Home / Browse projects / Pune, Maharashtra / KUL Utsav Phase I -Building G

Completed No litigation declared Residential / Group Housing project

KUL Utsav Phase I -Building G

By Kumar Builders

RG-MH-20214 · RERA P52100003489 · Last updated on MahaRERA portal: 4 Sep 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 49 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
2 of 11Construction stages donefurthest along: Slabs of Super Structure, 85%
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

KUL Utsav Phase I -Building G is a Residential / Group Housing project by Kumar Builders in Pune, Maharashtra, registered with MahaRERA as P52100003489 on 5 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2023. The completion date has moved by 49 months from the original filing.

At a glance

Project

  • NameKUL Utsav Phase I -Building G
  • TypeResidential / Group Housing
  • Location
    • kondhwa BK
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003489
  • ReraGenie IDRG-MH-20214

Builder

  • NameKumar Builders
  • Entity typePartnership
  • Other registrations6 more →
  • Completed5 of 7
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseMay 2019Revised toJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 15 May 2019)
  • Buildings1 building record
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Utsav Phase I -Building GNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.

Utsav Phase I -Building G: 49% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)100%
Plinth70%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises37%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 4 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes10%
Street LightingYes0%
Community BuildingsYes80%
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes20%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes5%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered51

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area652 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3797.38
Proposed, not sanctioned3,797 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchA Shangrila Gardens Bund Garden Road Pune 411001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAniruddha Vaidya and Associates
EngineerJW Consultants LLP
PartnerRole in project
Kumar Builders-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009390May 2019 → Mar 2022

Reason as filed by the promoterApplicant submits that now the construction of this project is at the stage of completion. The external structure of the building is ready. The brickwork, internal and external plastering and internal POP are more than 60 % completed. The work remaining is finishing tasks of wall plastering, tiles, plumbing, sanitary fitting etc. Applicant submits due to COVID 19 pandemic lockdown was declared in Pune in March’2020. As a result the labours working on the site of this Applicant went back to their native places outside Maharashtra. As a result the construction work on the site of the Applicant i

EXT52100012594May 2019 → Jun 2023

Reason as filed by the promoterThe Applicant is requesting for extension upto 30/06/2023 and submits that the following factors have caused the subject delay of 9 months:- • Shortage of certain material in the markets due to the supply chain disruptions and scarcity of materials like metals and semi-conductors • Installation and licence for working of lift is awaited. The application was filed with required fees in Aug’22, however, the licence is still awaited. This has delayed the lift installation completion. • Increase in the materials costs had to lead to stricter payments terms and delivery terms. • The other buildings

EXT52100001775May 2019 → May 2020

Reason as filed by the promoterAppointed RCC contractor constantly have low labour strength, he was unable to achieve milestones, after several instructions given by us. Deployed Labours had low skilled/productivity level; thus we were not getting work quality up to the mark. Therefore we rectify the quality for betterment of the project, in the process of rectification and deployment of skilled workers work is delayed.

Litigation declared1

CaseCourtStatus
404/2014/2014Bombay High CourtPending

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Jul 2023

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Utsav G Registration Cert.pdf4 Sep 2023
Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate Form 4.pdf29 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_Utsav G.pdf26 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Utsav G FORM 5.pdf7 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 LAtest Form Ustav G.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: From5_UtsavG_Mar22.pdf21 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Utsav G.pdf23 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Utsav G.pdf23 Sep 2022
Certificates of CA (Form 3)File: CA Certificate_Ustav G.pdf23 Sep 2022
Other - TechnicalFile: Drainage NOC.pdf6 Sep 2022
Other - TechnicalFile: Drainage Passing.pdf6 Sep 2022
Other - TechnicalFile: Plumber Licence.pdf6 Sep 2022
Other - TechnicalFile: Rain Water Harvesting - Drowing.pdf6 Sep 2022
Other - TechnicalFile: Rain water harvesting - NOC.pdf6 Sep 2022
Other - TechnicalFile: Water Meter NOC.pdf6 Sep 2022
Disclosure of sold/ booked inventoryFile: Disclosure Sold-Booked Inventory .pdf19 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: CC124720 dt27 112020.pdf10 Aug 2021
Declaration about Commencement CertificateFile: Declaration CC.pdf10 Aug 2021
Disclosure of sold/ booked inventoryFile: Utsav-G-RERA-consent-compressed.pdf2 Aug 2021
Disclosure of sold/ booked inventoryFile: KUL Utsav - Extension Request Letter.pdf2 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_KUL_Utsav_G_.pdf26 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality-Cert.pdf26 Jul 2021
Certificates of CA (Form 3)File: Kul Utsav - G Form 3.pdf26 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Kul Utsav G.pdf26 Jul 2021
OtherFile: Representation for extension beyond Covid 19 deadline.pdf13 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: scan.pdf26 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Kul Utsav G Building.pdf18 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate- G Buld Utsav.pdf18 Feb 2019
Certificates of CA (Form 3)File: Kul UtsavG CA1.pdf18 Feb 2019
Certificates of CA (Form 5)File: Kul Utsav G.pdf13 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE_Utsav G.pdf10 May 2018
Declaration in FORM BFile: Utsav G Form B.pdf29 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: kul Utsav Commencement certificate.pdf28 Feb 2018
Copy of the legal title reportFile: Title Certificate for KUL Utsav Building G.pdf30 Jul 2017
Building plan approvalFile: Building Plan for KUL Utsav Building G.pdf29 Jul 2017
Layout approvalFile: KUL UTSAV LAYOUT.PDF29 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate for KUL Utsav Building G.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: KUL UTSAV LAYOUT.PDF29 Jul 2017
Building Plan Approval (IOD)File: Building Plan for KUL Utsav Building G.pdf29 Jul 2017
Declaration in FORM BFile: Declaration in Form B for KUL Utsav Building G.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for KUL Utsav Building G.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate for KUL Utsav Construction of Phase I - Building G.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate for KUL Utsav Building G.pdf29 Jul 2017
Proforma of Allotment letterFile: Appl Allotment and Undertaking for KUL Utsav Building G.pdf29 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Kumar Buena VistaPashan Pune36CompletedMay 2010Mar 2010

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 49 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KUL Utsav Phase I -Building G on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near kondhwa BK13,700+ in Pune

2 kmKUL Utsav Phase I -BuildCompleted 75Lapsed / revoked 45Other 94Dot size: filed unitsN

Filed coordinates, straight-line distance. 214 registered projects within 2 km.

Builder: Kumar Builders

Kumar Builders has 7 registrations on MahaRERA, including KUL Utsav Phase I -Building G and KUL Utsav Phase I -Building F. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KUL Utsav Phase I -Building G is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KUL Utsav Phase I -Building G?

The registered promoter entity is Kumar Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KUL Utsav Phase I -Building G?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KUL Utsav Phase I -Building G?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KUL Utsav Phase I -Building G?

The professionals named in the filing: Architect: Aniruddha Vaidya and Associates; Engineer: JW Consultants LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KUL Utsav Phase I -Building G?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KUL Utsav Phase I -Building G. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KUL Utsav Phase I -Building G to a free account