrance declared on the project land, in favour of Aditya Birla Capital Limited
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kumar Primeview E1 is a Others project by Kumar Properties & Promoters Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100052845 on 5 Oct 2023. Possession is promised by 31 Dec 2028. 194 of the 239 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameKumar Primeview E1
- TypeOthers
- Location
- Hadapsar
- pune
- Haveli
- 411028
- Pincode411028
- RERA no.P52100052845
- ReraGenie IDRG-MH-86924
Builder
- NameKumar Properties & Promoters Private Limited
- Entity typeCompany
- CINU45200PN2013PTC147354
- GSTIN27AAFCK1688N1ZW
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorRajas Vimalkumar Jain
- DirectorNImit Bhagwan Gujarathi
- Other registrations4 more →
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Oct 2023
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed76 files
Current status
Figures as on 21 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building E1 | NA | 30 | 29 | 223 | 16 | 239 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 47%.
Building E1: 52% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 47% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building E1 | NA | Rs 69.25 cr | Rs 41.96 cr |
| - | NA | Rs 15.20 cr | Rs 3.04 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Samir Valimbe |
| Engineer | Abhijeet Shekar |
| Chartered Accountant | Supriya Abhijeet Mundada |
| Chartered Accountant | SPAK & CO. |
| Partner | Role in project |
|---|---|
| Kumar Properties & Promoters Private Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Sep 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Sep 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Sep 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed76
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: KPPPL KPV E1 Form 1.pdf | 21 Apr 2026 |
| Withdrawal Update Form 2File: E1 PrimeView Engineering Certificate.pdf | 21 Apr 2026 |
| Withdrawal Update Form 3File: KPPPL KPV E1 Form 3_compressed.pdf | 21 Apr 2026 |
| Form 5 (FY 2024-2025)File: KPPPL KPV E1.pdf | 7 Feb 2026 |
| Withdrawal Update Form 1File: Primeview E1 Arch Certificate.pdf | 23 Jan 2026 |
| Withdrawal Update Form 2File: E1 Pebble Park Engineers Certificate.pdf | 23 Jan 2026 |
| Withdrawal Update Form 3File: Primeview E1 CA Certificate_compressed.pdf | 23 Jan 2026 |
| Form 5 (FY 2023-2024)File: Form 5 - Kumar PrimeView E1 - 2023-24.pdf | 8 Jan 2026 |
| Withdrawal Update Form 1File: Primeview E1.PDF | 7 Nov 2025 |
| Withdrawal Update Form 2File: E1 Pebble Park Engineeru0027s Certificate.pdf | 7 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 Prime View E1_Sep 25_RERA Site_Signed_compressed.pdf | 7 Nov 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kumar Primeview E1.pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kumar Primeview E1 Bldg.PDF | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E1 Pebble Park Engineer's Certificate.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: KUMAR PRIMEVIEW - E1.PDF | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Primeview E1 Bldg.PDF | 15 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kumar Primeview E1_compressed.pdf | 15 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E1 Engineers Certificate.pdf | 15 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: KUMAR PRIMEVIEW - E1.PDF | 15 Jan 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrances - Primeview E1.pdf | 22 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Kumar Primeview E1_compressed.pdf | 22 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrances - Primeview E1.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Primeview E1 Bldg.PDF | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kumar Primeview E1.pdf | 20 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Kumar Primeview - E1.PDF | 20 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kumar Primeview E1.PDF | 26 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance - Kumar Primeview E1.pdf | 23 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance - Kumar Primeview E1.pdf | 23 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kumar Primeview E1.pdf | 15 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kumar PrimeView E1.pdf | 15 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold inventory - Kumar Primeview E1.pdf | 15 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Kumar Primeview E1 - 2023-24.pdf | 7 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Kumar PrimeView E1 - 2023-24.pdf | 7 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kumar PrimeView E 1.pdf | 12 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kumar PrimeView E 1.pdf | 8 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kumar PrimeView E 1.pdf | 8 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold - PrimeView E1.pdf | 8 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - PrimeView E1.pdf | 19 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kumar PrimeView E1.pdf | 18 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E1_Pebble_Park_Primeview_Engineer's Certificate.pdf | 18 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - PrimeView E1.pdf | 18 Jan 2024 |
| Other - TechnicalFile: Declaration - Area Confirmation in Title Report E1.PDF | 18 Sep 2023 |
| Other - TechnicalFile: Form 1 E Kumar Prime view.pdf | 5 Sep 2023 |
| Other - TechnicalFile: Form 1 E Kumar Prime view.pdf | 5 Sep 2023 |
| Layout approvalFile: Main Layout compressed.pdf | 4 Sep 2023 |
| Building plan approvalFile: E1 and E2 ground floor plan.pdf | 4 Sep 2023 |
| Building plan approvalFile: E1 E2 E3 vertical floor.pdf | 4 Sep 2023 |
| Building plan approvalFile: E1 Parking Layout.pdf | 4 Sep 2023 |
| Building plan approvalFile: E1 plan.pdf | 4 Sep 2023 |
| Building plan approvalFile: E1 Vertical.pdf | 4 Sep 2023 |
| Building plan approvalFile: E11.pdf | 4 Sep 2023 |
| PAN CardFile: Companyy PAN.pdf | 4 Sep 2023 |
| Copy of the legal title reportFile: Legal Search Report.PDF | 4 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: No Encumbrance Finance.pdf | 4 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: No Encumbrance Legal.pdf | 4 Sep 2023 |
| Details of encumbrances concerned to LegalFile: No Encumbrance Finance.pdf | 4 Sep 2023 |
| Details of encumbrances concerned to LegalFile: No Encumbrance Legal.pdf | 4 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: Main Layout compressed.pdf | 4 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: E1 and E2 ground floor plan.pdf | 4 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: E1 E2 E3 vertical floor.pdf | 4 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: E1 Parking Layout.pdf | 4 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: E1 plan.pdf | 4 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: E1 Vertical.pdf | 4 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: E11.pdf | 4 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 4 Sep 2023 |
| Declaration about Commencement CertificateFile: Declaration Form D Commencement Certificate E1.PDF | 4 Sep 2023 |
| Declaration in FORM BFile: Form B.pdf | 4 Sep 2023 |
| CERSAI detailsFile: CERSAI Declaration.PDF | 4 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kumar Primeview E1.pdf | 4 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate org Director.pdf | 4 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate org Co director.pdf | 4 Sep 2023 |
| Proforma of Allotment letterFile: Allotment letter E1.pdf | 4 Sep 2023 |
| Proforma of Agreement for saleFile: Agreement to Sale - Final - Kumar PrimeView final.pdf | 4 Sep 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account.pdf | 4 Sep 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment letter E1.pdf | 4 Sep 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation ATS E1.pdf | 4 Sep 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| KUMAR PEBBLE PARK JOY 1 - C1P52100048543 | HADAPSAR, Pune | 56 | Jan 2023 | Ongoing | Dec 2026 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations, which the RERA portal never shows together
- All 76 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Kumar Primeview E1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near pune13,700+ in Pune
Amanora Arbano Towers 73,74,75 and 76
City Corporation Limited
Astrana
Dilip Baburao Tupe
Leisure Town Phase 1
Sai Proviso Homes
ARV Newtown Phase III
Vedant Infracon
Kumar Parc Residences - A2
Kumar Properties Infratech Developers Pvt
Kumar Parc residences - A1
Kumar Properties Infratech Developers Pvt
Builder: Kumar Properties & Promoters Private Limited
Kumar Properties & Promoters Private Limited has 5 registrations on MahaRERA, including Kumar Primeview E1 and Kumar Primeview E2. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Kumar Primeview E1 is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kumar Primeview E1?
The registered promoter entity is Kumar Properties & Promoters Private Limited, a company as per the filing. Its CIN U45200PN2013PTC147354 and GSTIN 27AAFCK1688N1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kumar Primeview E1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kumar Primeview E1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kumar Primeview E1?
The professionals named in the filing: Architect: Samir Valimbe; Engineer: Abhijeet Shekar; Chartered Accountant: Supriya Abhijeet Mundada; Chartered Accountant: SPAK & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kumar Primeview E1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.