Home / Browse projects / Raigarh, Maharashtra / Jindal Aura
Jindal Aura
By Jindal Builders and Developers
RG-MH-23254 · RERA P52000078562 · Last updated on MahaRERA portal: 9 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 4 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 6 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Jindal Aura is a Residential / Group Housing project by Jindal Builders and Developers in Raigarh, Maharashtra, registered with MahaRERA as P52000078562 on 27 Dec 2024. Possession is promised by 31 Dec 2027. 9 of the 21 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameJindal Aura
- TypeResidential / Group Housing
- Location
- Survey no 743/8/Plot no 1
- Panvel City
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000078562
- ReraGenie IDRG-MH-23254
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on27 Dec 2024
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed69 files
Current status
Figures as on 9 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Jindal Aura | NA | 8 | 7 | 21 | 0 | 21 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.
Jindal Aura: 55% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
Progress on shared amenities15
As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed22
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Jindal Aura | NA | Rs 3.63 cr | Rs 2.63 cr |
| - | NA | Rs 42.20 lakh | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | O7 Associates |
| Engineer | SAMARTH AGARWAL |
| Engineer | MADAN KUMAR SRIVASTAVA |
| Chartered Accountant | Naina Jain |
| Chartered Accountant | SAMARPIT GANESH PINGALE |
| Partner | Role in project |
|---|---|
| Jindal Builders and Developers | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Oct 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Oct 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed69
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 JINDAL AURA.pdf | 9 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 JINDAL AURA.pdf | 9 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Jindal Aura.pdf | 9 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Jindal Aura.pdf | 9 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Jindal Aura.pdf | 9 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Jindal Aura.pdf | 9 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A Jindal Aura.pdf | 7 May 2026 |
| Withdrawal Update Form 1File: Jindal Aura Form 1.pdf | 8 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 JINDAL AURA.pdf | 8 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Jindal Aura.pdf | 8 Apr 2026 |
| Withdrawal Update Form 1File: Architect Certificate Jindal Aura.pdf | 14 Jan 2026 |
| Withdrawal Update Form 2File: JINAL AURA - FORM 2.pdf | 14 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 Jindal Aura.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Jindal Aura.pdf | 11 Oct 2025 |
| Withdrawal Update Form 2File: Form-2 Jindal Aura.pdf | 11 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Jindal Aura.pdf | 11 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Aura.pdf | 22 Sep 2025 |
| Form 1File: Jindal Aura Form 1 Q4 FY 24-25.pdf | 21 Jul 2025 |
| Form 2File: Jindal Aura Form 2 Q4 FY 24-25.pdf | 21 Jul 2025 |
| Form 3File: Form 3 Jindal Aura Q4 FY 24 25.pdf | 21 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory- Aura Q1 25-26.pdf | 21 Jul 2025 |
| Withdrawal Update Form 1File: FORM 1 AURA Q1 25-26.pdf | 21 Jul 2025 |
| Withdrawal Update Form 1File: FORM 1 AURA Q1 25-26.pdf | 21 Jul 2025 |
| Withdrawal Update Form 2File: FORM 2 JINDAL AURA Q1 25-26.pdf | 21 Jul 2025 |
| Withdrawal Update Form 2File: FORM 2 JINDAL AURA Q1 25-26.pdf | 21 Jul 2025 |
| Withdrawal Update Form 3File: Aura Form3.pdf | 21 Jul 2025 |
| Withdrawal Update Form 3File: Aura Form3.pdf | 21 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jindal Aura Q4 FY 24 25.pdf | 16 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jindal Aura Form 1 Q4 FY 24-25.pdf | 9 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jindal Aura Form 2 Q4 FY 24-25.pdf | 9 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Jindal Aura Form - 2 A 310325.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jindal Aura Form 1 Q3 FY 24 25Final.pdf | 10 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Jindal Aura Form 3 Q3 FY 24-25 Final.pdf | 10 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jindal Aura Form 2 Q3 FY 24 25 Final.pdf | 10 Jan 2025 |
| Deviation Report with respect to model copy of AgreementFile: Sale Agreement Deviation Final 1.pdf | 18 Dec 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Sheet Part 2.pdf | 18 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 24 25 Jindal Aura.pdf | 9 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jindal Aura Fy 24 25.pdf | 9 Dec 2024 |
| Other - TechnicalFile: Annexure A.pdf | 9 Dec 2024 |
| Other - TechnicalFile: RERA MAIL from PMC dated 09 12 24.pdf | 9 Dec 2024 |
| Building plan approvalFile: Aura Plan.pdf | 7 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: RENEWAL CC 743-8-1_20241206_0001.pdf | 7 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Aura Plan.pdf | 7 Dec 2024 |
| Other - LegalFile: Land Purchase Document Jindal Aura compressed.pdf | 7 Dec 2024 |
| Other - LegalFile: Jindal Aura 7 12.pdf | 7 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf | 13 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jindal Aura Fy 24 25.pdf | 9 Nov 2024 |
| Proforma of Agreement for saleFile: Revised Final Draft Agg 743 8 Plot No 1.pdf | 9 Nov 2024 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 24 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jindal Aura.pdf | 24 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A ASA.pdf | 24 Oct 2024 |
| Building plan approvalFile: CC_compressed.pdf | 23 Oct 2024 |
| Layout approvalFile: CC Plan_compressed.pdf | 23 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: Self Declaration legal and Financial.pdf | 23 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: CC Plan_compressed.pdf | 23 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC_compressed.pdf | 23 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: CC_compressed.pdf | 23 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: JBD Bank Format A.pdf | 23 Oct 2024 |
| Deviation Report with respect to Allotment letterFile: Allotment Letter Deviation.pdf | 23 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Self Declaration legal and Financial.pdf | 23 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A SSA.pdf | 23 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A SOA.pdf | 23 Oct 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: IDBI Bank format B.pdf | 23 Oct 2024 |
| PAN CardFile: 1 PAN Card.pdf | 22 Oct 2024 |
| Copy of the legal title reportFile: Title and Search.pdf | 22 Oct 2024 |
| Declaration in FORM BFile: Form B Aura.pdf | 22 Oct 2024 |
| Declaration about Commencement CertificateFile: Format D.pdf | 22 Oct 2024 |
| CERSAI detailsFile: CERSAI Report.pdf | 22 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Loan encumbrance.pdf | 22 Oct 2024 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Jindal LegacyP52000054929 | Sai Nagar, Raigarh | 189 | Feb 2024 | Certificate Signed | Mar 2027 | Jan 1970 |
| Jindal ImperiaP52000053510 | Kasbe, Raigarh | 133 | Nov 2023 | Certificate Signed | Mar 2027 | Jan 1970 |
| Jindal EnclaveP52000054516 | Kasbe, Raigarh | 153 | Jan 2024 | Certificate Signed | Mar 2027 | Jan 1970 |
| Jindal AvenueP52000031962 | PANVEL, Raigarh | - | Nov 2021 | Certificate Signed | Dec 2024 | Jan 1970 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 69 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Jindal Aura on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Panvel City5,900+ in Raigarh
Filed coordinates, straight-line distance. 394 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: Jindal Builders and Developers
Jindal Builders and Developers has 7 registrations on MahaRERA, including JINDAL RESIDENCY and Sakasi Park III. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Jindal Aura is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Jindal Aura?
The registered promoter entity is Jindal Builders and Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Jindal Aura?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Jindal Aura?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Jindal Aura?
The professionals named in the filing: Architect: O7 Associates; Engineer: SAMARTH AGARWAL; Engineer: MADAN KUMAR SRIVASTAVA; Chartered Accountant: Naina Jain; Chartered Accountant: SAMARPIT GANESH PINGALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Jindal Aura?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback