Jay Krishna
By Shreegoandevi Enterprises Private Limited
RG-MH-67613 · RERA P51800010788 · Last updated on MahaRERA portal: 16 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 48 months
- 3 extensions taken
- Rs 33.40 crore secured on the land, in favour of Axis Trustee Services Ltd
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Jay Krishna is a Residential / Group Housing project by Shreegoandevi Enterprises Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010788 on 31 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 48 months from the original filing. 87 of the 200 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameJay Krishna
- TypeResidential / Group Housing
- Location
- JANGAL MANGAL ROAD
- Kurla
- Mumbai Suburban
- 400078
- Pincode400078
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800010788
- ReraGenie IDRG-MH-67613
Builder
- NameShreegoandevi Enterprises Private Limited
- Entity typeCompany
- CINU70109MH2022PTC392044
- GSTIN27ABJCS5661G1Z0
- DirectorsPREMJI NARAN PATEL karta Patel, DINESH PREMJI PATEL Patel, RASILA DINISH PATEL PATEL
- PartnerNAVALBEN PREMJI PATEL Patel
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed309 files
Current status
Figures as on 16 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JAY KRISHNA | NA | 35 | 35 | 162 | 38 | 200 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.
JAY KRISHNA: 84% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 93% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 85% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 83% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 40% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 80% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 55% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 51.93 cr | Rs 20.40 cr |
| JAY KRISHNA | NA | Rs 16.65 cr | Rs 16.65 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Amol Manohar Kaphale |
| Architect | Manohar M. Kalpesh & Associates |
| Engineer | Associated Structural Engineers LLP |
| Engineer | Rohit Chavan |
| Chartered Accountant | Shripati Gandhi Chaudhari and Co |
| Chartered Accountant | Shripati Gandhi Choudhari & Co |
| Chartered Accountant | Kapure & Kapure |
| Chartered Accountant | Rahul Bera |
| Partner | Role in project |
|---|---|
| Shreegoandevi Enterprises Private Limited | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe seek extension of one year for due date of completion of the project that is 29/12/2023. As per the current progress of the work and situation of the statutory approvals, we shall require some more time to complete the project. 1. Hence, we request you to kindly grant us an extension of One year that is from 30/12/2022 to 29/12/2023. 2. We undertake to comply with all the Statutory Compliances with respect to MahaRERA during the extended period.
Reason as filed by the promoterAs per attachment
Reason as filed by the promoterWe are applying order bearing number 40/2022 dated 22nd December 2022 issued by the Maharashtra Real Estate Regulatory Authority “(MahaRERA)” that is extension without consent.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jun 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed309
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 309 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form1 - 2026 - 3rd July 2026.pdf | 16 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - ASC - 15th July 2026.pdf | 16 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Signed_merged.pdf | 16 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A - 2026.pdf | 7 Jul 2026 |
| Form 5 (FY 2023-2024)File: Form 5 FY 2023-24_page-0001.pdf | 6 Jul 2026 |
| Form 5 (FY 2024-2025)File: Form 5 FY 2024-25_page-0001.pdf | 6 Jul 2026 |
| Form 5 (FY 2025-2026)File: Form 5 FY 2025-26_page-0001.pdf | 6 Jul 2026 |
| Form 2A (FY 2018-2019)File: Form 2A-March 19.pdf | 9 Jun 2026 |
| Form 2A (FY 2019-2020)File: Form 2A-March 20.pdf | 9 Jun 2026 |
| Form 2A (FY 2020-2021)File: Form 2 A- March 2021.pdf | 9 Jun 2026 |
| Form 2A (FY 2021-2022)File: Form 2A March 22.pdf | 9 Jun 2026 |
| Form 2A (FY 2022-2023)File: Form 2A 2023.pdf | 9 Jun 2026 |
| Form 2A (FY 2023-2024)File: FROM-2A 2024.pdf | 9 Jun 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - 2025 - SGEPL.pdf | 9 Jun 2026 |
| Form 5 (FY 2017-2018)File: shree gaondevi ent 17-18.pdf | 9 Jun 2026 |
| Form 5 (FY 2018-2019)File: shree gaondevi ent 18-19.pdf | 9 Jun 2026 |
| Form 5 (FY 2019-2020)File: shree gaindevi ent 19-20.pdf | 9 Jun 2026 |
| Form 5 (FY 2020-2021)File: shree gaondevi ent 20-21_compressed.pdf | 9 Jun 2026 |
| Form 5 (FY 2021-2022)File: Form 5 21-22.pdf | 9 Jun 2026 |
| Form 5 (FY 2022-2023)File: Form 5 22-23.pdf | 9 Jun 2026 |
| Form 1File: Form 1 Architects Certificate 30092024.pdf | 21 May 2026 |
| Form 2File: Form 2 Engineers Certificate 30092024.pdf | 21 May 2026 |
| Form 3File: final SGD Form 3 Sep 24_compressed.pdf | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Discolsure of sold booked inventory 30-09-2024.pdf | 21 May 2026 |
| Form 1File: Architects Certificate 03-01-25.pdf | 21 May 2026 |
| Form 2File: Form 2.pdf | 21 May 2026 |
| Form 3File: final SGD Form 3 Dec 24_compressed.pdf | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory.pdf | 21 May 2026 |
| Form 1File: Architecture certificate.pdf | 21 May 2026 |
| Form 2File: Form 2- 30-06-2025_compressed.pdf | 21 May 2026 |
| Form 3File: SGE CA_compressed_merged.pdf | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: SGE Book inventory_compressed.pdf | 21 May 2026 |
| Form 1File: Form 1.pdf | 21 May 2026 |
| Form 2File: Form 2_compressed.pdf | 21 May 2026 |
| Form 3File: Form 3_compressed.pdf | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: disclosure of sold inventory.pdf | 21 May 2026 |
| Form 1File: Form 1.pdf | 21 May 2026 |
| Form 2File: Form 2.pdf | 21 May 2026 |
| Form 3File: Form 3 DEC 2025_merged_compressed.pdf | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Diclosure of sold-booked inventory_compressed.pdf | 21 May 2026 |
| Form 1File: MMK FORM 1.pdf | 21 May 2026 |
| Form 2File: ASC FORM 2.pdf | 21 May 2026 |
| Form 3File: FROM 3_Compress.pdf | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Booked Inventry A wing and B wing.pdf | 21 May 2026 |
| Form 1File: MMK March2024 SGE Form 1.pdf | 21 May 2026 |
| Form 2File: ASC Form 2 March 2024.pdf | 21 May 2026 |
| Form 3File: final SGD Form 3 March 24.pdf | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosur Of Sold Booked Inventory SGE March2024.pdf | 21 May 2026 |
| Form 1File: Form 1 April 2026_compressed.pdf | 5 May 2026 |
| Form 2File: Form 2 April 2026_compressed.pdf | 5 May 2026 |
| Form 3File: Form 3 March 2026_compressed.pdf | 5 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY-SHREE GAON DEVI March 26.pdf | 5 May 2026 |
| Certificates of CA (Form 3)File: SGE CA_compressed.pdf | 23 Jul 2025 |
| Certificates of CA (Form 3)File: SGE CA_compressed_merged.pdf | 23 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- 30-06-2025_compressed.pdf | 23 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: SGE Book inventory_compressed.pdf | 23 Jul 2025 |
| Certificates of CA (Form 3)File: New Form 3 2025 SGEPL_compressed.pdf | 29 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2025 ASC_compressed.pdf | 29 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Discolsure of SoldBooked Inventory_compressed.pdf | 29 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 SGEPL_compressed.pdf | 23 Apr 2025 |
| Certificates of CA (Form 3)File: final SGD Form 3 Dec 24_compressed.pdf | 11 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 11 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate 03-01-25.pdf | 10 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf | 10 Feb 2025 |
| Certificates of CA (Form 3)File: final SGD Form 3 Sep 24_compressed.pdf | 9 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer's Certificate 30092024.pdf | 9 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Discolsure of sold booked inventory 30-09-2024.pdf | 30 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect's Certificate 30092024.pdf | 19 Oct 2024 |
| Declaration in FORM BFile: Form B.pdf | 29 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A DPP 25-7-24.pdf | 29 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A PNP 25-7-24.pdf | 29 Jul 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Separate Bank Account 25-7-24.pdf | 29 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf | 27 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf | 27 Jul 2024 |
| Certificates of CA (Form 3)File: FROM 3_Compress.pdf | 17 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MMK FORM 1.pdf | 14 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ASC FORM 2.pdf | 14 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Booked Inventry A wing and B wing.pdf | 14 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf | 1 Jul 2024 |
| Building plan approvalFile: Plan 10.pdf | 25 Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 309 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Jay Krishna on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JANGAL MANGAL ROAD6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 481 registered projects within 2 km.
Runwal Forests Tower 9 - 11
Wheelabrator Alloy Castings Limited
SHRADDHA VARDAAN
SHRADDHA LANDMARK PRIVATE LIMITED
SHRADDHA EVOQUE
SHRADDHA LANDMARK PRIVATE LIMITED
Sugee Vaayu
Sugee Developers Private Limited
SHRADDHA CLASSIC
SHRADDHA LANDMARK PRIVATE LIMITED
Om Siddhivinayak CHS Ltd
Shree Shiv Samarth Reality
See every Mumbai Suburban project, with the district possession charts
Builder: Shreegoandevi Enterprises Private Limited
Shreegoandevi Enterprises Private Limited has 1 registration on MahaRERA, including Jay Krishna. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Jay Krishna is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Jay Krishna?
The registered promoter entity is Shreegoandevi Enterprises Private Limited, a company as per the filing. Its CIN U70109MH2022PTC392044 and GSTIN 27ABJCS5661G1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Jay Krishna?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Jay Krishna?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Jay Krishna?
The professionals named in the filing: Architect: Amol Manohar Kaphale; Architect: Manohar M. Kalpesh & Associates; Engineer: Associated Structural Engineers LLP; Engineer: Rohit Chavan; Chartered Accountant: Shripati Gandhi Chaudhari and Co; Chartered Accountant: Shripati Gandhi Choudhari & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Jay Krishna?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback