Home / Browse projects / Nashik, Maharashtra / AVADH UTOPIA

Registered No litigation declared Others project

AVADH UTOPIA

By DHATRAK CONSTRUWELL

RG-MH-13566 · RERA P51600026740 · Last updated on MahaRERA portal: 25 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 49 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedmoved 49 months from the original
38 of 55Construction stages doneacross 5 buildings; furthest along: Podiums (if any), 90%
285 of 534Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

AVADH UTOPIA is a Others project by DHATRAK CONSTRUWELL in Nashik, Maharashtra, registered with MahaRERA as P51600026740 on 21 Oct 2020. Possession is promised by 30 Dec 2029. The completion date has moved by 49 months from the original filing. 249 of the 534 units on this registration are recorded sold or booked, and 38 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAVADH UTOPIA
  • TypeOthers
  • Location
    • RADHA NAGAR
    • MAKHMALABAD ROAD PANCHVATI
    • Nashik
    • 422003
  • Pincode422003
  • RERA no.P51600026740
  • ReraGenie IDRG-MH-13566

Builder

  • NameDHATRAK CONSTRUWELL
  • Entity typePartnership
  • PartnersHARIBHAU LAKSHMAN DHATRAK, PRAVIN HARIBHAU DHATRAK, HEMANT HARIBHAU DHATRAK
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2020First promiseNov 2025Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Oct 2020
  • Promised completion30 Dec 2029
  • Revised completionRevised to 30 Dec 2029 (originally 30 Nov 2025)
  • Buildings5 building records
  • Documents filed96 files

Current status

47%249 of 534 units booked
41.2%Work done, per cost certificate

Figures as on 25 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA2121721789
BNA222276076
CNA21211440144
DNA21211440144
ENA1010602181

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 25 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

38 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 90%.

A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.55%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D52%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor90%
Slabs of Super Structure38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%

Progress on shared amenities15

As on 25 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area11,345 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Aug 2025

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI40569.06
Proposed, not sanctioned40,569 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNo 1 Ground Floor Suyojit Sankul ,Sharanpur Road Nashik- 422 002 Maharashtra
Estimated costRs 120.35 cr
Cost incurredRs 49.63 cr
Work done41.24%
BuildingWingEstimatedIncurred
-NARs 32.49 crRs 5.66 cr
DNARs 25.61 crRs 1.42 cr
CNARs 22.62 crRs 16.59 cr
BNARs 15.46 crRs 5.96 cr
ANARs 14.65 crRs 13.67 cr
ENARs 9.51 crRs 6.33 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectORIGIN ARCHITECTS
EngineerLILADHAR JAWALE
EngineerRameshwar Uttam Nagare
Chartered AccountantASHOK J. MODI
Chartered AccountantA R N R AND ASSOCIATES
Chartered AccountantVipin Khobragade & Co.
Chartered AccountantRahul Nawandar and Associates
PartnerRole in project
DHATRAK CONSTRUWELL-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA03092502498Nov 2025 → Dec 2029

Reason as filed by the promoterWe have attached letter for Reason for Delay with this submission.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12605169Durgesh Nandkumar OzarkarDHATRAK CONSTRUWELL13/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2029

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q4 25-26.pdf25 Jun 2026
Withdrawal Update Form 2File: Avadh Form2 Q4 2025-2026.pdf25 Jun 2026
Withdrawal Update Form 3File: Avadh Q4 Form3 2025-26_compressed.pdf25 Jun 2026
Withdrawal Update Form 1File: Form 1 Avadh-Q3-2025-26.pdf6 Apr 2026
Withdrawal Update Form 2File: Avadh Form 2 Q3 2025-2026.pdf6 Apr 2026
Withdrawal Update Form 3File: AVADH FORM 3 Q2 2025-26 (1)_compressed.pdf6 Apr 2026
Withdrawal Update Form 1File: Avadh Form 1 Q2 2025-2026.pdf11 Dec 2025
Withdrawal Update Form 2File: Avadh Form 2 Q2 2025-2026.pdf11 Dec 2025
Withdrawal Update Form 3File: AVADH FORM 3 Q2 2025-26 (1)_compressed.pdf11 Dec 2025
Withdrawal Update Form 1File: Q1 form1 2025-2026.pdf3 Sep 2025
Withdrawal Update Form 2File: Avadh Form2 Q1 2025-2026.pdf3 Sep 2025
Withdrawal Update Form 3File: AVADH - Q1 FY 25-26 FORM-3_compressed.pdf3 Sep 2025
Form 2A (FY 2024-2025)File: 2A.pdf3 Sep 2025
Form 5 (FY 2024-2025)File: AVADH FORM 5 2024-25.pdf2 Sep 2025
Commencement Certificates / NA Order for plotted developmentFile: 03 NMC-Commencement-AVADH.pdf9 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Avadh Form1 Q4 2024-25.pdf5 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Avadh-Form 3 Q4 2024-25 (1)_compressed.pdf5 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q-4 2024-2025 Avadh.pdf5 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1-Q3 2024-2025.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Avadh Q-3 2024-2025_compressed_compressed (1).pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 1 24-25.pdf24 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 2 24-25.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: Avadh Q-2 2024-2025 Sold Unsold_1_11zon.pdf24 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q-2 2023-2024.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q-3 2023-2024.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q-3 2023-2024.pdf14 Feb 2025
Building plan approvalFile: Sheet No 1.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 2024-2025 Avadh Architect.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Avadh Form3 Q-2 2024-2025 Signed_11zon.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2 2024-2025 Avadh.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Sheet No 1.pdf5 Feb 2025
Declaration about Commencement CertificateFile: Declaration Commencemnt Certificate.pdf5 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A 2023-2024 Avadh.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1Q-1 2024-2025 Architect Certificate.pdf25 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q1-24-25 Signed_compressed.pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q-1 2024-2025 Avadh Engineer Certificate.pdf25 Oct 2024
Disclosure of sold/ booked inventoryFile: Q-1 2024-2025 sold unsold_compressed.pdf25 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5-DCAU.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AVADH FORM 1 Q4 -23-24.pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 23-24 Avadh_compressed.pdf24 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AVADH FORM 2 Q4 -23-24.pdf24 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2022-2023 avadh.pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 23-24 Avadh.pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Q2 2023-2024 Avadh.pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q-3 2023-2024 Avadh.pdf14 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2A 2021-2022 Avadh.pdf13 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A 2022-2023 Avadh.pdf13 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 2023-2024 Avadh.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2 2023-2024 Avadh.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 2023-2024 Avadh.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3-Q1-23-24_compressed.pdf1 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Q2_compressed.pdf1 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Q4.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Booking Status Q1 22-23.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Booking Status Q2 2022-23.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Booking Status Q3 22-23.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Booking Status Q4 22-23.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Booking Status Q1 23-24.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Booking Status Q2 23-24.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Booking Status Q3 23-24.pdf16 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June22_compressed (1).pdf16 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept22_compressed.pdf16 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec22_compressed.pdf16 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Q4_compressed.pdf16 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Q3 Avadh_compressed.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: DC-Form 5.pdf16 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Avadh Form 1-Q1.pdf16 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Avadh Form 1-Q2.pdf16 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Avadh Form 1-Q3.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Avadh Form 2-Q1.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Avadh Form 2-Q2.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Avadh Form 2-Q3.pdf16 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: APRIL 2021_FORM-1.pdf18 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: APRIL 2022_FORM-1.pdf18 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Apr2021 Form2 (1).pdf18 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Apr2022 Form2 (1).pdf18 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 merge.pdf18 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3 2021-22_compressed.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: DC - RERA FORM 5 FY 20-21.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22 (1).pdf18 Feb 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
PRIYANKA BLOSSOMS NO 42-1-3 Serene Meadows Anandwalli Shiwar Gangapur Road Nashik89CompletedJun 2017Jun 2017

How this compares with Nashik

47%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 49 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AVADH UTOPIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAKHMALABAD ROAD PANCHVATI4,100+ in Nashik

Builder: DHATRAK CONSTRUWELL

DHATRAK CONSTRUWELL has 3 registrations on MahaRERA, including PRIYANKA RESIDENCY and AVADH UTOPIA. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if AVADH UTOPIA is delayed beyond 30 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AVADH UTOPIA?

The registered promoter entity is DHATRAK CONSTRUWELL, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AVADH UTOPIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AVADH UTOPIA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AVADH UTOPIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AVADH UTOPIA?

The professionals named in the filing: Architect: ORIGIN ARCHITECTS; Engineer: LILADHAR JAWALE; Engineer: Rameshwar Uttam Nagare; Chartered Accountant: ASHOK J. MODI; Chartered Accountant: A R N R AND ASSOCIATES; Chartered Accountant: Vipin Khobragade & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AVADH UTOPIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AVADH UTOPIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AVADH UTOPIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.