Amol Ajit Ravetkar: RERA track record

GSTIN 27AGTPR5446G1ZR · Individual · attribution by exact filing name, entity resolution in progress

Amol Ajit Ravetkar has 16 registrations on MahaRERA, including Piyusha and Sukhniwas. Its filings disclose 8 earlier MahaRERA projects: declares 8 of 8 past projects completed on time.

16RERA registrations
8Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation
Follow this developer. An email when Amol Ajit Ravetkar registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 16 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
JanhaviP52100028769Lokmanya Colony, Kothrud, Pune, 4110387961%30 Mar 2021Registered
SHRI KESHAVLAXMIP52100053892Ideal Colony, Pune, 4110385242%8 Dec 2023Registered
NIVEDITAPR1260002500589Rambaug Colony, Pune, 4110382832%18 Aug 2025Registered
SWARGANDHAP52100046968Bhamburda Shivajinagar, Pune, 411016280%26 Sep 2022Registered
ADITIP52100050632KOTHRUD, Pune, 4110382730%21 Apr 2023Registered
SHIVSUDHAPR1260002501282Rambaug Colony, Pune, 411038230%20 Oct 2025Registered
SUMUKHPR1260002502924Model Colony, Pune, 411016210%18 Mar 2026Registered
ARISHAP52100055981Erandwane, Pune, 411004160%2 May 2024Registered
Nirmitee ViharPR1260002500783Kothrud, Pune, 411038130%15 Sep 2025Registered
SUMANP52100054831Erandwane, Pune, 4110041338%15 Feb 2024Registered
HRISHIKESHP52100050088DECCAN GYMKHANA, Pune, 4110041118%15 Mar 2023Registered
70 WEST AVENUEP52100017946Erandawane, Pune, 411038--28 Sep 2018Completed
AnushreeP52100024833Kothrud, Pune, 411038--9 Mar 2020Completed
PiyushaP52100002284Pune (M Corp.), Pune, 411004--31 Jul 2017Completed
SHRI-OMP52100019369Dahanukar Colony, Lane no 5, Shri Om Cooperative Society, Pune, 411038--23 Jan 2019Completed
SukhniwasP52100009654Shivajinagar, Pune, 411016--22 Aug 2017Completed

What this promoter declares as its own experience

Amol Ajit Ravetkar declares experience on 8 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Poornima
11 Dec 201211 Dec 2012On time
Tulips
30 Apr 201330 Apr 2013On time
Om Bramha
31 Mar 201531 Mar 2015On time
Rahul Vihar - A
3 Oct 20163 Oct 2016On time
Anusha Residency
1 Jan 201713 Dec 2016On time
Piyusha
31 Mar 20194 Jan 2019On time
Suvarna
31 Mar 202024 Jan 2020On time
Manali
28 Feb 202123 Oct 2020On time

Frequently asked questions

How do I verify Amol Ajit Ravetkar as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AGTPR5446G1ZR on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Amol Ajit Ravetkar?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the Amol Ajit Ravetkar developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.