Home / Browse projects / Mumbai Suburban, Maharashtra / CHANDAK SARVAM
CHANDAK SARVAM
By CHANDAK REALTORS PRIVATE LIMITED
RG-MH-19187 · RERA P51800078249 · Last updated on MahaRERA portal: 25 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 7 cases
- Rs 200.00 crore secured on the land, in favour of Standard Chartered Bank
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CHANDAK SARVAM is a Residential / Group Housing project by CHANDAK REALTORS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800078249 on 29 Nov 2024. Possession is promised by 31 Dec 2030. 58 of the 294 units on this registration are recorded sold or booked, and 3 of 66 construction stages are filed complete.
At a glance
Project
- NameCHANDAK SARVAM
- TypeResidential / Group Housing
- Location
- J B Nagar
- Andheri East
- Sahar
- Andheri
- Mumbai Suburban
- 400059
- Pincode400059
- RERA no.P51800078249
- ReraGenie IDRG-MH-19187
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Nov 2024
- Promised completion31 Dec 2030
- Revised completionNone
- Buildings6 building records
- Documents filed101 files
Current status
Figures as on 25 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 19 | 15 | 63 | 0 | 63 |
| WING B | NA | 19 | 15 | 51 | 0 | 51 |
| WING C | NA | 19 | 15 | 50 | 0 | 50 |
| WING D | NA | 19 | 15 | 39 | 0 | 39 |
| WING E | NA | 19 | 15 | 52 | 0 | 52 |
| WING F | NA | 19 | 15 | 39 | 0 | 39 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 25 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Basement (if any), at 80%.
WING A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING D16%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING E15%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 60% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING F15%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 60% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed506
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING A | 97 | 97 |
| WING B | 70 | 70 |
| WING C | 96 | 96 |
| WING D | 71 | 71 |
| WING E | 85 | 85 |
| WING F | 87 | 87 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Mahapalika Laghuvetan Karmachari Sahakari GruhMAHA | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING A | NA | Rs 59.01 cr | Rs 2.53 cr |
| WING F | NA | Rs 55.02 cr | Rs 2.36 cr |
| - | NA | Rs 51.19 cr | Rs 2.19 cr |
| WING C | NA | Rs 46.86 cr | Rs 2.01 cr |
| WING E | NA | Rs 46.47 cr | Rs 1.99 cr |
| WING D | NA | Rs 42.81 cr | Rs 1.83 cr |
| WING B | NA | Rs 39.93 cr | Rs 1.71 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ATUL DESAI CONULTANTS |
| Engineer | Chirag Shah |
| Engineer | Gopal Madugula |
| Chartered Accountant | Kedia Singhania and Co |
| Chartered Accountant | Singhvi and Singhvi |
| Partner | Role in project |
|---|---|
| CHANDAK REALTORS PRIVATE LIMITED | - |
Litigation declared7
| Case | Court | Status |
|---|---|---|
| 10655/2012 | HIGH COURT OF BOMBAY | Pending |
| 19203/2022 | HIGH COURT OF BOMBAY | Pending |
| 16264/2024 | HIGH COURT OF BOMBAY | Pending |
| 2076/2024 | Dindoshi Court | Pending |
| 1883/2024 | Dindoshi Court | Pending |
| 1803/2024 | Dindoshi Court | Pending |
| 304/2010 | HIGH COURT OF BOMBAY | Pending |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Nov 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Nov 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Apr 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2030
Documents filed101
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1-March 2026.pdf | 25 Apr 2026 |
| Withdrawal Update Form 2File: Form -2 CRPL-Sarvam.pdf | 25 Apr 2026 |
| Withdrawal Update Form 3File: Form 3-March 26-Sarvam-compressed.pdf | 25 Apr 2026 |
| Form 2A (FY 2025-2026)File: Form 2A-Chandak Sarvam-2025-26.pdf | 24 Apr 2026 |
| Form 2A (FY 2024-2025)File: Form 2A- Engineer Certificate- CRPL.pdf | 24 Feb 2026 |
| Withdrawal Update Form 1File: Sarvam Form 1.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Form 2- Sarvam Project-Dec 25.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: Chandak Sarvam Form 3 SIgned.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: Form 1-30092025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 1File: Form 1-30092025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: CRPL SARVAM FORM 2.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: CRPL SARVAM FORM 2.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Sarvam-Form 3-30092025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Sarvam-Form 3-30092025.pdf | 18 Oct 2025 |
| Withdrawal Update Form 1File: Form 1-30092025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: CRPL SARVAM FORM 2.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Sarvam-Form 3-30092025.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Chandak Sarvam-September 2025.pdf | 23 Sep 2025 |
| Form 1File: Form 1 Ekatmata June 2025.pdf | 20 Jul 2025 |
| Form 2File: FORM-2 ekatmata June 2025.pdf | 20 Jul 2025 |
| Form 3File: Form 3-ekatmata-june 2025.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sarvam.pdf | 20 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Chandak Sarvam Sold-Unsold-Revsied on 02052025.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1-Chandak Sarvam-26042025.pdf | 26 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Chandak sarvam-31032025.pdf | 26 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Ekatmata March 2025.pdf | 26 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Chandak Sarvam-Sold-Unsold-31032025.pdf | 26 Apr 2025 |
| Building plan approvalFile: 1.pdf | 25 Apr 2025 |
| Building plan approvalFile: 2.pdf | 25 Apr 2025 |
| Building plan approvalFile: 3.pdf | 25 Apr 2025 |
| Building plan approvalFile: 4.pdf | 25 Apr 2025 |
| Building plan approvalFile: 5.pdf | 25 Apr 2025 |
| Building plan approvalFile: 6.pdf | 25 Apr 2025 |
| Building plan approvalFile: 7.pdf | 25 Apr 2025 |
| Building plan approvalFile: 8.pdf | 25 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 25 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 25 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 25 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 25 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 25 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 25 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 25 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 8.pdf | 25 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- Engineer Certificate- CRPL.pdf | 25 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- 31122024.pdf | 7 Mar 2025 |
| CERSAI detailsFile: CERSAI-Assest Based Report-Ekatmata-IDBI.pdf | 7 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Chandak Sarvam-Sold-unsold-DEc 2024.pdf | 19 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Chandak Sarvam-Sold-unsold-DEc 2024.pdf | 19 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Form-3MahaRERA ekatmata 31122024.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ekatmata Dec -2024.pdf | 25 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Form-3MahaRERA ekatmata 31122024.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ekatmata Dec -2024.pdf | 25 Jan 2025 |
| Other - FinanceFile: Sarvam-Rehab-Declaration cum Undertaking-04112024-compressed.pdf | 21 Nov 2024 |
| Other - FinanceFile: Sarvam-Rehab-Declaration cum Undertaking-04112024-compressed.pdf | 21 Nov 2024 |
| Other - FinanceFile: Declaration Land Cost-13112024.pdf | 13 Nov 2024 |
| Other - TechnicalFile: Sarvam- Annexure A-Declaration-04112024.pdf | 13 Nov 2024 |
| Copy of the legal title reportFile: RERA Title Report -05112024.pdf | 6 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Ekatmata-2112024.pdf | 6 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Engineer.pdf | 6 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Aditya Sir-Disclosure Interest.pdf | 6 Nov 2024 |
| Building plan approvalFile: Building Plan - Sheet 8.pdf | 5 Nov 2024 |
| Building plan approvalFile: Building Plan - Sheet 7.pdf | 5 Nov 2024 |
| Building plan approvalFile: Building Plan - Sheet 6.pdf | 5 Nov 2024 |
| Building plan approvalFile: Building Plan - Sheet 5.pdf | 5 Nov 2024 |
| Building plan approvalFile: Building Plan - Sheet 4.pdf | 5 Nov 2024 |
| Building plan approvalFile: Building Plan - Sheet 3.pdf | 5 Nov 2024 |
| Building plan approvalFile: Building Plan - Sheet 2.pdf | 5 Nov 2024 |
| Building plan approvalFile: Building Plan - Sheet 1.pdf | 5 Nov 2024 |
| Building plan approvalFile: Ekatmata IOD letter.pdf | 5 Nov 2024 |
| Building plan approvalFile: Ekatmata LOI.pdf | 5 Nov 2024 |
| Layout approvalFile: Ekatmata - Layout Plan.pdf | 5 Nov 2024 |
| PAN CardFile: CRPL PAN Card.pdf | 5 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: Sarvam-Encumbrances relating to Finance-04112024-merged.pdf | 5 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: Ekatmata - Layout Plan.pdf | 5 Nov 2024 |
| Proforma of Allotment letterFile: Allotment Letter-Protected Version.pdf | 5 Nov 2024 |
| Declaration in FORM BFile: Form B Affidavit Cum Declaration-05112024.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Sarvam.pdf | 5 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Ekatamata CC.pdf | 5 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan - Sheet 7.pdf | 5 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Ekatmata LOI.pdf | 5 Nov 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations, which the RERA portal never shows together
- All 101 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep CHANDAK SARVAM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri East6,700+ in Mumbai Suburban
SKYLINE BUSINESS WORLD WING C
Skyline Prashasti
NAMAN PREMIER
SHREE NAMAN DEVELOPERS PVT LTD
I STAY TOWER K (STUDIO)
I-STAY HOUSING PRIVATE LIMITED
TRILIVE MAROL TOWER B
I-STAY HOUSING PRIVATE LIMITED
TBC Marol Phase 1
AGATE REALTORS AND DEVELOPERS
I STAY TOWER - I STUDIO
STARWING REAL ESTATE COMPANY
See every Mumbai Suburban project, with the district possession charts
Builder: CHANDAK REALTORS PRIVATE LIMITED
CHANDAK REALTORS PRIVATE LIMITED has 5 registrations on MahaRERA, including Chandak Treesourus and Chandak Highscape City 1A. Its filings disclose 10 earlier MahaRERA projects, none completed yet. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if CHANDAK SARVAM is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CHANDAK SARVAM?
The registered promoter entity is CHANDAK REALTORS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CHANDAK SARVAM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CHANDAK SARVAM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CHANDAK SARVAM?
The professionals named in the filing: Architect: ATUL DESAI CONULTANTS; Engineer: Chirag Shah; Engineer: Gopal Madugula; Chartered Accountant: Kedia Singhania and Co; Chartered Accountant: Singhvi and Singhvi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CHANDAK SARVAM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.