KAMALRAJ PRAYAG C
By Kamalraj V Square Properties LLP
RG-MH-49337 · RERA P52100050546 · Last updated on MahaRERA portal: 21 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KAMALRAJ PRAYAG C is a Residential / Group Housing project by Kamalraj V Square Properties LLP in DIGHI, 411015, registered with MahaRERA as P52100050546 on 21 Apr 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 6 months from the original filing. 47 of the 52 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameKAMALRAJ PRAYAG C
- TypeResidential / Group Housing
- Location
- PUNE ALANDI ROAD
- DIGHI
- 411015
- Pincode411015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100050546
- ReraGenie IDRG-MH-49337
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on21 Apr 2023
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2025)
- Buildings1 building record
- Documents filed54 files
Current status
Figures as on 21 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KAMALRAJ PRAYAG C | NA | 16 | 16 | 52 | 0 | 52 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
KAMALRAJ PRAYAG C: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 21 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| KAMALRAJ PRAYAG C | NA | Rs 14.13 cr | Rs 14.10 cr |
| - | NA | Rs 2.92 cr | Rs 2.92 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHASHANK PHADKE |
| Architect | PHADKE SHASHANK |
| Engineer | FIROZ PATHAN |
| Chartered Accountant | AGH AND ASSOCIATES |
| Chartered Accountant | C R LUNIYA AND COMPANY Luniya |
| Partner | Role in project |
|---|---|
| Kamalraj V Square Properties LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay due to lack of labour availability, rainy season, some paper work related to project such as revised plan. 95 % work completed only 5 % work is balance, which will complete before 31st December 2025.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed54
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Kamalraj Prayag Form1 Bldg C.pdf | 21 Jan 2026 |
| Withdrawal Update Form 2File: Form 2-25-26-3rd Qtr Prayag.pdf | 21 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Dec 25 - Prayag C.pdf | 21 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 Prayag C.pdf | 29 Nov 2025 |
| Withdrawal Update Form 1File: Kamalraj Prayag Form1 Bldg C.pdf | 27 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - Prayag C - 25-26 - 2nd Qtr.pdf | 27 Oct 2025 |
| Withdrawal Update Form 3File: Form - 3 Prayag C - 25-26 - Q2_11zon.pdf | 27 Oct 2025 |
| Form 5 (FY 2023-2024)File: Form 5 Prayag C.pdf | 8 Oct 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prayag C.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Prayag C.pdf | 14 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Prayag C.pdf | 31 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prayag C - Dec-24.pdf | 20 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Prayag_C_Quality_Assurance_Form_2A.pdf | 16 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kamalraj Form1 - Prayag C.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prayag C - Sept 24.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Prayag C.pdf | 17 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1- Prayag c.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prayag C.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Prayag C - Form 1.pdf | 18 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prayag C March 24.pdf | 18 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prayag C Dec 23.pdf | 22 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Prayag C Dec 23.pdf | 12 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prayag C.pdf | 8 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Prayag C.pdf | 20 Oct 2023 |
| CERSAI detailsFile: Declaration regarding NO CERSAI.pdf | 13 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Prayag.pdf | 13 Apr 2023 |
| Details of encumbrances concerned to FinanceFile: Declaration for Financial Encumbrances.pdf | 12 Apr 2023 |
| Details of encumbrances concerned to LegalFile: Declaration for Financial Encumbrances.pdf | 12 Apr 2023 |
| Declaration about Commencement CertificateFile: Declaration for Commencement Certificate.pdf | 12 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Bank Account.pdf | 12 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation for Allotment.pdf | 12 Apr 2023 |
| Layout approvalFile: PCMC Sanction Layout.pdf | 27 Mar 2023 |
| Layout approvalFile: scan007197.pdf | 27 Mar 2023 |
| Layout approvalFile: scan007199.pdf | 27 Mar 2023 |
| Layout approvalFile: scan007201.pdf | 27 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: PCMC Sanction Layout.pdf | 27 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: scan007197.pdf | 27 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: scan007199.pdf | 27 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: scan007201.pdf | 27 Mar 2023 |
| Building plan approvalFile: Regular Sanction plan layout 15-03-22.pdf | 18 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Regular Sanction plan layout 15-03-22.pdf | 18 Mar 2023 |
| Proforma of Agreement for saleFile: RERA ATS Wing C.pdf | 18 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report - Prayag C.pdf | 18 Mar 2023 |
| Copy of the legal title reportFile: Prayag Search Report.pdf | 27 Feb 2023 |
| Declaration in FORM BFile: Form B C wing Rera.pdf | 2 Feb 2023 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 2 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other Real Estate Orgn.pdf | 30 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate organization.pdf | 18 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: Form B AND Encumbrances Legal.pdf | 6 Jan 2023 |
| Details of encumbrances concerned to LegalFile: Form B AND Encumbrances Legal.pdf | 6 Jan 2023 |
| PAN CardFile: PAN.pdf | 5 Jan 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 15-03-2022.pdf | 5 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arichilture Certificate form 1 c building v square.pdf | 5 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg cert C Building.pdf | 5 Jan 2023 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Kamalraj PrayagP52100020219 | DATTA NAGAR | 208 | Mar 2019 | Certificate Signed | Apr 2025 | Not delivered |
| VIVANTA | SURVEY NO 11 HISSA NO 2B -1 PLOT NO 4 SIDDHANATHWADI TALUKA WAI DISTRICT SATARA | 32 | - | Completed | Jul 2017 | Jul 2017 |
| OLARK | SECTOR NO 9 PLOT NO 14 MOSHI PRADHIKARAN TALUKA HAVELI DISTRICT PUNE | 72 | - | Completed | Jul 2017 | Jul 2017 |
| OLARK | SECTOR NO 9 PLOT NO 14 MOSHI PRADHIKARAN TALUKA HAVELI DISTRICT PUNE | 72 | - | Completed | Jul 2017 | Jul 2017 |
| LAXMI ANAND | SURVEY NO 69 P CTS NO 1894 AT SANGHVI TAL HAVELI DIST PUNE | 24 | - | Completed | Jul 2017 | Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 54 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep KAMALRAJ PRAYAG C on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DIGHI
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
Kohinoor Viva Pixel- Phase II
RISING ASSOCIATES
VIVACITY
REALCON LANDMARKS LLP
TRIAA VASANTAM CITY CENTER PHASE 1
Triaa Realtors LLP
QUE 101 PHASE I
ANNR Unique Realty LLP
NYATI ERA I
NYATI CONSTRUCTION PRIVATE LIMITED
ONE ARETHA PHASE 1
Triaa Landmarks LLP
Builder: Kamalraj V Square Properties LLP
Kamalraj V Square Properties LLP has 2 registrations on MahaRERA, including Kamalraj Prayag and KAMALRAJ PRAYAG C. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record.
Frequently asked questions
What does it mean that KAMALRAJ PRAYAG C shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if KAMALRAJ PRAYAG C is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KAMALRAJ PRAYAG C?
The registered promoter entity is Kamalraj V Square Properties LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KAMALRAJ PRAYAG C?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KAMALRAJ PRAYAG C?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KAMALRAJ PRAYAG C?
The professionals named in the filing: Architect: SHASHANK PHADKE; Architect: PHADKE SHASHANK; Engineer: FIROZ PATHAN; Chartered Accountant: AGH AND ASSOCIATES; Chartered Accountant: C R LUNIYA AND COMPANY Luniya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KAMALRAJ PRAYAG C?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.