Home / Browse projects / Pune, Maharashtra / Jare Aangan

Registered No litigation declared Residential / Group Housing project

Jare Aangan

By Sachin Vasant Jare

RG-MH-82878 · RERA P52100051275 · Last updated on MahaRERA portal: 15 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
7 of 11Construction stages donefurthest along: Installation of Lifts, 98%
7 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

Jare Aangan is a Residential / Group Housing project by Sachin Vasant Jare in Pune, Maharashtra, registered with MahaRERA as P52100051275 on 8 Jun 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 49 of the 56 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameJare Aangan
  • TypeResidential / Group Housing
  • Location
    • Chikhali
    • Haveli
    • Pune
    • 411062
  • Pincode411062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051275
  • ReraGenie IDRG-MH-82878

Builder

  • NameSachin Vasant Jare
  • Entity typeIndividual
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredJun 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Jun 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed62 files

Current status

88%49 of 56 units booked
59.9%Work done, per cost certificate

Figures as on 15 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Jare AanganNA8756056

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 98%.

Jare Aangan: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 15 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Open Space60

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area739 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Dec 2025

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI2600.0
Proposed, not sanctioned2,359 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEmpire Estate Chinchwad 411019
Estimated costRs 7.00 cr
Cost incurredRs 4.19 cr
Work done59.87%
BuildingWingEstimatedIncurred
Jare AanganNARs 6.00 crRs 2.60 cr
-NARs 1.00 crRs 1.59 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShekhar Kokane kokane
EngineerPiraji Narayanrao Kambale
EngineerShriram Ramesh Nagargoje
Chartered AccountantNPSR & Associates - CA. Vivek Lahoti
Chartered AccountantGanesh Sunil Mandlecha
PartnerRole in project
Sachin Vasant Jare-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA09012619375Dec 2025 → Dec 2026

Reason as filed by the promoterSir / Madam, all construction activities of the project have been completed in all respects. The project is now at the final statutory stage, and the only remaining milestone is Firm Demarcation and receipt of the Completion Certificate (CC) from the competent authority. The application for firm demarcation has already been submitted to the concerned authority, and the same is under process. As per the current status and official communication, the Firm Demarcation is expected to be received on or before 31.03.2026 The critical path of the project presently consists only of the following activ

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 (1).pdf15 Jun 2026
Withdrawal Update Form 2File: Form 2 Engg (1).pdf15 Jun 2026
Withdrawal Update Form 3File: Form 3 CA (1).pdf15 Jun 2026
Withdrawal Update Form 1File: Form 1 Jare Aangan.pdf31 Jan 2026
Withdrawal Update Form 2File: Form 2 Jare Aangan.pdf31 Jan 2026
Withdrawal Update Form 3File: Form 3 Jare Aangan.pdf31 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf31 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf4 Dec 2025
Withdrawal Update Form 2File: Form 2 Aangan with sign.pdf4 Dec 2025
Withdrawal Update Form 3File: Form 3 with sign corect.pdf4 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5 WIith Sign.pdf3 Oct 2025
Form 5 (FY 2023-2024)File: Jare Angan Form 5.pdf3 Oct 2025
Withdrawal Update Form 1File: Form 1 Aangan.pdf8 Sep 2025
Withdrawal Update Form 2File: Form 2 Aangan with sign.pdf8 Sep 2025
Withdrawal Update Form 3File: Final Form 3 Q4_compressed.pdf8 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Jare Aangan Form 3 31-03-25.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31-03-25 Jare Aangan.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jare Aangan 31-03-25.pdf14 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30 06 2024.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30 09 2024.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30 12 2024.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30 06 2024.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30 09 2024.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31 12 2024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30 06 2024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30 09 2024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 30 12 2024.pdf13 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Jare Angan Form 5.pdf23 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf21 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30 Sept 2023.pdf21 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31 Dec 2023.pdf21 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31 March 2024.pdf21 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1.pdf21 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2.pdf21 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3.pdf21 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4.pdf21 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf21 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Q1_compressed.pdf21 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Q2_compressed.pdf21 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Q3_compressed.pdf21 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 Q4_compressed.pdf21 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Disclosure of Interest in Other Real Estate Organizations (2).pdf10 May 2023
Layout approvalFile: Approved Layout_compressed.pdf2 May 2023
Building plan approvalFile: Building Plan_compressed.pdf2 May 2023
PAN CardFile: PAN Card.pdf2 May 2023
Copy of the legal title reportFile: Search Title_compressed.pdf2 May 2023
Details of encumbrances concerned to FinanceFile: Legal Encumbrances.pdf2 May 2023
Details of encumbrances concerned to FinanceFile: Financial Encumbrances.pdf2 May 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf2 May 2023
Details of encumbrances concerned to LegalFile: Financial Encumbrances.pdf2 May 2023
Copy of Layout Approval (in case of layout)File: Approved Layout_compressed.pdf2 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan_compressed.pdf2 May 2023
Commencement Certificates / NA Order for plotted developmentFile: CC-Latest.pdf2 May 2023
Declaration about Commencement CertificateFile: Declaration of CC.pdf2 May 2023
Declaration in FORM BFile: Form B.pdf2 May 2023
CERSAI detailsFile: CERSAI_Search_Report.pdf2 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jare Angan_compressed.pdf2 May 2023
Proforma of Agreement for saleFile: Agreement - JARE ANGAN - Draft.pdf2 May 2023
Proforma of Allotment letterFile: Draft Allotment Letter.pdf2 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.pdf2 May 2023
Deviation Report with respect to Allotment letterFile: Deviation wrt Allotment.pdf2 May 2023
Deviation Report with respect to model copy of AgreementFile: Deviation wrt Agreement.pdf2 May 2023

How this compares with Pune

88%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Jare Aangan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chikhali13,700+ in Pune

2 kmJare AanganCompleted 47Lapsed / revoked 21Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 96 registered projects within 2 km.

Builder: Sachin Vasant Jare

Sachin Vasant Jare has 4 registrations on MahaRERA, including Shridhar Heights and Jare Shrusti. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Jare Aangan is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Jare Aangan?

The registered promoter entity is Sachin Vasant Jare, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Jare Aangan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Jare Aangan?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Jare Aangan?

The professionals named in the filing: Architect: Shekhar Kokane kokane; Engineer: Piraji Narayanrao Kambale; Engineer: Shriram Ramesh Nagargoje; Chartered Accountant: NPSR & Associates - CA. Vivek Lahoti; Chartered Accountant: Ganesh Sunil Mandlecha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Jare Aangan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Jare Aangan. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Jare Aangan to a free account