Home / Browse projects / Nashik, Maharashtra / JAGANNATH RESIDENCY
JAGANNATH RESIDENCY
RG-MH-13678 · RERA P51600027274 · Last updated on MahaRERA portal: 7 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 48 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
JAGANNATH RESIDENCY is a Residential / Group Housing project by YASHWANT JAGANNATH PAWAR in Nashik, Maharashtra, registered with MahaRERA as P51600027274 on 1 Dec 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 31 of the 62 units on this registration are recorded sold or booked, and 30 of 33 construction stages are filed complete.
At a glance
Project
- NameJAGANNATH RESIDENCY
- TypeResidential / Group Housing
- Location
- MAPARWADI ROAD
- BEHIND JINDAL HOUSING
- Maparwadi
- Sinnar
- Nashik
- 422113
- Pincode422113
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600027274
- ReraGenie IDRG-MH-13678
Builder
- NameYASHWANT JAGANNATH PAWAR
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Dec 2020
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
- Buildings3 building records
- Documents filed107 files
Current status
Figures as on 7 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JAGANNATH RESIDENCY WING A | NA | 2 | 1 | 30 | 0 | 30 |
| JAGANNATH RESIDENCY WING B | NA | 2 | 1 | 16 | 0 | 16 |
| JAGANNATH RESIDENCY WING C | NA | 2 | 1 | 16 | 0 | 16 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 7 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.
JAGANNATH RESIDENCY WING A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
JAGANNATH RESIDENCY WING B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
JAGANNATH RESIDENCY WING C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 7 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ASHISH PATIL |
| Engineer | ROHIT NIMASE |
| Engineer | Prabhakar Shivaji Mandlik |
| Engineer | Yashwant Jayanth Pawar |
| Chartered Accountant | CA PARESH P SABADRA |
| Chartered Accountant | RSPH & Associates |
| Chartered Accountant | Pratik D Jain |
| Partner | Role in project |
|---|---|
| YASHWANT JAGANNATH PAWAR | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterLack of manpower and labour supply post covid time. Most of the North Indian labourers were away and hence we had a very bad time to re establish the work momentum.
Reason as filed by the promotera) As the entire country including Nashik District were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, I stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are st
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Nov 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Nov 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Nov 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed107
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 107 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: RERA Audit - 2024-25 signed copy - Final .pdf | 7 Mar 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - March 25.pdf | 4 Mar 2026 |
| Form 2A (FY 2020-2021)File: Form 2A - March 21.pdf | 4 Mar 2026 |
| Form 2A (FY 2021-2022)File: Form 2A - March 22.pdf | 4 Mar 2026 |
| Form 2A (FY 2022-2023)File: Form 2A - March 23.pdf | 4 Mar 2026 |
| Form 2A (FY 2023-2024)File: Form 2A - March 24.pdf | 4 Mar 2026 |
| Form 1File: AR June 25.pdf | 3 Dec 2025 |
| Form 2File: ER June 25.pdf | 3 Dec 2025 |
| Form 3File: CA June 25-Final.pdf | 3 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure June 25.pdf | 3 Dec 2025 |
| Form 1File: AR Sept 25.pdf | 3 Dec 2025 |
| Form 2File: ER Sept 25.pdf | 3 Dec 2025 |
| Form 3File: CA Sept 25-Final.pdf | 3 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Sep 25.pdf | 3 Dec 2025 |
| Form 1File: AR - March 25.pdf | 29 Nov 2025 |
| Form 2File: ER - March 25 final.pdf | 29 Nov 2025 |
| Form 3File: CA - March 25_final.pdf | 29 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 25.pdf | 29 Nov 2025 |
| Declaration in FORM BFile: Form B JCP.pdf | 21 Mar 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Plinth Completion JCP.pdf | 21 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A(2).pdf | 18 Mar 2025 |
| CERSAI detailsFile: CERSAI Report.pdf | 18 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A(1).pdf | 18 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of intrest - Annexture A.pdf | 18 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A (3).pdf | 18 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: B C Dec 24.pdf | 10 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sept B and C.pdf | 1 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - Dec 24 wing A .pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Dec-24.pdf | 25 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-Dec-24.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Dec-24.pdf | 25 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 4 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FinalForm 5 FY 2023-24 (1).pdf | 4 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sold Booked Inventry March 24.pdf | 3 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sold Booked Inventry June 24.pdf | 3 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sold Booked Inventry Sept 24.pdf | 3 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR - June 23.pdf | 30 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR - Sept 23.pdf | 30 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR - DEC 23.pdf | 30 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR - March 24.pdf | 30 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR - June 24.pdf | 30 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR - Sept 24.pdf | 30 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA- Sept 23_001.pdf | 30 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA- Sept 24_001.pdf | 30 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA - June 24_001.pdf | 30 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA - March 24_001.pdf | 30 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA -Dec 23.pdf | 30 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA -June 23.pdf | 30 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate sept 24.pdf | 30 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER - June 24.pdf | 30 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER -March 24.pdf | 30 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER - Dec 23.pdf | 30 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER -Sept 23.pdf | 30 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER - June 23.pdf | 30 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 25 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RA Report- Final.pdf | 18 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RA Report- Final.pdf | 18 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 1 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 1 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Mar'23.pdf | 1 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 27 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JCP Dec 22 CA certificate final.pdf | 18 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JCP Builders And Builders Arch1.pdf | 14 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JCP Builders And Builders Arch2.pdf | 14 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JCP Builders And Builders Arch3.pdf | 14 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JCP Builders And Builders Arch3_001.pdf | 14 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JCP Developers and Builders Arch 4.pdf | 14 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JCP Builders And Builders Engg.pdf | 14 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JCP Builders And Builders Engg1.pdf | 14 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JCP Builders And Builders Engg2.pdf | 14 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JCP Builders And Builders Engg3.pdf | 14 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JCP Builders And Builders Engg4.pdf | 14 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JCP Developers and Builders Engg (1).pdf | 14 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: JCP_RA 21 22_signed.pdf | 3 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 17 Feb 2023 |
| Declaration about Commencement CertificateFile: Form D.pdf | 20 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Booked.pdf | 20 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR jcp.pdf | 25 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ERjcp.pdf | 25 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JCP Developers CA Certificate.pdf | 11 Nov 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 107 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep JAGANNATH RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BEHIND JINDAL HOUSING4,100+ in Nashik
Filed coordinates, straight-line distance. 8 registered projects within 2 km.
Yashwant Row Bungalow
Pankaj Ashok More
SHREE SATYANARAYAN ROONGTA FORUM
ROONGTA HOMES LLP
LIFE 360
VELOCITY INFRA PROJECTS
THE PLATINUM MALL BY PARKSYDE
JAIKUMAR CONSTRUCTIONS LTD
GLOBAL VILLE
SHRADDHA INFRA
AVADH UTOPIA
DHATRAK CONSTRUWELL
See every Nashik project, with the district possession charts
Builder: YASHWANT JAGANNATH PAWAR
YASHWANT JAGANNATH PAWAR has 1 registration on MahaRERA, including JAGANNATH RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if JAGANNATH RESIDENCY is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of JAGANNATH RESIDENCY?
The registered promoter entity is YASHWANT JAGANNATH PAWAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in JAGANNATH RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for JAGANNATH RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at JAGANNATH RESIDENCY?
The professionals named in the filing: Architect: ASHISH PATIL; Engineer: ROHIT NIMASE; Engineer: Prabhakar Shivaji Mandlik; Engineer: Yashwant Jayanth Pawar; Chartered Accountant: CA PARESH P SABADRA; Chartered Accountant: RSPH & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JAGANNATH RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback