Home / Browse projects / Mumbai Suburban, Maharashtra / KAATYAYNI HEIGHTS TOWER 2 PHASE 2

Registration lapsed No litigation declared Residential / Group Housing project

KAATYAYNI HEIGHTS TOWER 2 PHASE 2

By STARWING DEVELOPERS PRIVATE LIMITED

RG-MH-03096 · RERA P51800020411 · Last updated on MahaRERA portal: 18 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
29 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 0%
42 of 161Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

KAATYAYNI HEIGHTS TOWER 2 PHASE 2 is a Residential / Group Housing project by STARWING DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800020411 on 9 Apr 2019. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 6 months from the original filing. 119 of the 161 units on this registration are recorded sold or booked, and 29 of 33 construction stages are filed complete.

At a glance

Project

  • NameKAATYAYNI HEIGHTS TOWER 2 PHASE 2
  • TypeResidential / Group Housing
  • Location
    • Near Sona Udyog Bhavan
    • Parsi Panchayat Road
    • Andheri (East) Mumbai: 400053
    • ANDHERI EAST
    • Andheri
    • Mumbai Suburban
    • 400053
  • Pincode400053
  • RERA no.P51800020411
  • ReraGenie IDRG-MH-03096

Builder

  • NameSTARWING DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorRAJEEV RAMESHKUMAR DUBE
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

16 months past promisethis monthRegisteredApr 2019First promiseDec 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Apr 2019
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2024)
  • Buildings3 building records
  • Documents filed84 files

Current status

74%119 of 161 units booked

Figures as on 18 Apr 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KAATYAYNI HEIGHTS TOWER 2 PHASE 2 A WINGNA262377077
KAATYAYNI HEIGHTS TOWER 2 PHASE 2 B WINGNA262358058
PARKING TOWERNA262302626

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 18 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 0%.

KAATYAYNI HEIGHTS TOWER 2 PHASE 2 A WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
KAATYAYNI HEIGHTS TOWER 2 PHASE 2 B WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PARKING TOWER82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed260

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots260
Closed/Covered260

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,748 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Jul 2025

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI9866.51
Proposed, not sanctioned619 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMULUND

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMS DP
ArchitectSTUDIODP
EngineerSUSHIL TRIPATI
Chartered AccountantROHIT JHA
PartnerRole in project
STARWING DEVELOPERS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800027365Dec 2024 → Jun 2025

Reason as filed by the promoterThis has reference to your telephonis query, whereby you had sought our explanation about inordinate delay in issue of Occupation Permission to the las wing of Sale building in above referred project. Our explanation is as under: We had applied for final fire NOC for the building on 07/08/2023. The same was issued by the Mumbai Fire Brigade only on 02/12/2023. We had submitted BCC and applied for Occupation Permission to SRA on 15/09/2023, upon completion of construction work and compliance of maximum LOI/I0A conditions. The application is processed by the department, however Occupation Permis

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Sep 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Jun 2023

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: form 3.pdf18 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf18 Apr 2025
Declaration in FORM BFile: P51800020411_FileName_3.pdf28 Feb 2025
Disclosure of sold/ booked inventoryFile: inventory disclosure (3).pdf28 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf20 Jan 2025
Certificates of CA (Form 3)File: form 3.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf20 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf13 Jan 2025
Certificates of CA (Form 3)File: form 3.pdf13 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf13 Jan 2025
Declaration about Commencement CertificateFile: CC COVERING LETTER.pdf13 Jan 2025
CERSAI detailsFile: CERSAI_Acknowledgemnt__Kaatyayni Heights.pdf13 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A (quality assurance)_FY 2022-23.pdf13 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_CA Certificate_FY 2022-23.pdf13 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf13 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_CA Certificate_FY 2023-24.pdf13 Jan 2025
Certificates of CA (Form 3)File: form 3 jan to march 24.pdf7 Nov 2024
Certificates of CA (Form 3)File: form 3 april to june 24.pdf7 Nov 2024
Certificates of CA (Form 3)File: form 3 july to sep 24.pdf7 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1architect certificate DEC23.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2ENGINEER CERTIFICATE DEC23.pdf12 Jan 2024
Certificates of CA (Form 3)File: FORM 3 CA certificate DEC23.pdf12 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf2 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf2 Nov 2023
Certificates of CA (Form 3)File: form 3.pdf2 Nov 2023
Certificates of CA (Form 3)File: CA certificate KH Phase 2 31032023.pdf25 Jul 2023
Certificates of CA (Form 3)File: CA certificate KH Phase 2 300623 revised.pdf25 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate Phase-2_30-06-2023.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE Maha RERA 30062023.pdf14 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Mogra Tower 2 A wing OC.pdf6 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate Phase-2_31-03-2023.pdf9 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate KH T2 31-03-2023.pdf8 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20 Phase-2.pdf6 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21 Phase-2.pdf6 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22 Phase-2.pdf6 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer form 2A_Old format_FY 2020-21.pdf3 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer form 2A_New format_FY 2021-22.pdf3 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate Phase 2 31-12-2022.pdf24 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate KH T2 31-12-2022.pdf23 Feb 2023
Certificates of CA (Form 3)File: CA certificate KH Phase 2 31122022.pdf23 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate Phase-2.pdf18 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KH phase 2engineer certificate.pdf18 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Phase-2.pdf10 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate_Phase-2.pdf10 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf23 Oct 2021
Certificates of CA (Form 3)File: Form 3 Phase 2_com.pdf23 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE T2_compressed.pdf21 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 31-07-2021_compressed.pdf19 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase 2 30062021 (1)_compressed.pdf19 Aug 2021
Certificates of CA (Form 3)File: RERA PHASE II_19082021_compressed (1).pdf19 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate KH T.pdf15 Apr 2021
Certificates of CA (Form 3)File: FORM-3 SDPL Phase II.pdf15 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH PH 2.pdf4 Dec 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG PHASE 2.pdf4 Dec 2020
Certificates of CA (Form 3)File: CA PHASE 2.pdf4 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf31 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf31 Jul 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf31 Jul 2020
Certificates of CA (Form 3)File: CA.pdf31 Jul 2020
Details of Restarting of Construction work post lockdownFile: Project Status Due to Covid Phase 2.pdf6 Jul 2020
Certificates of CA (Form 3)File: CA PHASE 2_compressed.pdf25 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf23 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG.pdf23 Jan 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A.pdf23 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH P2.pdf19 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG P2.pdf19 Oct 2019
Certificates of CA (Form 3)File: CA PHASE 2 COMP.pdf18 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf10 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf5 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG.pdf31 Jul 2019
Certificates of CA (Form 3)File: CA.pdf31 Jul 2019
Details of encumbrancesFile: Tata encumbrance.pdf30 Jul 2019
Building plan approvalFile: IOD COMP.pdf6 Apr 2019
Layout approvalFile: LAYOUT PLAN.pdf6 Apr 2019
Copy of the legal title reportFile: title 01.pdf6 Apr 2019
Copy of the legal title reportFile: title 02.pdf6 Apr 2019
Details of encumbrancesFile: NO ENCUMBRANCE.pdf6 Apr 2019
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf6 Apr 2019
Building Plan Approval (IOD)File: IOD COMP.pdf6 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.PDF6 Apr 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
KAATYAYNI ENCLAVE A AND C WINGVAKOLA SANTACRUZ EAST66CompletedMay 2013May 2013

How this compares with Mumbai Suburban

74%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 6 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KAATYAYNI HEIGHTS TOWER 2 PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ANDHERI EAST6,700+ in Mumbai Suburban

Builder: STARWING DEVELOPERS PRIVATE LIMITED

STARWING DEVELOPERS PRIVATE LIMITED has 6 registrations on MahaRERA, including APURVA RESIDENCIES and KAATYAYNI ENCLAVE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that KAATYAYNI HEIGHTS TOWER 2 PHASE 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KAATYAYNI HEIGHTS TOWER 2 PHASE 2 is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KAATYAYNI HEIGHTS TOWER 2 PHASE 2?

The registered promoter entity is STARWING DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KAATYAYNI HEIGHTS TOWER 2 PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KAATYAYNI HEIGHTS TOWER 2 PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KAATYAYNI HEIGHTS TOWER 2 PHASE 2?

The professionals named in the filing: Architect: MS DP; Architect: STUDIODP; Engineer: SUSHIL TRIPATI; Chartered Accountant: ROHIT JHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KAATYAYNI HEIGHTS TOWER 2 PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KAATYAYNI HEIGHTS TOWER 2 PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KAATYAYNI HEIGHTS TOWER 2 PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.