ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / KRUSHNA KUNJ PARK

Completed No litigation declared Others project

KRUSHNA KUNJ PARK

By Narayan Labhu Sarode

RG-MH-83583 · RERA P51600021740 · Last updated on MahaRERA portal: 21 Jun 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 7 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

KRUSHNA KUNJ PARK is a Others project by Narayan Labhu Sarode in Nashik, Maharashtra, registered with MahaRERA as P51600021740 on 23 Jul 2019. The registration is recorded completed; possession was promised by 30 Dec 2024.

At a glance

Project

  • NameKRUSHNA KUNJ PARK
  • TypeOthers
  • Location
    • NEAR KARGIL CHOWK
    • DATTA NAGAR CHUNCHALE
    • Nashik
    • 422007
  • Pincode422007
  • RERA no.P51600021740
  • ReraGenie IDRG-MH-83583

Builder

  • NameNarayan Labhu Sarode
  • Entity typeIndividual
  • GSTIN27AMCPS2335J1ZX
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations7 more →
  • Completed6 of 8
  • Declared earlier projects8 →

Key dates

this monthRegisteredJul 2019PromisedDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2019
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed24 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KRUSHNA KUNJ PARKNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Jun 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

KRUSHNA KUNJ PARK: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Jun 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered14

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area750 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1512.52
Proposed, not sanctioned1,513 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAJ ARCADE AMBAD LINK ROAD NASHIK

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVINAYAK K PATIL
EngineerROHAN K GHUMRE
EngineerSAGAR S SHAH
EngineerSHIRISH NER
Chartered AccountantNIRAV S SHAH
PartnerRole in project
Narayan Labhu Sarode-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Jul 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jul 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Jun 2021

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf21 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf21 Jun 2021
Certificates of CA (Form 3)File: Form 3.pdf21 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 2019-20.pdf21 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2020-21.pdf21 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf21 Jun 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf21 Jun 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration.pdf21 Jun 2021
OtherFile: CREDAI.pdf20 Dec 2019
Layout approvalFile: Plot Layout.pdf21 Jul 2019
Copy of Layout Approval (in case of layout)File: Plot Layout.pdf21 Jul 2019
Building plan approvalFile: Sanctioned Plan.pdf2 Jul 2019
PAN CardFile: PAN.pdf2 Jul 2019
Copy of the legal title reportFile: Title Report.pdf2 Jul 2019
Details of encumbrancesFile: No Encumbrance.pdf2 Jul 2019
Building Plan Approval (IOD)File: Sanctioned Plan.pdf2 Jul 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf2 Jul 2019
Declaration in FORM BFile: Form B.pdf2 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf2 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf2 Jul 2019
Certificates of CA (Form 3)File: Form 3.pdf2 Jul 2019
Proforma of Allotment letterFile: Allotment Letter.pdf2 Jul 2019
Proforma of Allotment letterFile: Agreement For Sale - Flat.pdf2 Jul 2019
Proforma of Allotment letterFile: Agreement For Sale - Shop.pdf2 Jul 2019

Promoter's earlier projects7

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

7 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Sarode Park Phase 1 - Building No. AP51600055886Behind Mhada Building, Pathardi, Nashik35Apr 2024CompletedDec 2026Apr 2025
Shree Ganesh Row House - BP51600047514Patil Park, Chunchale, Nashik-Nov 2022CompletedDec 2024Apr 2023
GOLDEN PARKP51600027510NEAR DATTA MANDIR STOP, CHUNCHALE, Nashik-Dec 2020CompletedJun 2024Mar 2022
Shree Ganesh Row HouseP51600033841Near Papaya Nursery, Patil Park, Nashik-Mar 2022CompletedDec 2023Jul 2022
Sarode SankulP51600018930CHUNCHALE, Nashik-Dec 2018CompletedDec 2021Jul 2019
VASTU PARKDATTA NAGAR CHUNCHALE NASHIK25-CompletedAug 2020Aug 2018
Ashtvinayak Row-HousesDatta Nagar Chunchale Nashik8-CompletedDec 2017Jun 2017

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KRUSHNA KUNJ PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DATTA NAGAR CHUNCHALE4,100+ in Nashik

Builder: Narayan Labhu Sarode

Narayan Labhu Sarode has 8 registrations on MahaRERA, including Vastu Park and Sarode Sankul. Its filings disclose 8 earlier MahaRERA projects: declares 8 of 8 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if KRUSHNA KUNJ PARK is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRUSHNA KUNJ PARK?

The registered promoter entity is Narayan Labhu Sarode, an individual as per the filing. Its GSTIN 27AMCPS2335J1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRUSHNA KUNJ PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KRUSHNA KUNJ PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRUSHNA KUNJ PARK?

The professionals named in the filing: Architect: VINAYAK K PATIL; Engineer: ROHAN K GHUMRE; Engineer: SAGAR S SHAH; Engineer: SHIRISH NER; Chartered Accountant: NIRAV S SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRUSHNA KUNJ PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRUSHNA KUNJ PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRUSHNA KUNJ PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.