ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai City, Maharashtra / Kakad West End

Completed No litigation declared Residential / Group Housing project

Kakad West End

By Kakad Realty Pvt Ltd

RG-MH-09331 · RERA P51900003122 · Last updated on MahaRERA portal: 17 Mar 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 19 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Jan 2024Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

Kakad West End is a Residential / Group Housing project by Kakad Realty Pvt Ltd in Mumbai City, Maharashtra, registered with MahaRERA as P51900003122 on 4 Aug 2017. The registration is recorded completed; possession was promised by 8 Jan 2024. The completion date has moved by 19 months from the original filing.

At a glance

Project

  • NameKakad West End
  • TypeResidential / Group Housing
  • Location
    • Mumbai City
    • 400020
  • Pincode400020
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900003122
  • ReraGenie IDRG-MH-09331

Builder

  • NameKakad Realty Pvt Ltd
  • Entity typeCompany
  • Managing DirectorsKunal Kakad, Malav Kakad

Key dates

this monthRegisteredAug 2017First promiseJun 2022Revised toJan 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Aug 2017
  • Promised completion8 Jan 2024
  • Revised completionRevised to 8 Jan 2024 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kakad West EndNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Kakad West End: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed37

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots37
Closed/Covered37

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area758 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Bhairavi CHS LtdAndheriMumbai Suburban

Approvals and building plan

Permissible FSI2150.0
Proposed, not sanctioned754 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLinking Road Khar West

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjay Mane
EngineerSurendra Velji Patel
EngineerBipinkumar Sanghvi
PartnerRole in project
Kakad Realty Pvt Ltd-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900011652Jun 2022 → Jun 2023

Reason as filed by the promoterPlease see Explanatory Note for Reasons of Delay uploaded in "Other" Section below due to constraints of space.

EXT51900016685Jun 2022 → Sep 2023

Reason as filed by the promoterPlease find attached our explanatory note for a nominal extension of 3 months since Project is almost complete.

EXT51900017669Jun 2022 → Jan 2024

Reason as filed by the promoterTo, The Concerned Officer, Maharashtra Real Estate Regulatory Authority 6th & 7th Floor, Housefin Bhavan, Plot No. C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400051 Subject: Request for Post Facto Extension of the RERA Registration date to align with the OC date for Project MahaRera Reg No P51900003122. Dear Sir/Madam, We are writing to formally request an Post Facto extension of the project completion timeline for Kakad West End, located at Bhardawadi Lane, Andheri West, Maharashtra. We have uploaded and submitted all documents that are required for us to be fully compliant i

Litigation declared1

CaseCourtStatus
1494/2010Bombay High CourtPre admission Stage

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Jan 2024

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - LegalFile: Declaration.pdf17 Mar 2025
Status of ConveyanceFile: Declaration.pdf17 Mar 2025
Other - FinanceFile: Declaration.pdf17 Mar 2025
Other - TechnicalFile: Declaration.pdf17 Mar 2025
Foreclosure of the ProjectFile: Declaiation.pdf17 Mar 2025
Home Buyer /Allottee Grievance Redressal CellFile: Declaration.pdf17 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Declaration.pdf17 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Declaration.pdf17 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 KWE jan 24.pdf13 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: KRPL Form 5 signed for FY 23-24.pdf13 Mar 2025
Certificates of CA (Form 3)File: Form 3 KWE Dec 23.pdf25 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: KWE OC 08012024.pdf16 Jan 2024
Certificates of CA (Form 3)File: KWE Form 3 Sept 23.pdf7 Nov 2023
Certificates of CA (Form 3)File: FORM 3 KWE_compressed.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 for FY 2022-23 KWE.pdf11 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 KWE Sept 23.pdf28 Sep 2023
Certificates of CA (Form 3)File: Form 3.pdf3 Jun 2023
Declaration in FORM BFile: Affidavit cum declaration for Form B.pdf2 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf2 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf2 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf2 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Booked Inventory.pdf2 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclorure of booked lnventory.pdf2 Jun 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Declaration.pdf26 May 2023
Details of encumbrances concerned to LegalFile: Encumbrance Declaration.pdf26 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 KWE Aug 2022.pdf26 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest RERA MK.pdf26 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest RERA KK.pdf26 May 2023
Proforma of Agreement for saleFile: draft agreement-KWE.pdf26 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Declaration.pdf26 May 2023
Deviation Report with respect to Allotment letterFile: Allotment Deviation.pdf26 May 2023
Deviation Report with respect to model copy of AgreementFile: draft agreement-KWE.pdf26 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Signed Form 5 for FY 21-22.pdf17 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Revalidated CC KWE.pdf29 Mar 2022
Declaration about Commencement CertificateFile: CC Declaration.pdf25 Mar 2022
Disclosure of sold/ booked inventoryFile: Declaration.pdf25 Mar 2022
CERSAI detailsFile: CERSAI Declaration.pdf25 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: KRPL Form 5 19-20.pdf3 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: KRPL Form 5 20-21_compressed.pdf3 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Proposed work of KWE dt 1st Aug 2020.pdf11 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Proposed work of KWE dt 3rd Aug 2021.pdf11 Aug 2021
Proforma of Allotment letterFile: KWE RERA AFS .pdf25 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form513112019.pdf15 Nov 2019
Certificates of CA (Form 5)File: KRPL FORM 5 for 2017-18.pdf16 Nov 2018
Status of Formation of Legal EntityFile: Annexure A.pdf23 Mar 2018
Layout approvalFile: Declaration for Layout.pdf28 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate - KRPL.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Declaration for Layout.pdf28 Jul 2017
Declaration in FORM BFile: KRPL Form B Declaration.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate KWE.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate KWE.pdf28 Jul 2017
Certificates of CA (Form 3)File: Rera - Kakad Realty.pdf28 Jul 2017
Proforma of Allotment letterFile: KRPL Decaration for NO AGREEMENT AND ALLOTMENT.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Revalidation receipt.pdf26 Jul 2017
Building plan approvalFile: IOD of KWE.pdf6 Jul 2017
PAN CardFile: KRPL Pan Card.pdf6 Jul 2017
Copy of the legal title reportFile: Title Certificate KWE.pdf6 Jul 2017
Building Plan Approval (IOD)File: IOD of KWE.pdf6 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC of KWE.pdf6 Jul 2017

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 19 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is completed

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kakad West End on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mumbai City780+ in Mumbai City

2 kmKakad West EndCompleted 10Lapsed / revoked 3Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: Kakad Realty Pvt Ltd

Kakad Realty Pvt Ltd has 1 registration on MahaRERA, including Kakad West End. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if Kakad West End is delayed beyond 8 Jan 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kakad West End?

The registered promoter entity is Kakad Realty Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kakad West End?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kakad West End?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kakad West End?

The professionals named in the filing: Architect: Ajay Mane; Engineer: Surendra Velji Patel; Engineer: Bipinkumar Sanghvi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kakad West End?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kakad West End. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kakad West End to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.