JAGANNATH PARADISE
By MAYUR GROUP
RG-MH-44410 · RERA P51700050635 · Last updated on MahaRERA portal: 26 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- Completion date moved by 9 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
JAGANNATH PARADISE is a Others project by MAYUR GROUP in BADLAPUR WEST, 421503, registered with MahaRERA as P51700050635 on 21 Apr 2023. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 9 months from the original filing. 109 of the 121 units on this registration are recorded sold or booked, and 8 of 20 construction stages are filed complete.
At a glance
Project
- NameJAGANNATH PARADISE
- TypeOthers
- Location
- SURVEY NO 258 HISSA NO 1 SURVEY NO 258 HISSA NO 4 MAUJE BADLAPUR TAL AMBERNATH
- BADLAPUR WEST
- 421503
- Pincode421503
- RERA no.P51700050635
- ReraGenie IDRG-MH-44410
Builder
- NameMAYUR GROUP
- Entity typePartnership
- GSTIN27AAZFM8650R1ZW
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersBHAVANA JAGANNATH PISEKAR, DHANANJAY JAGANNATH PISEKAR
- Other registrations3 more →
- Completed2 of 4
- Past their filed date1
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on21 Apr 2023
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 31 Dec 2025)
- Buildings2 building records
- Documents filed84 files
Current status
Figures as on 26 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JAGANNATH PARADISE A WING | NA | 7 | 7 | 48 | 4 | 52 |
| JAGANNATH PARADISE B WING | NA | 8 | 0 | 62 | 7 | 69 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 26 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 20 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 65%.
JAGANNATH PARADISE A WING63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 65% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 55% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
JAGANNATH PARADISE B WING63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 65% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 15% |
Progress on shared amenities15
As on 26 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 44% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 45% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed132
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| JAGANNATH PARADISE A WING | 66 | 66 |
| JAGANNATH PARADISE B WING | 66 | 66 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| JAGANNATH PARADISE B WING | NA | Rs 7.51 cr | Rs 7.13 cr |
| JAGANNATH PARADISE A WING | NA | Rs 5.68 cr | Rs 5.40 cr |
| - | NA | Rs 1.26 cr | Rs 37.68 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCHITECT SACHIN VILAS SA |
| Architect | MOHIT C WAKLE |
| Engineer | ATUL KUDTARKAR AND ASSOCIATES PVT LTD |
| Engineer | SACHIN BORSE |
| Chartered Accountant | NILESH A PATKI |
| Chartered Accountant | RAVIRAJ B DANGE AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| MAYUR GROUP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project has been substantially completed in accordance with sanctioned plans, with structural, finishing, and allied works executed for the building. We are in a process of applying of the Completion Certificate to the Competent Authority, Further there is procedural requirements and inspection timelines, it could not be obtained within the registration period ending 31.12.2025. To comply with the Real Estate (Regulation and Development) Act, 2016, and protect the interests of allottees, we seek an extension of project registration solely to align validity with the certification process. T
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Feb 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Feb 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed84
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2A 31032025.pdf | 26 Feb 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 22 Nov 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 22 Nov 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 22 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Mayur group.pdf | 18 Sep 2025 |
| Form 1File: Form 1 _Architect certificate.pdf | 20 Jul 2025 |
| Form 2File: Form 2 MG.pdf | 20 Jul 2025 |
| Form 3File: Form 3 MG.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold.pdf | 20 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 17 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 16 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 16 May 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE 31032025.pdf | 12 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 22 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 22 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 22 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 30 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 MG_11zon.pdf | 29 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 28 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 11 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 11 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Mayur Group.pdf | 11 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE .pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 MG jun 24_11zon.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate .pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality assurance certificate.pdf | 9 May 2024 |
| Disclosure of sold/ booked inventoryFile: disclosure- mayur group.pdf | 9 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Mayur.pdf | 9 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf | 30 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate.pdf | 30 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE - MAYUR GROUP.pdf | 16 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate - DEC-23.pdf | 12 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate - DEC-23.pdf | 12 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold jun23_11zon.pdf | 12 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold-unsold Sept-23_11zon.pdf | 12 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold Dec23_11zon.pdf | 12 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - DEC-23.pdf | 12 Jan 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 12 Jan 2024 |
| Other - TechnicalFile: SELF DECLARATION CUM UNDERTAKING_11zon.pdf | 12 Jan 2024 |
| Details of encumbrances concerned to FinanceFile: Non Encumbrances - Finance.pdf | 29 Nov 2023 |
| Details of encumbrances concerned to LegalFile: Non Encumbrances - Finance.pdf | 29 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate MG SEPT-23.pdf | 28 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate MG SEPT-23.pdf | 28 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 2023-24 Q2_11zon.pdf | 28 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mayur Group Engineers Certificate.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Mayur Group CA Certificate.pdf | 20 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate new_11zon.pdf | 14 Apr 2023 |
| Other - TechnicalFile: PLINTH LEVEL CERTIFICATE.pdf | 14 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form-3_11zon.pdf | 31 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECH CERTIFICATE_11zon.pdf | 13 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DICLOSURE-JAGANNATH PISEKAR.pdf | 13 Mar 2023 |
| Layout approvalFile: PLAN-1.pdf | 22 Feb 2023 |
| Building plan approvalFile: PLAN-1.pdf | 22 Feb 2023 |
| Building plan approvalFile: PLAN-2.pdf | 22 Feb 2023 |
| Building plan approvalFile: PLAN-3.pdf | 22 Feb 2023 |
| Layout approvalFile: PLAN-2.pdf | 22 Feb 2023 |
| Layout approvalFile: PLAN-3.pdf | 22 Feb 2023 |
| PAN CardFile: Mayur Group Pan.pdf | 22 Feb 2023 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT_11zon.pdf | 22 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Non encumbrances (finance)_11zon.pdf | 22 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Non encumbrances (Legal)_11zon.pdf | 22 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Non encumbrances (finance)_11zon.pdf | 22 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Non encumbrances (Legal)_11zon.pdf | 22 Feb 2023 |
| Copy of Layout Approval (in case of layout)File: PLAN-1.pdf | 22 Feb 2023 |
| Copy of Layout Approval (in case of layout)File: PLAN-2.pdf | 22 Feb 2023 |
| Copy of Layout Approval (in case of layout)File: PLAN-3.pdf | 22 Feb 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN-1.pdf | 22 Feb 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN-2.pdf | 22 Feb 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN-3.pdf | 22 Feb 2023 |
| Declaration about Commencement CertificateFile: Declaration of CC.pdf | 22 Feb 2023 |
| Declaration in FORM BFile: FORM B BUILDER_11zon.pdf | 22 Feb 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200260761698_For_Asset_Based_Search_20_02_2023_11_23_27_497.pdf | 22 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest mayur pisekar.pdf | 22 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest dhananjay pisekar.pdf | 22 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest Jyoti pisekar.pdf | 22 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest bhavana pisekar.pdf | 22 Feb 2023 |
| Proforma of Agreement for saleFile: AGREEMENT FOR SALE.pdf | 22 Feb 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| JAGANNATH GALAXYP51700018451 | JOVELI, Thane | Nov 2018 | Completed | Dec 2024Registered original: Oct 2022 | Aug 2023 |
| JAGANNATH PRIDEP51700004903 | Badlapur (M Cl), Thane | Aug 2017 | Completed | Mar 2022 | Apr 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations, which the RERA portal never shows together
- All 84 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep JAGANNATH PARADISE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BADLAPUR WEST
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
Builder: MAYUR GROUP
MAYUR GROUP has 4 registrations on MahaRERA, including JAGANNATH PRIDE and JAGANNATH GALAXY. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record.
Frequently asked questions
What are my rights if JAGANNATH PARADISE is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of JAGANNATH PARADISE?
The registered promoter entity is MAYUR GROUP, a partnership as per the filing. Its GSTIN 27AAZFM8650R1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in JAGANNATH PARADISE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for JAGANNATH PARADISE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at JAGANNATH PARADISE?
The professionals named in the filing: Architect: ARCHITECT SACHIN VILAS SA; Architect: MOHIT C WAKLE; Engineer: ATUL KUDTARKAR AND ASSOCIATES PVT LTD; Engineer: SACHIN BORSE; Chartered Accountant: NILESH A PATKI; Chartered Accountant: RAVIRAJ B DANGE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in JAGANNATH PARADISE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback