Kanak Heights - Geeta Bhavan Chsl
RG-MH-90942 · RERA P51800047686 · Last updated on MahaRERA portal: 14 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kanak Heights - Geeta Bhavan Chsl is a Others project by KANAK REALITY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800047686 on 21 Nov 2022. Possession was promised by 1 Jun 2025 and is now 16 months past that date. 32 of the 56 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameKanak Heights - Geeta Bhavan Chsl
- TypeOthers
- Location
- HAJI BAPU ROAD
- MALAD EAST
- Borivali
- Mumbai Suburban
- 400097
- Pincode400097
- RERA no.P51800047686
- ReraGenie IDRG-MH-90942
Builder
- NameKANAK REALITY
- Entity typePartnership
- PartnersBHUPENDRA KANUNGO, HIMANSHU MARU, SHAILESH VORA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on21 Nov 2022
- Promised completion1 Jun 2025
- Revised completionNone
- Buildings1 building record
- Documents filed69 files
Current status
Figures as on 14 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KANAK HEIGHTS - GEETA BHAVAN CHSL | NA | 19 | 18 | 49 | 7 | 56 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
KANAK HEIGHTS - GEETA BHAVAN CHSL: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 14 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed30
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| GEETA BHAVAN CHSL | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| KANAK HEIGHTS - GEETA BHAVAN CHSL | NA | Rs 12.89 cr | Rs 10.60 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | HARISH D GANDHI |
| Engineer | SHRI BHAVESH PARMAR |
| Engineer | jacob dsouza |
| Chartered Accountant | HEMAL P SHAH & CO |
| Partner | Role in project |
|---|---|
| KANAK REALITY | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Oct 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jul 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed69
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certificate April-June 25.pdf | 14 Apr 2026 |
| Withdrawal Update Form 2File: Engineer Certificate April-June 25.pdf | 14 Apr 2026 |
| Withdrawal Update Form 3File: CA Certificate.pdf | 14 Apr 2026 |
| Withdrawal Update Form 1File: Architect Certificate April-June 25.pdf | 28 Mar 2026 |
| Withdrawal Update Form 2File: Engineer Certificate April-June 25.pdf | 28 Mar 2026 |
| Withdrawal Update Form 3File: CA Certificate (April 25-June25).pdf | 28 Mar 2026 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certifictae (Jan-march 2025).pdf | 8 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificat.pdf | 16 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate (01-01-25 to 31-03-25).pdf | 16 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 1 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 21 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 16 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 22 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 19 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 19 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Certificate form 2A March 24.pdf | 2 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginner Certificate Jan-March 24.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate march 24.pdf | 18 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 18 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Sep-Dec 23.pdf | 13 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate Dec 23.pdf | 12 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Certificate Dec 23.pdf | 12 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Oct-dec 22.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Jan-March 23.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate April-June 23.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate July- Sep 23.pdf | 19 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 18 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3.pdf | 18 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 22-23.pdf | 11 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate March 23.pdf | 2 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate June 23.pdf | 2 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 22 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 27 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect kanak.pdf | 17 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca kanak_compressed.pdf | 17 Jan 2023 |
| CERSAI detailsFile: CTS COVERING LETTER.pdf | 16 Nov 2022 |
| Details of encumbrances concerned to FinanceFile: CTS AND NO ENCUMBRANCE.pdf | 2 Nov 2022 |
| Details of encumbrances concerned to LegalFile: CTS AND NO ENCUMBRANCE.pdf | 2 Nov 2022 |
| CERSAI detailsFile: Corrected CTS Letter (IOD,CC).pdf | 2 Nov 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200250727094_For_Asset_Based_Search_28_10_2022_12_02_10_809.pdf | 2 Nov 2022 |
| Copy of the legal title reportFile: Corrected CTS Letter (IOD,CC).pdf | 18 Oct 2022 |
| Details of encumbrances concerned to FinanceFile: Corrected CTS Letter (IOD,CC).pdf | 18 Oct 2022 |
| Details of encumbrances concerned to LegalFile: Corrected CTS Letter (IOD,CC).pdf | 18 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA Certificate (Geeta Bhavan).pdf | 18 Oct 2022 |
| Other - LegalFile: Corrected CTS Letter (IOD,CC).pdf | 18 Oct 2022 |
| Copy of the legal title reportFile: TITLE REPORT KANAK.pdf | 17 Aug 2022 |
| Details of encumbrances concerned to FinanceFile: No Encumberance Letter For RERA.pdf | 17 Aug 2022 |
| Details of encumbrances concerned to LegalFile: No Encumberance Letter For RERA.pdf | 17 Aug 2022 |
| Proforma of Agreement for saleFile: ALLOTMENT LETTER KANAK HEIGHTS-GEETA BHAVAN CHSL.pdf | 17 Aug 2022 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER KANAK HEIGHTS-GEETA BHAVAN CHSL.pdf | 17 Aug 2022 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE KANAK HEIGHTS-GEETA BHAVAN CHSL.pdf | 17 Aug 2022 |
| Proforma of Agreement for saleFile: AGREEMENT FOR SALE KANAK HEIGHTS-GEETA BHAVAN CHSL.pdf | 17 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Details For RERA.pdf | 17 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: Devaition On AL For RERA.pdf | 17 Aug 2022 |
| Deviation Report with respect to model copy of AgreementFile: Devaition On AFS For RERA.pdf | 17 Aug 2022 |
| Layout approvalFile: Final Drwaing_1-3.pdf | 12 Jul 2022 |
| Layout approvalFile: Final Drwaing_4-end.pdf | 12 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: Final Drwaing_1-3.pdf | 12 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: Final Drwaing_4-end.pdf | 12 Jul 2022 |
| Building plan approvalFile: IOD Geeta Bhavan (MCGM).pdf | 9 Jul 2022 |
| PAN CardFile: Kanak PAN CARD.pdf | 9 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD Geeta Bhavan (MCGM).pdf | 9 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 2331987_FirstCC_signed.pdf | 9 Jul 2022 |
| Declaration about Commencement CertificateFile: CC Covering Letter.pdf | 9 Jul 2022 |
| Declaration in FORM BFile: Form B.pdf | 9 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 9 Jul 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 69 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Kanak Heights - Geeta Bhavan Chsl on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MALAD EAST6,700+ in Mumbai Suburban
Alta Monte and Signet
ERA REALTORS PRIVATE LIMITED
MAULI OMKAR
MAULI SAI DEVELOPERS PVT LTD
HIVE 97
AMITY CONSTRUCTIONS
MAULI PRIDE
MAULI SAI DEVELOPERS PVT LTD
Aarambh Phase III by group Satellite
Satellite Developers Private Limited
Sethia Imperial Avenue
Sai Enterprises
See every Mumbai Suburban project, with the district possession charts
Builder: KANAK REALITY
KANAK REALITY has 1 registration on MahaRERA, including Kanak Heights - Geeta Bhavan Chsl. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Kanak Heights - Geeta Bhavan Chsl shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Kanak Heights - Geeta Bhavan Chsl is delayed beyond 1 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kanak Heights - Geeta Bhavan Chsl?
The registered promoter entity is KANAK REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kanak Heights - Geeta Bhavan Chsl?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kanak Heights - Geeta Bhavan Chsl?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kanak Heights - Geeta Bhavan Chsl?
The professionals named in the filing: Architect: HARISH D GANDHI; Engineer: SHRI BHAVESH PARMAR; Engineer: jacob dsouza; Chartered Accountant: HEMAL P SHAH & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kanak Heights - Geeta Bhavan Chsl?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback