Home / Browse projects / Raigarh, Maharashtra / Kalista
Kalista
By Vihara Trinity Ventures LLP
RG-MH-34299 · RERA P52000048863 · Last updated on MahaRERA portal: 17 Oct 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kalista is a Plotted project by Vihara Trinity Ventures LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000048863 on 24 Jan 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 7 of the 50 units on this registration are recorded sold or booked.
At a glance
Project
- NameKalista
- TypePlotted
- Location
- Neral Road
- Vanjarpada
- Karjat
- Wanjarpada
- Karjat
- Raigarh
- 410101
- Pincode410101
- RERA no.P52000048863
- ReraGenie IDRG-MH-34299
Builder
- NameVihara Trinity Ventures LLP
- Entity typePartnership
- PartnersDipakkumar Arjan Suthar, Dharmesh Praful Chavan, Vijayshree Jagganath Shetty
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Jan 2023
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2025)
- BuildingsNot stated in filing
- Documents filed74 files
Current status
Figures as on 17 Oct 2025, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 17 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 5% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Saiprasad Suresh Parte | Mira-Bhayandar (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | The Design India |
| Engineer | The Design India |
| Chartered Accountant | Rutuja Narsingh and Associates |
| Chartered Accountant | Gaurav S Rajpal |
| Partner | Role in project |
|---|---|
| Vihara Trinity Ventures LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31/12/2027. to complete the project and fulfil all regulatory requirements.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jan 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Jan 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Jan 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed74
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 March 2025.pdf | 17 Oct 2025 |
| Form 2File: Form 2 - March 2025.pdf | 17 Oct 2025 |
| Form 3File: Form 3- March 2025.pdf | 17 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Kalista.pdf | 17 Oct 2025 |
| Declaration in FORM BFile: Form B.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 2024.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2024.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 MAr 2023.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 2023.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 2023.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2023.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar 2024.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 2024.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 2023.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2024.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 2024.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2024.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2024.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 2024.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 2023.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2023.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 2023.pdf | 8 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2023.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2024.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2024.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 2024.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 2024.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2023.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 2023.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2023.pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 2023.pdf | 8 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 8 Apr 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 8 Apr 2025 |
| Other - TechnicalFile: PERT Chart.pdf | 8 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 8 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf | 8 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf | 8 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalista as on Sept 2024.pdf | 25 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalista as on 30th Sept 2023.pdf | 6 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalista as on 31st December 2023.pdf | 6 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Format Form 3 - Kalista as on 30-09-2023.pdf | 6 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Kalista- as on 31st Dec 2023 Final.pdf | 6 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mar 23.pdf | 23 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jun 23.pdf | 23 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 23.pdf | 23 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kalista 30-09-2023.pdf | 15 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalista as on 31-03-2023.pdf | 15 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kalista as on 30-06-2023.pdf | 15 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalista as on 31-03-2023.pdf | 15 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalista as on 30-06-2023.pdf | 15 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Format Form 5 Kalista FY2022-23.pdf | 15 Dec 2023 |
| Copy of the legal title reportFile: Short title-Kalista Vihara Trinity 14 01 2023.pdf | 14 Jan 2023 |
| Declaration about Commencement CertificateFile: Scan2023-01-14 Final Format D.pdf | 14 Jan 2023 |
| Proforma of Agreement for saleFile: AFS.pdf | 14 Jan 2023 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 14 Jan 2023 |
| Deviation Report with respect to Allotment letterFile: 1 Deviation Report with respect to model copy of Agreement (8).pdf | 14 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to Allotment letter (4).pdf | 14 Jan 2023 |
| Other - LegalFile: DECLARATION.pdf | 14 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCE - FINANCE.pdf | 13 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCE LEGAL.pdf | 13 Jan 2023 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCE - FINANCE.pdf | 13 Jan 2023 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCE LEGAL.pdf | 13 Jan 2023 |
| Declaration in FORM BFile: 1 Declaration in FORM B (2).pdf | 13 Jan 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200257408164_For_Asset_Based_Search_12_01_2023_13_03_27_395.pdf | 13 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form -3.pdf | 13 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A- SEPERATE BANK ACCOUNT.pdf | 13 Jan 2023 |
| PAN CardFile: Vihara Trinity Ventures LLP- Pancard.pdf | 9 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A.pdf | 9 Jan 2023 |
| Layout approvalFile: Plan.pdf | 3 Jan 2023 |
| Building plan approval or NA orderFile: Plan.pdf | 3 Jan 2023 |
| Copy of Layout Approval (in case of layout)File: Plan.pdf | 3 Jan 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan.pdf | 3 Jan 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC_compressed.pdf | 3 Jan 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 74 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Kalista on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vanjarpada, Karjat5,900+ in Raigarh
ForeverLand
HOABL IMPACTUM LAND PRIVATE LIMITED
Chitrapatjanak Dadasaheb Phalke Township - Pha
Anukarati Homes Pvt Ltd
Olympeo Neo City
PRIZTINE INFRA LLP
DEEPJYOTI CITY
DeepJyoti Infra
VISION AARAMBH
M/s Vision Aarambh ( AOP )
Olympeo Riverside - Phase 3
Olympeo Riverside Projects LLP
See every Raigarh project, with the district possession charts
Builder: Vihara Trinity Ventures LLP
Vihara Trinity Ventures LLP has 1 registration on MahaRERA, including Kalista. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Kalista is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kalista?
The registered promoter entity is Vihara Trinity Ventures LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kalista?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kalista?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kalista?
The professionals named in the filing: Architect: The Design India; Engineer: The Design India; Chartered Accountant: Rutuja Narsingh and Associates; Chartered Accountant: Gaurav S Rajpal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kalista?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback