Home / Browse projects / Nashik, Maharashtra / Karmaa Galaxy Phase 2
Karmaa Galaxy Phase 2
RG-MH-14813 · RERA P51600032375 · Last updated on MahaRERA portal: 19 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 38 months past the filed date
- Completion date moved by 8 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Karmaa Galaxy Phase 2 is a Residential / Group Housing project by KARMAA REALTY in Nashik, Maharashtra, registered with MahaRERA as P51600032375 on 4 Jan 2022. Possession was promised by 31 Aug 2023 and is now 38 months past that date. The completion date has moved by 8 months from the original filing. 13 of the 15 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete.
At a glance
Project
- NameKarmaa Galaxy Phase 2
- TypeResidential / Group Housing
- Location
- Tigrania Road
- Tapovan
- Nashik (M Corp.)
- Nashik
- 422011
- Pincode422011
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600032375
- ReraGenie IDRG-MH-14813
Builder
- NameKARMAA REALTY
- Entity typePartnership
- PartnersVINOD MADANLAL TALWAR, CHANDRA VINOD TALWAR, SUNIL GUPTA, KAVITA SUNIL GUPTA
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Jan 2022
- Promised completion31 Aug 2023
- Revised completionRevised to 31 Aug 2023 (originally 31 Dec 2022)
- Buildings2 building records
- Documents filed45 files
Current status
Figures as on 19 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Karmaa Galaxy Building 4 | NA | 1 | 1 | 5 | 0 | 5 |
| Karmaa Galaxy Building 3 | NA | 1 | 1 | 10 | 0 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
Karmaa Galaxy Building 4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Karmaa Galaxy Building 3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed10
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Karmaa Galaxy Building 4 | 5 | 5 |
| Karmaa Galaxy Building 3 | 5 | 5 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rupali and Vivek Jaykhedkar |
| Engineer | Keerthi Kumar |
| Chartered Accountant | Mukarram Daginawala |
| Chartered Accountant | Chetan Bumb |
| Chartered Accountant | Bhavana Loya |
| Partner | Role in project |
|---|---|
| KARMAA REALTY | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have completed the work in all aspects. The project is 98% complete. We have applied for Occupation Certificate and the timeline for the same is not certain as the Municipal Corporation is transitioning into an online system. Hence we request an extension for the same.
Reason as filed by the promoterWe have successfully completed the RCC Brickwork and Plaster work of the Buildings proposed. The finishing work for the same is ongoing. There was delay of work due to labour shortage which caused delay in finishing the work. However we are very much on schedule to finish the work before the 30th of April 2023. We have only sold 1 unit and taken the approval of the Allottee to extend the handover scheduled date. Kindly grant us the extension
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Dec 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Dec 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed45
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 Q1-23-24.PDF | 19 Jun 2026 |
| Form 2File: Form 2 Q1 23-24.pdf | 19 Jun 2026 |
| Form 3File: Form 3 Q1.pdf | 19 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Q1.pdf | 19 Jun 2026 |
| Form 1File: Form 1 Q2-23-24.PDF | 19 Jun 2026 |
| Form 2File: Form 2 Q2 23-24.pdf | 19 Jun 2026 |
| Form 3File: Form 3 Q2.pdf | 19 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Q2.pdf | 19 Jun 2026 |
| Form 1File: Form 1 Q4-21-22.PDF | 29 May 2026 |
| Form 2File: Form 2 Q4-21-22.PDF | 29 May 2026 |
| Form 3File: Form 3 Q4 21-22 1.pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 29 May 2026 |
| Form 1File: Form 1 Q1-22-23.PDF | 29 May 2026 |
| Form 2File: Form 2 Q1-22-23.pdf | 29 May 2026 |
| Form 3File: Form 3 Q1 22-23 1 .pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 29 May 2026 |
| Form 1File: Form 1 Q2-22-23.PDF | 29 May 2026 |
| Form 2File: Form 2 Q2 22-23.pdf | 29 May 2026 |
| Form 3File: Form 3 Q2 22-23 1 .pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf | 29 May 2026 |
| Form 1File: Form 1 Q3-22-23.PDF | 29 May 2026 |
| Form 2File: Form 2 Q3 22-23.pdf | 29 May 2026 |
| Form 3File: Form 3 Q3 22-23 1 .pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 29 May 2026 |
| Form 1File: Form 1 Q4-22-23.PDF | 29 May 2026 |
| Form 2File: Form 2 Q4 22-23.pdf | 29 May 2026 |
| Form 3File: Form 3 Q4 22-23 1_0001.pdf | 29 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 29 May 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1.pdf | 1 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 3CA_2023.pdf | 10 Jan 2023 |
| PAN CardFile: Karmaa Realty Pan.pdf | 28 Dec 2021 |
| CERSAI detailsFile: CRESAI1.pdf | 28 Dec 2021 |
| Copy of the legal title reportFile: TitleSearch.pdf | 22 Dec 2021 |
| Details of encumbrancesFile: RERA Karmaa Galaxy Free Hold Land.pdf | 22 Dec 2021 |
| Declaration about Commencement CertificateFile: RERA Karmaa Galaxy (Format - D).pdf | 22 Dec 2021 |
| Declaration in FORM BFile: RERA Karmaa Galaxy Form B Notary_compressed.pdf | 22 Dec 2021 |
| CERSAI detailsFile: CRESAI2.pdf | 22 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3CA_GalaxyPhase2.pdf | 22 Dec 2021 |
| Proforma of Allotment letterFile: AgreementDraft_Phase2.pdf | 22 Dec 2021 |
| Proforma of Allotment letterFile: RERA Karmaa Galaxy Allotment Letter.pdf | 22 Dec 2021 |
| Layout approvalFile: scan-2-compressed_compressed.pdf | 18 Dec 2021 |
| Building plan approvalFile: scan0113-compressed_compressed.pdf | 18 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: scan-2-compressed_compressed.pdf | 18 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: scan0113-compressed_compressed.pdf | 18 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: sr no 400-5,6,7,8_compressed.pdf | 18 Dec 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 45 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Karmaa Galaxy Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Tapovan4,100+ in Nashik
Filed coordinates, straight-line distance. 92 registered projects within 2 km.
Anandvan Housing Complex
Ravi Mahajan Buildcon LLP
SHREEJI INFINIA
SHREEJI LIFE SPACE
Waterways
Sanklecha Construction Private Limited
Shreejis Gujral Arcade
SHREEJI LIFE SPACE
VRAJ METROPOLIS SOUTH
SHREE INFRA SPACE
ALEEF BREEZE APARTMENT
KHATIB BUILDERS AND DEVELOPERS
See every Nashik project, with the district possession charts
Builder: KARMAA REALTY
KARMAA REALTY has 2 registrations on MahaRERA, including KARMAA GALAXY and Karmaa Galaxy Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What does it mean that Karmaa Galaxy Phase 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Karmaa Galaxy Phase 2 is delayed beyond 31 Aug 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Karmaa Galaxy Phase 2?
The registered promoter entity is KARMAA REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Karmaa Galaxy Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Karmaa Galaxy Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Karmaa Galaxy Phase 2?
The professionals named in the filing: Architect: Rupali and Vivek Jaykhedkar; Engineer: Keerthi Kumar; Chartered Accountant: Mukarram Daginawala; Chartered Accountant: Chetan Bumb; Chartered Accountant: Bhavana Loya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Karmaa Galaxy Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.