Home / Browse projects / Pune, Maharashtra / Kingston Avenue Phase II
Kingston Avenue Phase II
RG-MH-37802 · RERA P52100047815 · Last updated on MahaRERA portal: 24 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 4 cases
- Completion date moved by 24 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kingston Avenue Phase II is a Others project by Supreme Developers in Pune, Maharashtra, registered with MahaRERA as P52100047815 on 28 Nov 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 11 of the 68 units on this registration are recorded sold or booked, and 11 of 22 construction stages are filed complete.
At a glance
Project
- NameKingston Avenue Phase II
- TypeOthers
- Location
- Pimple Saudagar
- Pimpale Saudagar
- Haveli
- Pune
- 411027
- Pincode411027
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100047815
- ReraGenie IDRG-MH-37802
Builder
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on28 Nov 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
- Buildings2 building records
- Documents filed91 files
Current status
Figures as on 24 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building D | NA | 4 | 4 | 0 | 44 | 44 |
| Building E | NA | 3 | 2 | 0 | 24 | 24 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.
Building D75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 65% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Building E81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 55% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 65% |
Progress on shared amenities15
As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 85% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | Yes | 55% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed604
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building D | 60 | 240 | 300 |
| Building E | 38 | 266 | 304 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building E | NA | Rs 12.52 cr | Rs 3.54 cr |
| Building D | NA | Rs 9.56 cr | Rs 4.79 cr |
| - | NA | Rs 2.81 cr | Rs 59.01 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Khire Bhide Associates |
| Engineer | Bricklane |
| Engineer | Vilas Chorge |
| Chartered Accountant | ANJK AND CO LLP |
| Chartered Accountant | R V Nevatia & Co |
| Chartered Accountant | Chevale Aghav & Co LLP |
| Partner | Role in project |
|---|---|
| Supreme Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52100047815 up to 31/12/2026.
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 201797/2010 | Honorable CJSD Pune | Pending |
| 2100052/2013 | Honorable CJJD Pimpri | Pending |
| 2100145/2013 | Honorable CJJD Pimpri | Pending |
| 123/2021 | Honorable CJJD Pimpri | Pending |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jul 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed91
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1_compressed.pdf | 24 Apr 2026 |
| Form 2File: Form 2_compressed.pdf | 24 Apr 2026 |
| Form 3File: Form 3_compressed (2).pdf | 24 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and unsold Inventory_compressed (1).pdf | 24 Apr 2026 |
| Form 1File: kingstone Avenue D Bldg Certificate of completion of construction Form 1 (1).pdf | 27 Jan 2026 |
| Form 2File: Kingstone Avenue Phase II Engineers Certificate of Cost Incurred for Development Form 2.pd | 27 Jan 2026 |
| Form 3File: kingstone Avenue D Bldg Certificate of completion of construction Form 1 (1).pdf | 27 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Kingstone Avenue Phase II Sold.pdf | 27 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - Sukhwani Kingston Phase II_Signed.pdf | 2 Dec 2025 |
| Form 5 (FY 2023-2024)File: Form 5 - Sukhwani Kingston Phase II.pdf | 2 Dec 2025 |
| Form 1File: Form 1_compressed.pdf | 7 Nov 2025 |
| Form 2File: Kingstone_Engineers Certificate.pdf | 7 Nov 2025 |
| Form 3File: Kingstone_Form 3_compressed.pdf | 7 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Kingstone_Sold Unsold List.pdf | 7 Nov 2025 |
| Form 1File: Architech Certificate D building.pdf | 24 Jul 2025 |
| Form 2File: Engineers Certificate (1).pdf | 24 Jul 2025 |
| Form 3File: CA Certificate (1)_compressed.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold List (1).pdf | 24 Jul 2025 |
| Form 1File: Form 1 - Architect Certificate SD_compressed.pdf | 24 Jul 2025 |
| Form 2File: Form 2 Supreme Developers.pdf | 24 Jul 2025 |
| Form 3File: Form 3 - Supreme Developers_compressed.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Supreme Developers_Sold Unsold Booked List.pdf | 24 Jul 2025 |
| Form 1File: Form 1_compressed.pdf | 24 Jul 2025 |
| Form 2File: Form 2 Engineer Certificate - Dec 2024 Sign.pdf | 24 Jul 2025 |
| Form 3File: CA Certificate - December 2024 Sign_compressed.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - Dec 2024 sign.pdf | 24 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate SD_compressed.pdf | 22 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Supreme Developers_compressed.pdf | 22 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Supreme Developers.pdf | 22 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Supreme Developers_Sold Unsold Booked List.pdf | 22 Apr 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrance certificate with Finance and Legal.pdf | 15 Mar 2025 |
| Declaration in FORM BFile: Form B -Declaration by promoter.pdf | 15 Mar 2025 |
| CERSAI detailsFile: CERSAI Declaration.pdf | 15 Mar 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrance certificate with Finance and Legal.pdf | 15 Mar 2025 |
| Other - TechnicalFile: Plinth Certificate.pdf | 15 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate December 2024.pdf | 9 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - December 2024 - Signed.pdf | 9 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - December 2024.pdf | 9 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - December 2024.pdf | 9 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate - September 2024.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - September 2024.pdf | 9 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - September 2024 Sign.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - September 2024 - Sign.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate - September 2024.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - September 2024 - Sign.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - September 2024.pdf | 9 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - September 2024 Sign.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_FY_2022-23.pdf | 12 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_FY_2022-23.pdf | 12 Aug 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration format A on Seperate bank account.pdf | 7 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance March 2024.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate June 2024 - Sign.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Assurance Certificate 2022-23.pdf | 19 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Supreme Architect certificate .pdf | 7 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SUPREME DEV ENGINEERS CERTIFICATE March 2024.pdf | 7 May 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Signed.pdf | 7 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Signed.pdf | 7 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SUPREME DEV ARCHITECH CERTIFICATE Form 1.pdf | 20 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SUPREME DEV ENGINEERS CERTIFICATE SEPT 2023 - Form 2.pdf | 20 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SUPREME DEV CA CERTIFICATE 19122023 - Form 3.pdf | 20 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kingston_compressed.pdf | 7 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: kingston avenue e bldg architech certificate march 23_compressed.pdf | 7 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kingston_compressed.pdf | 7 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Kingston.pdf | 7 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kingston_compressed.pdf | 7 Jun 2023 |
| Proforma of Agreement for saleFile: Kingston Avenue Agreement To Sale_removed-3.pdf | 10 Nov 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report - Agreement - 4-11-22-10.pdf | 7 Nov 2022 |
| Details of encumbrances concerned to LegalFile: RERA draft -KINGSTON AVENUE- COMMERCIAL-18-36.pdf | 14 Oct 2022 |
| Details of encumbrances concerned to LegalFile: supreme non encumbarance_compressed-1.pdf | 8 Oct 2022 |
| Proforma of Allotment letterFile: Allotment letter sign on letter head_compressed.pdf | 22 Sep 2022 |
| Deviation Report with respect to Allotment letterFile: Deviation Report - Allotment Letter sign.pdf | 26 Aug 2022 |
| Details of encumbrances concerned to FinanceFile: No Encumbrance Certificate (1).pdf | 13 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Separate Bank Accts_compressed.pdf | 8 Aug 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200243163429_For_Asset_Based_Search_26_07_2022_17_53_08_888.pdf | 6 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Signed.pdf | 27 Jul 2022 |
| Layout approvalFile: Sanctioned Plan.pdf | 26 Jul 2022 |
| Building plan approvalFile: N A Order Page 1.pdf | 26 Jul 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Kingston Avenue Phase 1 | S No 70 Pimple Saudagar Pune | 160 | Completed | Dec 2019 | Dec 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 91 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Kingston Avenue Phase II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pimple Saudagar13,700+ in Pune
Filed coordinates, straight-line distance. 113 registered projects within 2 km.
VANTAGE TWENTY ONE
VIVANTA REALTY
SHAKTI GARDENS
Grandwell Properties and Leasing Private L
24K OPULA
KOLTE-PATIL DEVELOPERS LIMITED
Sukhwani Minerva
Sukhwani Ramchandani LLP
MIDORI TOWER PHASE 4
VIKRAM DEVELOPERS AND PROMOTERS
Sai Aura
WJV LANDMARKS LLP
Builder: Supreme Developers
Supreme Developers has 4 registrations on MahaRERA, including KINGSTONE AVENUE PH 1 and HILL SIDE RESIDENCY WING A B AND C. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Kingston Avenue Phase II is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kingston Avenue Phase II?
The registered promoter entity is Supreme Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kingston Avenue Phase II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kingston Avenue Phase II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kingston Avenue Phase II?
The professionals named in the filing: Architect: Khire Bhide Associates; Engineer: Bricklane; Engineer: Vilas Chorge; Chartered Accountant: ANJK AND CO LLP; Chartered Accountant: R V Nevatia & Co; Chartered Accountant: Chevale Aghav & Co LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kingston Avenue Phase II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.