Home / Browse projects / Pune, Maharashtra / KINGSTONE AVENUE PH 1

Completed No litigation declared Residential / Group Housing project

KINGSTONE AVENUE PH 1

By Supreme Developers

RG-MH-10411 · RERA P52100001909 · Last updated on MahaRERA portal: 12 May 2021

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
18 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 80%
2Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

KINGSTONE AVENUE PH 1 is a Residential / Group Housing project by Supreme Developers in Pune, Maharashtra, registered with MahaRERA as P52100001909 on 29 Jul 2017. The registration is recorded completed; possession was promised by 31 Dec 2019. The completion date has moved by 12 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameKINGSTONE AVENUE PH 1
  • TypeResidential / Group Housing
  • Location
    • Pimpale Saudagar
    • Haveli
    • Pune
    • 411027
  • Pincode411027
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001909
  • ReraGenie IDRG-MH-10411

Builder

  • NameSupreme Developers
  • Entity typePartnership
  • PartnersKANHAIYALAL HOTCHAND MATANI, SNEHA RAJESH PARIANI, KHEMCHAND UTTAMCHAND BHOJWANI, SAHIL MOTI MILANI
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredJul 2017First promiseDec 2018Revised toDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Jul 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • Buildings3 building records
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA150000
BNA150000
Commercial 1NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 12 May 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 80%.

A69%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
B77%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Commercial 166%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 12 May 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes35%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
A11
B11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,208 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI13471.47
Proposed, not sanctioned12,036 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEMPIRE ESTATE, PUNE MUMBAI ROAD, CHINCHWAD

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKHIRE BHIDE & ASSOCIATES
PartnerRole in project
Supreme Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001117Dec 2018 → Dec 2019

Reason as filed by the promoterWe hereby apply for extension of the following project KINGSTON AVENUE registered with the regulatory authority vide project registration certificate bearing no P52100001909 which expires on 31/12/2018. We request you to grant extension of RERA Registration for a further period of 12 months for as some work of Building A and development work are pending. Building B and Commercial Building is completed and competition certificate has been received on 27.12.2018 for the same. Hence we request to grant extension for balance pending work and increase project completion date by 12 months till 31/12

Litigation declared4

CaseCourtStatus
RCS2100052/2013/2013Civil court pimpriPENDING
2100145/2013/2013Civil court pimpriPENDING
SPL CS 201797/2010/2010Civil court senior division punePENDING
403031/2015Chief Judicial Magistrate MPCB ECORDER IS PASSED IN OUR FAVOUR

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000022277Praveen Ninu MahajanGhanshyam Jhangaldas Sukhwani29/11/2018
CC005000000033550Ganesh Vilas PhalkeGhanshyam Jhangaldas Sukhwani22/10/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Dec 2019

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY CERTIFICATE A BLDG.pdf12 May 2021
Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECHFORM4ABLDG.pdf22 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECHFORM4BCOMM.pdf22 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION BDLGB AND COMMERCIAL1.pdf30 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion A Bldg 1.pdf30 Dec 2019
Certificates of CA (Form 5)File: FORM 5_certified copy_compressed.pdf19 Oct 2019
OtherFile: SUPREME MPCB COURT ORDER.pdf9 May 2019
Building plan approvalFile: layout plan.pdf19 Apr 2019
Building plan approvalFile: club house floor plan.pdf19 Apr 2019
Building Plan Approval (IOD)File: layout plan.pdf19 Apr 2019
Building Plan Approval (IOD)File: club house floor plan.pdf19 Apr 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY CERTIFICATE B BLDG.pdf19 Apr 2019
OtherFile: Completion A Bldg.pdf19 Apr 2019
OtherFile: COMPLETION BDLGB AND COMMERCIAL.pdf19 Apr 2019
Certificates of CA (Form 5)File: Annual Report On Statement Of Accounts.pdf30 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf31 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS_CERTIFICATE.pdf31 Oct 2017
Certificates of CA (Form 3)File: CA_CERTIFICATE.pdf31 Oct 2017
Declaration in FORM BFile: Affidavit_Cum_Declaration.pdf28 Jul 2017
Building plan approvalFile: PHASING LAYOUT (ANNEXURE C2).pdf25 Jul 2017
Building plan approvalFile: PHASING LAYOUT (ANNEXURE C2).pdf25 Jul 2017
Copy of the legal title reportFile: combinepdf-ilovepdf-compressed.pdf25 Jul 2017
Building Plan Approval (IOD)File: PHASING LAYOUT (ANNEXURE C2).pdf25 Jul 2017
Building Plan Approval (IOD)File: PHASING LAYOUT (ANNEXURE C2).pdf25 Jul 2017
Proforma of Allotment letterFile: AGGREEMENT TO SALE.pdf25 Jul 2017
PAN CardFile: supreme pan card.PDF24 Jul 2017
Details of encumbrancesFile: Non Encumbrance Supreme.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Scan0006-ilovepdf-compressed.pdf24 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Supreme ARchitech certificate.pdf24 Jul 2017
Building plan approvalFile: SHEET 12.pdf21 Jul 2017
Layout approvalFile: BLDG SHEET.pdf21 Jul 2017
Building plan approvalFile: SHEET 1.pdf21 Jul 2017
Building plan approvalFile: SHEET 2.pdf21 Jul 2017
Building plan approvalFile: SHEET 2-A.pdf21 Jul 2017
Building plan approvalFile: SHEET 3.pdf21 Jul 2017
Building plan approvalFile: SHEET 4.pdf21 Jul 2017
Building plan approvalFile: SHEET 5.pdf21 Jul 2017
Building plan approvalFile: SHEET 6.pdf21 Jul 2017
Building plan approvalFile: SHEET 7.pdf21 Jul 2017
Building plan approvalFile: SHEET 8.pdf21 Jul 2017
Building plan approvalFile: SHEET 9.pdf21 Jul 2017
Building plan approvalFile: SHEET 10.pdf21 Jul 2017
Building plan approvalFile: SHEET 11.pdf21 Jul 2017
Copy of Layout Approval (in case of layout)File: BLDG SHEET.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 1.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 2.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 2-A.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 3.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 4.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 5.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 6.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 7.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 8.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 9.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 10.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 11.pdf21 Jul 2017
Building Plan Approval (IOD)File: SHEET 12.pdf21 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S _CERTIFICATE (FORM 2).pdf21 Jul 2017
Certificates of CA (Form 3)File: CA_CERTIFICATE (FORM 3).PDF21 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KINGSTONE AVENUE PH 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pimpale Saudagar13,700+ in Pune

2 kmKINGSTONE AVENUE PH 1Completed 72Lapsed / revoked 46Other 67Dot size: filed unitsN

Filed coordinates, straight-line distance. 185 registered projects within 2 km.

Builder: Supreme Developers

Supreme Developers has 4 registrations on MahaRERA, including KINGSTONE AVENUE PH 1 and HILL SIDE RESIDENCY WING A B AND C. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if KINGSTONE AVENUE PH 1 is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KINGSTONE AVENUE PH 1?

The registered promoter entity is Supreme Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KINGSTONE AVENUE PH 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KINGSTONE AVENUE PH 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KINGSTONE AVENUE PH 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KINGSTONE AVENUE PH 1?

The professionals named in the filing: Architect: KHIRE BHIDE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KINGSTONE AVENUE PH 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KINGSTONE AVENUE PH 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KINGSTONE AVENUE PH 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.