ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / Krishitas Orchard

Registered No litigation declared Others project

Krishitas Orchard

By Krishita Developers LLP

RG-MH-77348 · RERA P51600047474 · Last updated on MahaRERA portal: 19 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Feb 2027Possession promisedmoved 18 months from the original
3 of 11Construction stages donefurthest along: Internal walls, 90%
11 of 13Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 131 documents Report an error

Krishitas Orchard is a Others project by Krishita Developers LLP in Nashik, Maharashtra, registered with MahaRERA as P51600047474 on 2 Nov 2022. Possession is promised by 28 Feb 2027. The completion date has moved by 18 months from the original filing. 2 of the 13 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameKrishitas Orchard
  • TypeOthers
  • Location
    • Holaram Colony
    • Kulkarni Garden
    • Nashik (M Corp.)
    • Nashik
    • 422005
  • Pincode422005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600047474
  • ReraGenie IDRG-MH-77348

Builder

  • NameKrishita Developers LLP
  • Entity typePartnership
  • GSTIN27AAWFK8672N1Z3
  • PartnersAkshay Swapnil Shah, Ashray Milind Shah, Achin Dahyalal Shah

Key dates

this monthRegisteredNov 2022First promiseAug 2025Revised toFeb 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Nov 2022
  • Promised completion28 Feb 2027
  • Revised completionRevised to 28 Feb 2027 (originally 1 Aug 2025)
  • Buildings1 building record
  • Documents filed131 files

Current status

15%2 of 13 units booked
54.8%Work done, per cost certificate

Figures as on 19 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Krishitas OrchardNA659413

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

Krishitas Orchard: 43% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed66

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots66
Closed/Covered23
Open Space43

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area796 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Mar 2026

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI2534.93
Proposed, not sanctioned2,535 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSoham Complex, Patil Lane No 3 and 4 College Road Nashik-422201
Estimated costRs 6.06 cr
Cost incurredRs 3.32 cr
Work done54.79%
BuildingWingEstimatedIncurred
Krishitas OrchardNARs 6.06 crRs 3.32 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRavi Amrutkar
EngineerSachin shah
Chartered AccountantParesh Sabadra
Chartered AccountantRSPH & Associates
Chartered AccountantPratik D Jain
PartnerRole in project
Krishita Developers LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23032620340Aug 2025 → Oct 2026

Reason as filed by the promoter1. We have obtained full occupancy certificate from Nashik Municipal Corporation dated 23/01/2026. 2. The photos of present status of project are enclosed herewith.

P51600047474/WarAug 2025 → Feb 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Sep 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 28 Feb 2027

Documents filed131

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: AR June 25.pdf19 Sep 2026
Withdrawal Update Form 1File: AR June 25.pdf19 Sep 2026
Withdrawal Update Form 1File: Form 1-AR Final .pdf19 Sep 2026
Withdrawal Update Form 1File: Form 1-AR Final .pdf19 Sep 2026
Withdrawal Update Form 2File: Form 2 -ER.pdf19 Sep 2026
Withdrawal Update Form 2File: ER june 25-Final.pdf19 Sep 2026
Withdrawal Update Form 2File: ER june 25-Final.pdf19 Sep 2026
Withdrawal Update Form 2File: ER june 25-Final.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3-CA.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3-CA.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3-CA.pdf19 Sep 2026
Withdrawal Update Form 3File: Form 3-CA.pdf19 Sep 2026
Form 5 (FY 2025-2026)File: RA Report_Krishita 25-26 -Final.pdf21 Aug 2026
Form 2A (FY 2022-2023)File: Form2 A - March 2023.pdf30 Mar 2026
Form 2A (FY 2023-2024)File: Form 2A - March 2024.pdf30 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A - March 2025.pdf30 Mar 2026
Form 2A (FY 2025-2026)File: Form 2A - March 2026.pdf30 Mar 2026
Withdrawal Update Form 1File: AR June 25.pdf17 Mar 2026
Withdrawal Update Form 2File: 2 ER June 2024 Final.pdf17 Mar 2026
Withdrawal Update Form 3File: CA june 25 FINAL.pdf17 Mar 2026
Form 1File: AR SEPT.pdf16 Mar 2026
Form 2File: ER Sept 24.pdf16 Mar 2026
Form 3File: Final CA Sept 24.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure sept.pdf16 Mar 2026
Form 1File: AR - March 25-min.pdf16 Mar 2026
Form 2File: ER - March 25-min.pdf16 Mar 2026
Form 3File: CA certificate final.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - March 25.pdf16 Mar 2026
Form 1File: Architect Certificate.pdf16 Mar 2026
Form 2File: Eng Certificate.pdf16 Mar 2026
Form 3File: Final CA certificate signed.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory.pdf16 Mar 2026
Form 1File: 1 AR CERT Q4 23-24.pdf16 Mar 2026
Form 2File: 2 ER CERT Q4 -23-24.pdf16 Mar 2026
Form 3File: 3 CA Cert Signed Final.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked.pdf16 Mar 2026
Form 1File: 1 AR June 24 Final.pdf16 Mar 2026
Form 2File: 2 ER June 2024 Final.pdf16 Mar 2026
Form 3File: CA Certificate June 24 Final.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Q1 24-25- Krishita Orchard.pdf16 Mar 2026
Form 1File: AR.pdf16 Mar 2026
Form 2File: ER.pdf16 Mar 2026
Form 3File: Krishita CA cert_March 23.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf16 Mar 2026
Form 1File: Ar-Spet-23.pdf16 Mar 2026
Form 2File: ER-Sept-23.pdf16 Mar 2026
Form 3File: CA Certificate-sept23.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure-Sep-23.pdf16 Mar 2026
Form 1File: AR-Dec-23.pdf16 Mar 2026
Form 2File: ER-Dec-23.pdf16 Mar 2026
Form 3File: CA Certificate- Dec23.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure--Dec-23.pdf16 Mar 2026
Form 5 (FY 2022-2023)File: RERA Audit Report-22-23-.pdf17 Feb 2026
Form 5 (FY 2023-2024)File: RERA Audit 23-24.pdf17 Feb 2026
Form 5 (FY 2024-2025)File: RA Report_Krishita 24-25 final.pdf4 Feb 2026
Form 1File: AR - sept 25.pdf30 Dec 2025
Form 2File: ER sept 25.pdf30 Dec 2025
Form 3File: CA sept 25 final.pdf30 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold.pdf30 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR - March 25-min.pdf9 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA - March 25_compressed_11zon.pdf9 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER - March 25-min.pdf9 Jun 2025
Disclosure of sold/ booked inventoryFile: Disclosure - March 25.pdf9 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Dec 24_Krishita.pdf21 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Other - Technical.pdf8 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR certificate.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA certificate signed_compressed.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER certificate.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure.pdf10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR SEPT_compressed.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA Sept 24.pdf4 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Sept 24_compressed.pdf4 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final RA Report_Krishita_23-24.pdf4 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final RA Report_Krishita_23-24.pdf4 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure sept.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 AR June 24 Final.pdf14 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 ER June 2024 Final.pdf14 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate June 24 Final.pdf14 Aug 2024

How this compares with Nashik

15%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 18 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Krishitas Orchard on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kulkarni Garden4,100+ in Nashik

2 kmKrishitas OrchardCompleted 153Lapsed / revoked 34Other 94Dot size: filed unitsN

Filed coordinates, straight-line distance. 281 registered projects within 2 km.

Builder: Krishita Developers LLP

Krishita Developers LLP has 1 registration on MahaRERA, including Krishitas Orchard. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if Krishitas Orchard is delayed beyond 28 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Krishitas Orchard?

The registered promoter entity is Krishita Developers LLP, a partnership as per the filing. Its GSTIN 27AAWFK8672N1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Krishitas Orchard?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Krishitas Orchard?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Krishitas Orchard?

The professionals named in the filing: Architect: Ravi Amrutkar; Engineer: Sachin shah; Chartered Accountant: Paresh Sabadra; Chartered Accountant: RSPH & Associates; Chartered Accountant: Pratik D Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Krishitas Orchard?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Krishitas Orchard. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Krishitas Orchard to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.