RG-MH-48445 · RERA P51800003506 · Last updated on MahaRERA portal: 12 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 3 complaints at MahaRERA
- Completion date moved by 66 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KULDEEP-ISHCHHAYA CHS LTD is a Others project by TRIDEV REALTY AND CONSTRUCTION PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003506 on 5 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 66 months from the original filing. 33 of the 69 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameKULDEEP-ISHCHHAYA CHS LTD
- TypeOthers
- Location
- N S ROAD
- MULUND WEST
- Kurla
- Mumbai Suburban
- 400080
- Pincode400080
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003506
- ReraGenie IDRG-MH-48445
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed291 files
Current status
Figures as on 12 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KULDEEP-ISHCHHAYA CHS LTD | NA | 19 | 15 | 69 | 0 | 69 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
KULDEEP-ISHCHHAYA CHS LTD: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 12 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 95% |
| Electrical meter room, sub-station, receiving station | Yes | 95% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed66
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| KULDEEP-ISHCHHAYA CHS LTD | NA | Rs 14.10 cr | Rs 9.00 cr |
| - | NA | Rs 1.95 cr | Rs 1.45 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR SUNIL DEOLE |
| Architect | Sunil R Deole |
| Engineer | ADVANCE CREATIVE DESIGN CONSULTANCY Rajendra Paranjpe |
| Chartered Accountant | Himmat Shethia & Associates |
| Chartered Accountant | Malay Furia |
| Partner | Role in project |
|---|---|
| TRIDEV REALTY AND CONSTRUCTION PVT LTD | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRCC Work of completion of the building is nearing completion and the same is evident as per latest Form 1 dated 02-01-2023. Need extension for completing the finishing work and obtaining OC for the proposed building.
Reason as filed by the promoterWe have Real Estate project registered with MahaRERA authority with name “KULDEEPISHCHHAYA CHS LTD” vide Certificate No. P51800003506. Due date for the completion of the project as estimated at the time of the registration was 31/12/2020. Thereafter due to Notification/Order No 13 and 14 dated 2nd April 2020 and 18th May 2020 respectively issued by MahaRERA an extension of six months received and date of completion became 30th June 2021. Construction Status of the Project: The project is registered with one building consisting 15 Floors out of which construction of 12 Floors are completed & 3
Reason as filed by the promoterDeclaration letter with legitimate reasons for grant of extension required/sought for the concerned project along-with the justification of the completion of the balance work in Tabular Chart stating Activity/Task having it’s start date and proposed end date to be completed within stipulated proposed extended time-line is attached. Duly stamped and signed on each page application with more that 51% allottee’s consent on the letterhead is enclosed. Form 1 (Architect Certificate), Form 2 (Engineer’s Certificate) and Form 3 (Chartered Accountant’s Certificate) is duly uploaded till the latest qua
Reason as filed by the promoterMore than 95% of the work is completed as per latest Architect Certificate dated 31-12-2025 for the quarter ended 31-Dec-2025. For completion of the balance work viz. Car Lift, Stack Parking, Part Portion of Paving work, Installation of Electric Meters and relevant compliances for obtaining OC of the building, we seek extension of the project completion date up-to 31-Dec-2026.
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000012683 | URVASHI GOVARDHANDAS SHAH | TRIDEV REALTY AND CONTRUCTIONS | 30/12/2017 |
| CC006000000396365 | JAGANNATH YADAV | M/S. TRIDEV REALTY & CONSTRUCTIONS PVT. LTD. | 24/06/2023 |
| CC006000000396366 | RITESH YADAV | M/S. TRIDEV REALTY & CONSTRUCTIONS PVT. LTD. | 24/06/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Aug 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Mar 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed291
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 291 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1_Kuldeep_31-12-2024.pdf | 12 Mar 2026 |
| Form 2File: Form 2_31-12-24_Kuldeep.pdf | 12 Mar 2026 |
| Form 3File: Format_Form 3 - CA Certificate_31-12-2024_compressed.pdf | 12 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan_Tridev Kuldeep Disclosure 31-12-2024.pdf | 12 Mar 2026 |
| Form 1File: Form 1_Kuldeep_31-03-2025.pdf | 12 Mar 2026 |
| Form 2File: Form 2_Kuldeep 31-03-25.pdf | 12 Mar 2026 |
| Form 3File: Kuldeep_Form -3_31-03 -2025.pdf | 12 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan_Tridev Kuldeep Disclosure 31-03-2025.pdf | 12 Mar 2026 |
| Form 1File: 1 Form 1 Kuldeep 31-03-2021.pdf | 11 Mar 2026 |
| Form 2File: Form-2 31-03-2021 Kuldeep Niwas_compressed.pdf | 11 Mar 2026 |
| Form 3File: Kuldeep Form 3 31-03-2021.PDF | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan_Disclosure of Sold Inventory Kuldeep Niwas.PDF | 11 Mar 2026 |
| Form 1File: 2 Form 1 Kuldeep 30-06-2021.pdf | 11 Mar 2026 |
| Form 2File: Form-2 30-06-2021 Kuldeep Niwas_compressed.pdf | 11 Mar 2026 |
| Form 3File: Kuldeep Form 3 30-06-2021.PDF | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan_Disclosure of Sold Inventory Kuldeep Niwas.PDF | 11 Mar 2026 |
| Form 1File: Form-1 31-12-2021.PDF | 11 Mar 2026 |
| Form 2File: Form 2_31-12-2021 Kuldeep.PDF | 11 Mar 2026 |
| Form 3File: Form 3 Kuldeep 31-12-2021.PDF | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan_Tridev Kuldeep Disclosure Of Sold Inventories.PDF | 11 Mar 2026 |
| Form 1File: Form-1 31-03-2022.PDF | 11 Mar 2026 |
| Form 2File: Form 2_31-03-22 Kuldeep.PDF | 11 Mar 2026 |
| Form 3File: Form 3 Kuldeep 31-03-2022.PDF | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan_Tridev Kuldeep Disclosure Of Sold Inventories.PDF | 11 Mar 2026 |
| Form 1File: Form-1 30-06-2022.PDF | 11 Mar 2026 |
| Form 2File: Form 2_30-06-2022 Kuldeep.PDF | 11 Mar 2026 |
| Form 3File: Form 3 30-06-2022 Kuldeep.PDF | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan_Tridev Kuldeep Disclosure Of Sold Inventories.PDF | 11 Mar 2026 |
| Form 1File: Form-1 30-09-2022.PDF | 11 Mar 2026 |
| Form 2File: Form 2_30-09-2022 Kuldeep.PDF | 11 Mar 2026 |
| Form 3File: Form 3 30-09-2022 Kuldeep.PDF | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan_Tridev Kuldeep Disclosure Of Sold Inventories.PDF | 11 Mar 2026 |
| Form 1File: Form 1 _31-03-2023.pdf | 11 Mar 2026 |
| Form 2File: Form 2 31-03-2023_Kuldeep.pdf | 11 Mar 2026 |
| Form 3File: Form 3_31-03-2023_Kuldeep_compressed.pdf | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan Tridev Kuldeep Disclosure of Sold Inventories.pdf | 11 Mar 2026 |
| Form 1File: Form 1 _30-06-2023.pdf | 11 Mar 2026 |
| Form 2File: Form 2 30-06-2023_Kuldeep.pdf | 11 Mar 2026 |
| Form 3File: Form 3 30-06-2023_Kuldeep_compressed.pdf | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan Tridev Kuldeep Disclosure of Sold Inventories.pdf | 11 Mar 2026 |
| Form 1File: Form 1 _30-09-2023.pdf | 11 Mar 2026 |
| Form 2File: Form 2 30-09-2023_Kuldeep.pdf | 11 Mar 2026 |
| Form 3File: Form 3 30-09-2023_Kuldeep_compressed.pdf | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan Tridev Kuldeep Disclosure of Sold Inventories.pdf | 11 Mar 2026 |
| Form 1File: Form 1 _30-12-2023.pdf | 11 Mar 2026 |
| Form 2File: Form 2 31-12-2023_Kuldeep.pdf | 11 Mar 2026 |
| Form 3File: Form 3 31-12-2023_Kuldeep_compressed.pdf | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan Tridev Kuldeep Disclosure of Sold Inventories.pdf | 11 Mar 2026 |
| Form 1File: Form 1 _30-03-2024.pdf | 11 Mar 2026 |
| Form 2File: Form 2 31-03-2024_Kuldeep.pdf | 11 Mar 2026 |
| Form 3File: Form 3 31-03-2024_Kuldeep_compressed.pdf | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan Tridev Kuldeep Disclosure of Sold Inventories.pdf | 11 Mar 2026 |
| Form 1File: Form 1_30-06-2024.pdf | 11 Mar 2026 |
| Form 2File: Form 2 30-06-2024_Kuldeep.pdf | 11 Mar 2026 |
| Form 3File: Form 3 30-06-2024_Kuldeep_compressed.pdf | 11 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Scan Tridev Kuldeep Disclosure of Sold Inventories.pdf | 11 Mar 2026 |
| Form 5 (FY 2018-2019)File: Scan_Form No 5 Kuldeep 18-19.pdf | 11 Mar 2026 |
| Form 5 (FY 2019-2020)File: Scan_Form 5 Kuldeep 2019-2020.pdf | 11 Mar 2026 |
| Form 5 (FY 2020-2021)File: Scan_Form No 5 Kuldeep 20-21.pdf | 11 Mar 2026 |
| Form 5 (FY 2021-2022)File: Scan_Form 5 - Kuldeep FY 2021-2022.PDF | 11 Mar 2026 |
| Form 5 (FY 2022-2023)File: Scan_Form 5 FY 2022-2023_Kuldeep.pdf | 11 Mar 2026 |
| Form 5 (FY 2023-2024)File: Scan_Form 5 FY 2023-2024_Kuldeep.pdf | 11 Mar 2026 |
| Form 5 (FY 2024-2025)File: Scan_Form 5 - Kuldeep FY 2024-2025.pdf | 11 Mar 2026 |
| Commencement certificateFile: Full CC Kuldeep.pdf | 7 Mar 2026 |
| Withdrawal Update Form 1File: Scan_Form 1_Kuldeep_30-09-2025.pdf | 7 Mar 2026 |
| Withdrawal Update Form 1File: Scan_Form 1_Kuldeep_31-12-2025.pdf | 7 Mar 2026 |
| Withdrawal Update Form 2File: Scan_Form 2_Kuldeep_30-09-2025.pdf | 7 Mar 2026 |
| Withdrawal Update Form 2File: Scan_Form 2_Kuldeep_31-12-2025.pdf | 7 Mar 2026 |
| Withdrawal Update Form 3File: Kuldeep_Form -3_30-09-2025.pdf | 7 Mar 2026 |
| Withdrawal Update Form 3File: Kuldeep_Form -3_31-12 -2025.pdf | 7 Mar 2026 |
| Form 1File: Form 1 30-06-2020.pdf | 27 Feb 2026 |
| Form 2File: Form 2 30-06-2020.pdf | 27 Feb 2026 |
| Form 3File: Form 3 30-06-2020.PDF | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Kuldeep declaration of Sold inventories.PDF | 27 Feb 2026 |
| Form 1File: Kuldeep Form 1 31-12-2020.pdf | 27 Feb 2026 |
| Form 2File: Form 2 31-12-2020.pdf | 27 Feb 2026 |
| Form 3File: Form 3 31122020.PDF | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Kuldeep declaration of Sold inventories.PDF | 27 Feb 2026 |
| Form 1File: Final Form - 1_30-09-2017.pdf | 27 Feb 2026 |
| Form 2File: Final Form - 2 sep17.pdf | 27 Feb 2026 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| NANDJA CHS LTD | Nandja CHS ltd BPS Rd no 2 Mulund west Mumbai 400080 | 15 | Completed | Nov 2015 | Nov 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 291 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep KULDEEP-ISHCHHAYA CHS LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MULUND WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 334 registered projects within 2 km.
Eternia Towers A to D
Oberoi Constructions Limited
Bellanza Phase 1 - Wing A, B, C at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Atmosphere O2
Atmosphere Realty Pvt Ltd
Bellanza Phase 2 - Wing D, E, F at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Forest Hills Ph 1 at The Prestige City
PRESTIGE MULUND REALTY PRIVATE LIMITED
Kalpataru Elitus
Arimas Real Estate Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: TRIDEV REALTY AND CONSTRUCTION PVT LTD
TRIDEV REALTY AND CONSTRUCTION PVT LTD has 3 registrations on MahaRERA, including BALAJI APARTMENT and TRIDEV ANUBHAV. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if KULDEEP-ISHCHHAYA CHS LTD is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KULDEEP-ISHCHHAYA CHS LTD?
The registered promoter entity is TRIDEV REALTY AND CONSTRUCTION PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KULDEEP-ISHCHHAYA CHS LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against KULDEEP-ISHCHHAYA CHS LTD?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for KULDEEP-ISHCHHAYA CHS LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KULDEEP-ISHCHHAYA CHS LTD?
The professionals named in the filing: Architect: MR SUNIL DEOLE; Architect: Sunil R Deole; Engineer: ADVANCE CREATIVE DESIGN CONSULTANCY Rajendra Paranjpe; Chartered Accountant: Himmat Shethia & Associates; Chartered Accountant: Malay Furia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KULDEEP-ISHCHHAYA CHS LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback