ISHWAR PRATIK GRAND A AND B WING
RG-MH-13575 · RERA P51600026152 · Last updated on MahaRERA portal: 19 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 9 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ISHWAR PRATIK GRAND A AND B WING is a Residential / Group Housing project by KANAK DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600026152 on 25 Aug 2020. Possession was promised by 15 Jun 2026 and is now 4 months past that date. The completion date has moved by 9 months from the original filing. 79 of the 104 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.
At a glance
Project
- NameISHWAR PRATIK GRAND A AND B WING
- TypeResidential / Group Housing
- Location
- AGARTAKLI SHIWAR
- NASHIK
- 422011
- Pincode422011
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600026152
- ReraGenie IDRG-MH-13575
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on25 Aug 2020
- Promised completion15 Jun 2026
- Revised completionRevised to 15 Jun 2026 (originally 30 Sep 2025)
- Buildings2 building records
- Documents filed89 files
Current status
Figures as on 19 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ISHWAR PRATIK GRAND A WING | NA | 16 | 13 | 52 | 0 | 52 |
| ISHWAR PRATIK GRAND B WING | NA | 16 | 13 | 52 | 0 | 52 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 19 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
ISHWAR PRATIK GRAND A WING99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
ISHWAR PRATIK GRAND B WING99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 19 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed218
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| ISHWAR PRATIK GRAND A WING | 99 | 5 | 104 |
| ISHWAR PRATIK GRAND B WING | 114 | 0 | 114 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MRS NAYNA YUVARAJ PAWAR | Nashik | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| ISHWAR PRATIK GRAND A WING | NA | Rs 38.84 cr | Rs 26.22 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUMIT KUMATH |
| Engineer | MILIND RATHI |
| Chartered Accountant | PRITAM BAGMAR |
| Partner | Role in project |
|---|---|
| KANAK DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have in warded our application for completion certificate with NMC on 11.09.2025 and it is under process. We are seeking the completion certificate from NMC. Meanwhile we have completed the onsite works and obtained statutory clearances including Lift working letter, Fire completion certificate, Mseb electricity meters installed. Therefore, we kindly request mahaRERA to grant an extension of 9 months in project validity so that we may complete the remaining formalities and hand over full and complete document to our customers. We are currently waiting for approval from NMC. We r mailed alre
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Aug 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Aug 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Aug 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed89
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 AB Q4 31032026.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Form 2 AB Q4 31032026.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Form 3 AB Q4 31032026.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Form1 AB Wing Q3.pdf | 10 Mar 2026 |
| Withdrawal Update Form 2File: Form2 AB Q3.pdf | 10 Mar 2026 |
| Withdrawal Update Form 3File: Form3 AB Q3.pdf | 10 Mar 2026 |
| Form 2A (FY 2024-2025)File: Form2Aab31032025.pdf | 3 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Ab 2425.pdf | 3 Dec 2025 |
| Form 1File: Form 1 AB 30092025.pdf | 18 Oct 2025 |
| Form 2File: Form 2 AB 30092025.pdf | 18 Oct 2025 |
| Form 3File: Form 3 AB 30092025.pdf | 18 Oct 2025 |
| OthersFile: Form 2A AB 30092025.pdf | 18 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Sold Booked Inventory AB.pdf | 18 Oct 2025 |
| Form 1File: Form 1 ab 300625.pdf | 18 Sep 2025 |
| Form 2File: Form 2 ab 300625.pdf | 18 Sep 2025 |
| Form 3File: Form 3 ab 300625.pdf | 18 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Sold Booked Inventory ab.pdf | 18 Sep 2025 |
| OthersFile: Form 2A ab 300625.pdf | 18 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1Q4ab31032025.pdf | 2 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3abQ4.pdf | 2 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From2Q42425ab.pdf | 2 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2Aab31032025.pdf | 2 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2-31-12-2022 (2).pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2-30-9-2022 (1).pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2-1-4-2023.pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2-31-12-2022 (1).pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2-30-9-2022.pdf | 17 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2-31-12-2022.pdf | 17 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2-12-8-2020.pdf | 17 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2-10-7-2024.pdf | 17 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2-annual report.pdf | 17 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2-27-9-2022 -aNNUAL REPORT.pdf | 17 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 2425 ab.pdf | 25 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 2425 ab.pdf | 25 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase 2 Q2 2425.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase 2 Q1 2425 AB WING .pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase 2 Q2 AB WING 2425.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase 2 Q3 AB WING 2425.pdf | 25 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 2425 ab.pdf | 22 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 2324 ab.pdf | 22 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 2425 ab.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 2 Q3 2425 AB WING.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 2 Q2 2425 AB WING.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 2 Q1 2425 AB WING.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 Phase-2 Q3 ab_compressed.pdf | 6 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3q22324ab_compressed.pdf | 6 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3q12324ab.pdf | 6 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5pratikgrandab.pdf | 6 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - A And B Wing.pdf | 2 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA_Rahul Rathi_Phase I -A-B_31032023.pdf | 27 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 2.pdf | 27 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 2.pdf | 31 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICAT_11zon.pdf | 28 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE PHASE 2.pdf | 28 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-09-2022.pdf | 15 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase 2.pdf | 15 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Kanank Developers A and B.pdf | 15 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Kanak Developers.pdf | 27 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate.pdf | 26 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA_Rahul Rathi_Phase II.pdf | 26 Jul 2022 |
| Proforma of Allotment letterFile: Agreement to Sale Format 1.pdf | 25 Jan 2022 |
| Layout approvalFile: Copy of Layout.pdf | 19 Aug 2020 |
| Building plan approvalFile: Approved Plan -1.pdf | 19 Aug 2020 |
| Building plan approvalFile: Approved Plan -2.pdf | 19 Aug 2020 |
| Building plan approvalFile: 3.pdf | 19 Aug 2020 |
| Building plan approvalFile: Approved Plan -4.pdf | 19 Aug 2020 |
| Building plan approvalFile: Approved Plan -5.pdf | 19 Aug 2020 |
| Building plan approvalFile: Approved Plan -6.pdf | 19 Aug 2020 |
| Building plan approvalFile: Approved Plan -7.pdf | 19 Aug 2020 |
| Building plan approvalFile: Approved Plan-8.pdf | 19 Aug 2020 |
| Copy of Layout Approval (in case of layout)File: Copy of Layout.pdf | 19 Aug 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan -1.pdf | 19 Aug 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan -2.pdf | 19 Aug 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 19 Aug 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan -4.pdf | 19 Aug 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan -5.pdf | 19 Aug 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan -6.pdf | 19 Aug 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan -7.pdf | 19 Aug 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan-8.pdf | 19 Aug 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3.pdf | 19 Aug 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 89 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ISHWAR PRATIK GRAND A AND B WING on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NASHIK4,100+ in Nashik
Filed coordinates, straight-line distance. 71 registered projects within 2 km.
Anandvan Housing Complex
Ravi Mahajan Buildcon LLP
SHREEJI INFINIA
SHREEJI LIFE SPACE
Waterways
Sanklecha Construction Private Limited
Shreejis Gujral Arcade
SHREEJI LIFE SPACE
VRAJ METROPOLIS SOUTH
SHREE INFRA SPACE
ALEEF BREEZE APARTMENT
KHATIB BUILDERS AND DEVELOPERS
See every Nashik project, with the district possession charts
Builder: KANAK DEVELOPERS
KANAK DEVELOPERS has 4 registrations on MahaRERA, including ISHWAR PRATIK GRAND OJAS and ISHWAR PRATIK GRAND A AND B WING. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What does it mean that ISHWAR PRATIK GRAND A AND B WING shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ISHWAR PRATIK GRAND A AND B WING is delayed beyond 15 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ISHWAR PRATIK GRAND A AND B WING?
The registered promoter entity is KANAK DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ISHWAR PRATIK GRAND A AND B WING?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ISHWAR PRATIK GRAND A AND B WING?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ISHWAR PRATIK GRAND A AND B WING?
The professionals named in the filing: Architect: SUMIT KUMATH; Engineer: MILIND RATHI; Chartered Accountant: PRITAM BAGMAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ISHWAR PRATIK GRAND A AND B WING?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback