Home / Browse projects / Pune, Maharashtra / Janhavi

Registered No litigation declared Residential / Group Housing project

Janhavi

By Amol Ajit Ravetkar

RG-MH-17462 · RERA P52100028769 · Last updated on MahaRERA portal: 4 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 14 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 8 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 14 months from the original
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
31 of 79Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

Janhavi is a Residential / Group Housing project by Amol Ajit Ravetkar in Pune, Maharashtra, registered with MahaRERA as P52100028769 on 30 Mar 2021. Possession is promised by 18 Nov 2026. The completion date has moved by 14 months from the original filing. 48 of the 79 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameJanhavi
  • TypeResidential / Group Housing
  • Location
    • Lane No 3
    • Lokmanya Colony
    • Kothrud
    • Kothrud
    • Haveli
    • Pune
    • 411038
  • Pincode411038
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100028769
  • ReraGenie IDRG-MH-17462

Builder

  • NameAmol Ajit Ravetkar
  • Entity typeIndividual
  • GSTIN27AGTPR5446G1ZR
  • Other registrations15 more →
  • Completed5 of 16
  • Declared earlier projects8 →

Key dates

this monthRegisteredMar 2021First promiseSep 2025Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Mar 2021
  • Promised completion18 Nov 2026
  • Revised completionRevised to 18 Nov 2026 (originally 30 Sep 2025)
  • Buildings1 building record
  • Documents filed82 files

Current status

61%48 of 79 units booked
100.0%Work done, per cost certificate

Figures as on 4 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JanhaviNA151379079

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Janhavi: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed63

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots63
Closed/Covered63

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,612 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Aug 2026
LandownerVillageDistrict
Janhavi Co-operative Housing Society LtdKothrudPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI7683.77
Proposed, not sanctioned7,684 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLaukik Apartment, ground floor, Plot no 3, CTS No 870, Bhandarkar Road, Pune 411004
Estimated costRs 23.92 cr
Cost incurredRs 23.92 cr
Work done100.0%
BuildingWingEstimatedIncurred
JanhaviNARs 23.92 crRs 23.92 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA Design Studio
ArchitectMangesh Gotal
EngineerNilesh Gujar
Chartered AccountantPRASAD SADVILKAR & ASSOCIATES
Chartered AccountantPhule Wagh & Associates LLP
PartnerRole in project
Amol Ajit Ravetkar-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA07082622052Sep 2025 → Nov 2026

Reason as filed by the promoterThat we have already obtained the Full Occupancy Certificate (Full OC) for the aforesaid registered project from the competent authority, Pune Municipal Corporation (PMC), vide Occupancy Certificate No. OCC/[OCC/1259/24] dated 07/02/2025 well before our RERA Project Completion Date of 30/09/2025. 1. That, prior to submitting the application under the Completion Module on the MahaRERA Portal, we observed that certain fields of Builtup Area Floor Space Index (FSI)/ Inventory/ Floors related corrections are required to be carried out in the project details available on the MahaRERA Portal for app

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Feb 2025

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf4 Sep 2026
Withdrawal Update Form 1File: Last Form 1.pdf4 Sep 2026
Withdrawal Update Form 1File: Last Form 1.pdf4 Sep 2026
Withdrawal Update Form 2File: FORM 2.pdf4 Sep 2026
Withdrawal Update Form 2File: Last Form 2.pdf4 Sep 2026
Withdrawal Update Form 2File: Last Form 2.pdf4 Sep 2026
Withdrawal Update Form 3File: final sanction FORM 3 Chartered Accountant Certificate.pdf4 Sep 2026
Withdrawal Update Form 3File: final sanction FORM 3 Chartered Accountant Certificate.pdf4 Sep 2026
Withdrawal Update Form 3File: final sanction FORM 3 Chartered Accountant Certificate.pdf4 Sep 2026
Form 5 (FY 2020-2021)File: FORMAT Form 5 - CA Certificate FY 20-21.pdf29 Aug 2026
Form 5 (FY 2021-2022)File: FORMAT Form 5 - CA Certificate FY 21-22.pdf29 Aug 2026
Form 5 (FY 2022-2023)File: FORMAT Form 5 - CA Certificate FY 22-23.pdf29 Aug 2026
Form 5 (FY 2023-2024)File: FORMAT Form 5 - CA Certificate FY 23-24.pdf29 Aug 2026
Form 5 (FY 2024-2025)File: FORMAT Form 5 - CA Certificate FY 24-25.pdf29 Aug 2026
Form 5 (FY 2025-2026)File: FORMAT Form 5 - CA Certificate FY 25-26.pdf29 Aug 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf27 Aug 2026
Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf27 Aug 2026
Form 2A (FY 2022-2023)File: Form 2A 22-23.pdf27 Aug 2026
Form 2A (FY 2021-2022)File: Form 2A 21-22.pdf27 Aug 2026
Form 2A (FY 2020-2021)File: Form 2A 21-22.pdf27 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26 Janhavi.pdf6 Aug 2026
Form 1File: Form 1 Architects Certificate - 31032024.pdf18 Jun 2026
Form 2File: FORM 2 Engineer Certificate 30092025.pdf18 Jun 2026
Form 3File: Q2 FORM 3 Chartered Accountant Certificate.pdf18 Jun 2026
Disclosure of Sold and Booked InventoryFile: Inventory Declaration Sold Unsold.pdf18 Jun 2026
Form 1File: Form 1 Architects Certificate.pdf18 Jun 2026
Form 2File: FORM 2 Engineer Certificate.pdf18 Jun 2026
Form 3File: Q1 FORM 3 Chartered Accountant Certificate.pdf18 Jun 2026
Disclosure of Sold and Booked InventoryFile: Inventory Declaration Sold Unsold.pdf18 Jun 2026
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: janhavi Form 4.pdf19 Feb 2025
Other - TechnicalFile: janhavi Form 4.pdf19 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf10 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-FY 2023-24.pdf11 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Chartered Accountant Certificate.pdf11 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Janhavi Form 1 signed.pdf30 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate 31032024.pdf28 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Janhavi Form 5 FY 2022-23.pdf30 Sep 2023
Building plan approvalFile: 7.pdf14 Jun 2023
Building plan approvalFile: 8.pdf14 Jun 2023
Layout approvalFile: 1.pdf14 Jun 2023
Building plan approvalFile: 2.pdf14 Jun 2023
Building plan approvalFile: 3.pdf14 Jun 2023
Building plan approvalFile: 4.pdf14 Jun 2023
Building plan approvalFile: 5i.pdf14 Jun 2023
Building plan approvalFile: 6.pdf14 Jun 2023
Copy of Layout Approval (in case of layout)File: 1.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 5i.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 6.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 7.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 8.pdf14 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf14 Jun 2023
Declaration about Commencement CertificateFile: Format D Janhavi.pdf14 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- JANHAVI.pdf22 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - March 2022.pdf22 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - June 2022.pdf22 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sep 2022.pdf22 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2022.pdf22 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A FY 20-21.pdf22 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A FY 21-22.pdf22 Feb 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY.pdf22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 -March 2022.pdf22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 04072022 scan.pdf22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sep 2022.pdf22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2022.pdf22 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORMAT Form 5 - CA Certificate FY 20-21.pdf22 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORMAT Form 5 - CA Certificate FY 21-22.pdf22 Feb 2023
Details of encumbrancesFile: Upload.pdf8 Oct 2022
Layout approvalFile: Sanctioned Plans janhavi Final.pdf27 Mar 2021
Building plan approvalFile: Sanctioned Plans janhavi Final.pdf27 Mar 2021
PAN CardFile: Amol Sir Pan card New.pdf27 Mar 2021
Copy of the legal title reportFile: Janhavi Title Search Final.pdf27 Mar 2021
Details of encumbrancesFile: No Encumbarance Certificate.pdf27 Mar 2021
Copy of Layout Approval (in case of layout)File: Sanctioned Plans janhavi Final.pdf27 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Plans janhavi Final.pdf27 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: CC wo PMC stmp.pdf27 Mar 2021
Declaration in FORM BFile: Form B Affidavait Amol Sir.pdf27 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Janhavi.pdf27 Mar 2021

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

8 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
ManaliParvati Sahakar Nagar Pune 41100911CompletedFeb 2021Oct 2020
SuvarnaLane no 19 Dahanukar Colony Kothrud Pune 41103820CompletedMar 2020Jan 2020
PiyushaOff. law college road Erandwane Pune 41100418CompletedMar 2019Jan 2019
Anusha ResidencyParvati10CompletedJan 2017Dec 2016
Rahul Vihar - ALane 18 Dhanukar Colony Kothrud Pune15CompletedOct 2016Oct 2016
Om BramhaDhanukar Colony15CompletedMar 2015Mar 2015
TulipsLane no 14 Rajwade Path Bhandarkar Road Pune 41100421CompletedApr 2013Apr 2013
PoornimaGultekdi18CompletedDec 2012Dec 2012

How this compares with Pune

61%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 14 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Janhavi on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lokmanya Colony, Kothrud13,700+ in Pune

2 kmJanhaviCompleted 95Lapsed / revoked 48Other 150Dot size: filed unitsN

Filed coordinates, straight-line distance. 293 registered projects within 2 km.

Builder: Amol Ajit Ravetkar

Amol Ajit Ravetkar has 16 registrations on MahaRERA, including Piyusha and Sukhniwas. Its filings disclose 8 earlier MahaRERA projects: declares 8 of 8 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Janhavi is delayed beyond 18 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Janhavi?

The registered promoter entity is Amol Ajit Ravetkar, an individual as per the filing. Its GSTIN 27AGTPR5446G1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Janhavi?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Janhavi?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Janhavi?

The professionals named in the filing: Architect: A Design Studio; Architect: Mangesh Gotal; Engineer: Nilesh Gujar; Chartered Accountant: PRASAD SADVILKAR & ASSOCIATES; Chartered Accountant: Phule Wagh & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Janhavi?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Janhavi. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Janhavi to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.