Home / Browse projects / Mumbai City, Maharashtra / KALAYA TOWER

Completed No litigation declared Others project

KALAYA TOWER

By Akruti Developers and Builders

RG-MH-60854 · RERA P51900034579 · Last updated on MahaRERA portal: 6 Apr 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 17 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
52 of 64Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

KALAYA TOWER is a Others project by Akruti Developers and Builders in Mumbai City, Maharashtra, registered with MahaRERA as P51900034579 on 11 Apr 2022. The registration is recorded completed; possession was promised by 30 Jun 2026. The completion date has moved by 17 months from the original filing. 12 of the 64 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameKALAYA TOWER
  • TypeOthers
  • Location
    • Khed Galli
    • Prabhadevi Dadar
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900034579
  • ReraGenie IDRG-MH-60854

Builder

  • NameAkruti Developers and Builders
  • Entity typePartnership
  • PartnersSACHIN KALYAN PONDKULE, VINAY HEMANNA PAWALI, GANESH GOPAL JOSHI, AMIT MAHIPAT SAWANT

Key dates

this monthRegisteredApr 2022First promiseJan 2025Revised toJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Apr 2022
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 15 Jan 2025)
  • Buildings1 building record
  • Documents filed74 files

Current status

19%12 of 64 units booked
134.2%Work done, per cost certificate

Figures as on 6 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KALAYA TOWERNA232061364

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

KALAYA TOWER: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 6 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered32

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area558 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Sep 2025

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI3688.83
Proposed, not sanctioned3,689 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCBD BELAPUR NAVI MUMBAI
Estimated costRs 21.43 cr
Cost incurredRs 28.74 cr
Work done134.16%
BuildingWingEstimatedIncurred
KALAYA TOWERNARs 21.43 crRs 28.74 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAP ASSOCIATES
EngineerAmit Narendra Pradhan
Chartered AccountantAadil Ansari
Chartered AccountantR H Pothiwal & Associates
Chartered AccountantSachin K. Mishra & Co.
PartnerRole in project
Akruti Developers and Builders-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900027405Jan 2025 → Jul 2025

Reason as filed by the promoterDue to some cirmcatanse we are unble to complete our project i. e. we require extension till 30 July 2025

EA16102518141Jan 2025 → Jun 2026

Reason as filed by the promoter- Delay in receiving statutory approvals (e.g., environmental clearance, building permissions). - Financial constraints or funding delays. - Pandemic-related disruptions (e.g., COVID-19). - Litigation or legal disputes affecting project progress. - Material or labor shortages. - Infrastructure dependencies (e.g., road access, utilities). - Force Majeure: Natural calamities, war, floods, droughts, fire, or any other situation beyond the control of the promoter. - Reasonable Circumstances: Even without promoter default, if justified and documented, MahaRERA may grant an extension based on case-s

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12600797Dinesh Pratapchand JainAkruti Developers and Builders12/02/2026
CC12601176ATUL AVINASH JOSHIAkruti Developers and Builders03/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1.pdf6 Apr 2026
Withdrawal Update Form 2File: Form-2.pdf6 Apr 2026
Withdrawal Update Form 3File: Form-3.pdf6 Apr 2026
Occupational CertificateFile: FULL OCCUPATION CERTIFICATE.pdf6 Apr 2026
Occupational CertificateFile: FULL OCCUPATION CERTIFICATE PLAN.pdf6 Apr 2026
Form 5 (FY 2024-2025)File: Form 5 FY 2024-25.pdf14 Nov 2025
Form 2A (FY 2022-2023)File: Form 2A_March 23.pdf11 Nov 2025
Form 2A (FY 2023-2024)File: Form 2A_March 24.pdf11 Nov 2025
Form 2A (FY 2024-2025)File: Form 2A_March 25.pdf11 Nov 2025
Form 5 (FY 2022-2023)File: Form 5 FY 2022-23.pdf11 Nov 2025
Form 5 (FY 2023-2024)File: Form 5 FY 2023-24.pdf11 Nov 2025
Withdrawal Update Form 1File: Architect Certificate - Sep 25.pdf30 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate - Sep 25.pdf30 Oct 2025
Withdrawal Update Form 3File: CA Certificate_Jun-25.pdf30 Oct 2025
Withdrawal Update Form 1File: Architect Certificate - Jun-25.pdf14 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate - Jun 25.pdf14 Oct 2025
Withdrawal Update Form 3File: CA Certificate_Jun-25.pdf14 Oct 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory.pdf18 Mar 2025
Other - TechnicalFile: Certifcate of Work of updation details.pdf18 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations_compressed.pdf18 Mar 2025
Declaration in FORM BFile: Kalaya Tower Form B.pdf6 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_22-23.pdf6 Mar 2025
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal.pdf3 Feb 2025
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance.pdf3 Feb 2025
Declaration in FORM BFile: Form B_compressed.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf3 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Separate Bank Account Declaration.pdf3 Feb 2025
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance.pdf3 Feb 2025
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf3 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A FY-22-23.pdf3 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY-23-24.pdf3 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Dec24 - converted.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Dec 24.pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Dec 24.pdf25 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold inventory_Dec 24.pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-March 23.pdf19 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-March 24.pdf19 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-June 24.pdf19 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Sep 24.pdf19 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_2022-23.pdf19 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_2023-24.pdf19 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_June 24.pdf19 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Sep 24.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Sept 24.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_June 24.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 24.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_March 23.pdf19 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Audit Report_2022-23.pdf19 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Audit Report_2023-24.pdf19 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 f y 22-23.pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate (1)_compressed.pdf4 Apr 2022
OtherFile: DA 3_compressed.pdf1 Apr 2022
OtherFile: DA 4_compressed.pdf1 Apr 2022
OtherFile: PA 3_compressed.pdf1 Apr 2022
OtherFile: PA 4_compressed.pdf1 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200233678495_For_Asset_Based_Search_28_03_2022_17_19_59_993.pdf29 Mar 2022
Copy of the legal title reportFile: Titlereport 1 (2).pdf23 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC_signed.pdf23 Mar 2022
Proforma of Allotment letterFile: Draft Agreement_RERA_Kalaya Tower.pdf12 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: 17 - CC.pdf9 Feb 2022
OtherFile: Revalidation Issue Letter.pdf9 Feb 2022
OtherFile: 16 - IOD.pdf9 Feb 2022
Details of encumbrancesFile: Encumbrance Certificate.pdf31 Jan 2022
Declaration about Commencement CertificateFile: Deceleration Format D.pdf31 Jan 2022
Declaration in FORM BFile: Notary Form B declaration-compressed.pdf31 Jan 2022
Layout approvalFile: Akruti Plan 1.pdf24 Jan 2022
Building plan approvalFile: CC.pdf24 Jan 2022
Copy of the legal title reportFile: title certificate joshi(1)-compressed.pdf24 Jan 2022
Copy of Layout Approval (in case of layout)File: Akruti Plan 1.pdf24 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: CC.pdf24 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf24 Jan 2022
CERSAI detailsFile: RPM_MCHI_519000_MUM_1089.pdf24 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3.pdf24 Jan 2022
PAN CardFile: AKRUTI PAN CARD.pdf15 Jan 2022

How this compares with Mumbai City

19%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 17 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is completed

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KALAYA TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Prabhadevi Dadar780+ in Mumbai City

2 kmKALAYA TOWERCompleted 56Lapsed / revoked 56Other 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 196 registered projects within 2 km.

Builder: Akruti Developers and Builders

Akruti Developers and Builders has 1 registration on MahaRERA, including KALAYA TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if KALAYA TOWER is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KALAYA TOWER?

The registered promoter entity is Akruti Developers and Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KALAYA TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KALAYA TOWER?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KALAYA TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KALAYA TOWER?

The professionals named in the filing: Architect: SAP ASSOCIATES; Engineer: Amit Narendra Pradhan; Chartered Accountant: Aadil Ansari; Chartered Accountant: R H Pothiwal & Associates; Chartered Accountant: Sachin K. Mishra & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KALAYA TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KALAYA TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KALAYA TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.