Home / Browse projects / Aurangabad, Maharashtra / Khatod Arcade
Khatod Arcade
RG-MH-08607 · RERA P51500020629 · Last updated on MahaRERA portal: 6 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Khatod Arcade is a Others project by Ashok Ramnath Khatod in Aurangabad, Maharashtra, registered with MahaRERA as P51500020629 on 30 Apr 2019. Possession is promised by 31 Mar 2027. The completion date has moved by 24 months from the original filing. 4 of the 72 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameKhatod Arcade
- TypeOthers
- Location
- Deolai Road
- Satara
- Aurangabad (M Corp.)
- Aurangabad
- 431005
- Pincode431005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500020629
- ReraGenie IDRG-MH-08607
Builder
- NameAshok Ramnath Khatod
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on30 Apr 2019
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 30 Mar 2025)
- Buildings1 building record
- Documents filed150 files
Current status
Figures as on 6 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Khatod Arcade | NA | 10 | 7 | 44 | 28 | 72 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.
Khatod Arcade: 72% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Khatod Arcade | NA | Rs 5.43 cr | Rs 5.20 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Manoj Kala And Associates |
| Engineer | Arun Kumar Pani |
| Engineer | Abhishek Bakliwal |
| Chartered Accountant | Lathi and Tapdiya |
| Chartered Accountant | Narendra Navandar |
| Partner | Role in project |
|---|---|
| Ashok Ramnath Khatod | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Registered project is having Apartment Building structures which is in progress and the delay in construction of the Apartment Building is mainly on account of unavailability of labour. Hence, we apply for extension of time limit up to 31-03-2027.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Apr 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Apr 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Apr 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2027
Documents filed150
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 150 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Mar 26.pdf | 6 May 2026 |
| Withdrawal Update Form 2File: Form 2 Mar 26.pdf | 6 May 2026 |
| Withdrawal Update Form 3File: Form-3 Khathod_0001.pdf | 6 May 2026 |
| Withdrawal Update Form 1File: Form 1 Manoj Kala_0001.pdf | 22 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Ashok Khatod_0001.pdf | 22 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 Ashok Khatod_0001.pdf | 22 Jan 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 Dt-15-10-2025_0001.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Ashok Khatod_0001.pdf | 18 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form-5 Ashok Khatod Dt-30-09-2025_0001.pdf | 29 Sep 2025 |
| Form 1File: FORM 1.pdf | 11 Sep 2025 |
| Form 2File: form 2.pdf | 11 Sep 2025 |
| Form 3File: CA Certificate of Ashok Khatods 30-06-2025_0001.pdf | 11 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: disc.pdf | 11 Sep 2025 |
| OthersFile: form 2A.pdf | 11 Sep 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1_0001.pdf | 28 Apr 2025 |
| Certificates of CA (Form 3)File: Form-3 Ashok Khatode Dec-24_0001 (1).pdf | 28 Apr 2025 |
| Certificates of CA (Form 3)File: Form-3 Ashok Khatode Mar25.pdf | 28 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-02_0001.pdf | 28 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclousre_0001.pdf | 28 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A_0001.pdf | 28 Apr 2025 |
| Declaration in FORM BFile: KHATOD ARCADE Form B.pdf | 23 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Dt-10-01-2025_0001.pdf | 29 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Ashok Khatod_0001.pdf | 29 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Booked Inventory -Khatod Arcade_0001.pdf | 29 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A Ashok Khatod_0001.pdf | 29 Jan 2025 |
| Certificates of CA (Form 3)File: form 3Ashok Khatod Date-Dec 23.pdf | 9 Nov 2024 |
| Certificates of CA (Form 3)File: Form-3,Ashok Khatod Date Jan-March 24.pdf | 9 Nov 2024 |
| Certificates of CA (Form 3)File: Form-3,Ashok Khatod Date Apr-jun 24.pdf | 9 Nov 2024 |
| Certificates of CA (Form 3)File: Form-3,Ashok Khatod Date Jul-Sep 24.pdf | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11-10-2024 rera doc4.pdf | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5-7-2024 rera doc4.pdf | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 04-04-2024 rera doc4.pdf | 9 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Dt-01-07-2024_0001.pdf | 7 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Dt-01-10-2024_0001.pdf | 7 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Discolosure 31-03-2024.pdf | 7 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inve_0001_2.pdf | 7 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inve_0001_1.pdf | 7 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form -2A Dt-07-10-2024_0001.pdf | 7 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form -2A Dt-05-10-2024_0001.pdf | 7 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Dt-30-10-2024_0001.pdf | 7 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form - 5 - 07-12-2022_0001.pdf | 14 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 28-12-2023.pdf | 27 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 03-04-2024.pdf | 27 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate03-01-2024.pdf | 27 Apr 2024 |
| Building plan approvalFile: Scan_1585-05 (5 files merged) - converted.pdf | 6 Apr 2024 |
| Building Plan Approval (IOD)File: Scan_1585-05 (5 files merged) - converted.pdf | 6 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Scan_1586-01 (2 files merged).pdf | 6 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Q A Certificate 05-01-2024.pdf | 6 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Q A Certificate 03-04-2024.pdf | 6 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Discolosure 31-12-2023.pdf | 6 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kaagaz_20231123_165833586490.pdf | 23 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JUN 23.pdf | 23 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SEP 23.pdf | 23 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A 05 oct 22_0001.pdf | 28 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A 02 Jan 23_0001.pdf | 28 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A 04 Apr 2023_0001.pdf | 28 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A 05 July 23_0001.pdf | 28 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A 06 June 23_0001.pdf | 28 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Booking inventory 31 mar 23_0001.pdf | 28 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Booking Inventory 30 June 23_0001.pdf | 28 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Booking Inventory 30 Sep 23_0001.pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Form-03 31-03-2022_0001.pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Form-03 30-06-22_0001.pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Form-03 30-09-2022_0001.pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Form-03 31-12-2022_0001.pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Form-03 31-03-2023_0001.pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Form-03 30-06-2023_0001.pdf | 28 Oct 2023 |
| Certificates of CA (Form 3)File: Form-03 30-09-2023_0001.pdf | 28 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Ashok Khatod 2022-23.pdf | 21 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 28-03-2023.pdf | 10 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30-06-2023.pdf | 10 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 27-9-2023.pdf | 10 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A SEP 21.pdf | 10 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A DEC 21.pdf | 10 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A MAR 22.pdf | 10 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A JUN 22.pdf | 10 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DISC 30-09-2021.pdf | 10 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DISC 31-12-2021.pdf | 10 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DISC 31-3-2022.pdf | 10 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 150 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Khatod Arcade on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Satara1,400+ in Aurangabad
Filed coordinates, straight-line distance. 74 registered projects within 2 km.
One World Phase I
SIMAR PRIDE VENTURES LLP
The Solitairee Phase I
Dizzi Land Farms Private Limited
Neo Orbit
Piyush Infratech Pvt.Ltd.
180 and 51 Greens
A.M.PATEL INFRA PVT LTD
MILLENNIUM BUSINESS CENTER
MILLENNIUMPRO NEST LLP
The Solitairee Phase II
Dizzi Land Farms Private Limited
See every Aurangabad project, with the district possession charts
Builder: Ashok Ramnath Khatod
Ashok Ramnath Khatod has 1 registration on MahaRERA, including Khatod Arcade. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if Khatod Arcade is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Khatod Arcade?
The registered promoter entity is Ashok Ramnath Khatod, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Khatod Arcade?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Khatod Arcade?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Khatod Arcade?
The professionals named in the filing: Architect: Manoj Kala And Associates; Engineer: Arun Kumar Pani; Engineer: Abhishek Bakliwal; Chartered Accountant: Lathi and Tapdiya; Chartered Accountant: Narendra Navandar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Khatod Arcade?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.