Home / Browse projects / Thane, Maharashtra / ISHWAR BLISS

Completed No litigation declared Residential / Group Housing project

ISHWAR BLISS

By ISHWAR REALITY

RG-MH-29603 · RERA P51700028638 · Last updated on MahaRERA portal: 2 Dec 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 23 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
May 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

ISHWAR BLISS is a Residential / Group Housing project by ISHWAR REALITY in Thane, Maharashtra, registered with MahaRERA as P51700028638 on 25 Mar 2021. The registration is recorded completed; possession was promised by 31 May 2025. The completion date has moved by 23 months from the original filing.

At a glance

Project

  • NameISHWAR BLISS
  • TypeResidential / Group Housing
  • Location
    • KANSAI SECTION
    • AMBARNATH
    • Ambarnath(M Cl)
    • Thane
    • 421501
  • Pincode421501
  • RERA no.P51700028638
  • ReraGenie IDRG-MH-29603

Builder

  • NameISHWAR REALITY
  • Entity typePartnership
  • PartnerJAGDISH RAMA BANJAN
  • Other registrations8 more →
  • Completed5 of 9
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

this monthRegisteredMar 2021First promiseJun 2023Revised toMay 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Mar 2021
  • Promised completion31 May 2025
  • Revised completionRevised to 31 May 2025 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ISHWAR BLISSNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

ISHWAR BLISS: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 2 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Open Space10

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area559 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
MRS POURNIMA M JOSHIAmbarnath(M Cl)Thane
PADMA M SHASTRYAmbarnath(M Cl)Thane
PRASHANT M SHASTRYAmbarnath(M Cl)Thane

Approvals and building plan

Permissible FSI1778.72
Proposed, not sanctioned1,779 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBAHAR B WING 955-970 GANDHI CHOWK BADLAPUR EAST 421503

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAMOD KAMBLE
EngineerPRAMOD KAMBLE
Chartered AccountantAJAY HASSIJA & ASSOCIATES
PartnerRole in project
ISHWAR REALITY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700016859Jun 2023 → May 2024

Reason as filed by the promoterThe COVID-19 pandemic has had a significant impact on our project, leading to shortages of construction materials and equipment. Delays in delivery of building materials, shortage of labour, affected the completion of buildings. Flat sales have also been affected, due to non-sales and uncertain economic conditions, our construction delays have affected building completions.

EXT51700019841Jun 2023 → May 2025

Reason as filed by the promoterThe project is under construction & we have completed more than 85% work on the project. Despite our concerted efforts, we have encountered unforeseen challenges, namely a scarcity of essential construction materials and a shortage of skilled labor. there is a slight delay in finishing activities of the project. Under the above circumstance, we humbly request your honour to kindly grant extension of Project. The revised proposed date of completion as 31/05/2025 for our Project - “ISHWAR BLISS” bearing Registration No. P51700028638

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Dec 2024

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: bliss.pdf2 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: bliss oc.pdf2 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Ishwar Bliss.pdf29 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: signedForm 5 Ishwar Bliss.pdf29 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BLISS ARCHITECT.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bliss Engineer Certificate.pdf22 Jul 2024
Declaration in FORM BFile: FORM B.pdf27 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 24524.pdf27 May 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF INVENTORY.pdf27 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory 240424.pdf24 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30923 CA_compressed.pdf24 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 311223 CA_compressed.pdf24 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 20424 CA_compressed.pdf24 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ishwar Bliss Architect's Certificate.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bliss Engineer's Certificate.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arc certificate bliss.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng certificate bliss.pdf20 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Ishwar bliss form 5.pdf18 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Bliss Q2.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Bliss.pdf17 Oct 2023
Disclosure of sold/ booked inventoryFile: Ishwar Bliss Q2.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf23 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ishwar bliss (4).pdf23 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance.pdf23 Sep 2023
Disclosure of sold/ booked inventoryFile: sold unsold.pdf23 Sep 2023
Declaration in FORM BFile: FORM B.pdf2 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf2 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BLISS 309.pdf7 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Default Folder_78 (2).pdf7 Apr 2023
Disclosure of sold/ booked inventoryFile: SOLD_UNSOLD.pdf7 Apr 2023
Disclosure of sold/ booked inventoryFile: BLISS SOLD UNSOLD.pdf7 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf22 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Ishwar Bliss 20-21.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Ishwar Bliss 21-22_compressed (1).pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ishwar Bliss.pdf16 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: BLISS SOLD UNSOLD FLAT.pdf7 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf30 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engg Quality Insurance certificate.pdf30 Apr 2022
Disclosure of sold/ booked inventoryFile: disclosure Sold Inventory.pdf30 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_bliss.pdf31 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Quality Certificate _SC_bliss.pdf31 Dec 2021
Disclosure of sold/ booked inventoryFile: Sold Inventory _Bliss.pdf31 Dec 2021
Building plan approvalFile: PLAN REVISED 1.pdf7 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN REVISED 1.pdf7 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: ISHWAR BLISS CC 26072021 (1).pdf7 Aug 2021
Declaration about Commencement CertificateFile: DELECRATION CERTIFICATE.pdf7 Aug 2021
Disclosure of sold/ booked inventoryFile: SOLD STATMENT.pdf7 Aug 2021
Copy of the legal title reportFile: Title.pdf16 Mar 2021
Layout approvalFile: Plot plan.pdf9 Mar 2021
Building plan approvalFile: Plot plan.pdf9 Mar 2021
PAN CardFile: pan card.pdf9 Mar 2021
Details of encumbrancesFile: Encumberance Certificate.pdf9 Mar 2021
Copy of Layout Approval (in case of layout)File: Plot plan.pdf9 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Plot plan.pdf9 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: CC COPY.pdf9 Mar 2021
Declaration in FORM BFile: Pramoter form B.pdf9 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certifcate.pdf9 Mar 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf9 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ishwar Bliss RERA CA CERTIFICATE.pdf9 Mar 2021
Proforma of Allotment letterFile: format-agreement_for_sale-shastri-ishwar.pdf9 Mar 2021

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 23 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ISHWAR BLISS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMBARNATH7,600+ in Thane

Builder: ISHWAR REALITY

ISHWAR REALITY has 9 registrations on MahaRERA, including ISHWAR BLISS and ISHWAR SHUBHLAXMI. Its filings disclose 8 earlier MahaRERA projects: declares 3 of 5 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ISHWAR BLISS is delayed beyond 31 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ISHWAR BLISS?

The registered promoter entity is ISHWAR REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ISHWAR BLISS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ISHWAR BLISS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ISHWAR BLISS?

The professionals named in the filing: Architect: PRAMOD KAMBLE; Engineer: PRAMOD KAMBLE; Chartered Accountant: AJAY HASSIJA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ISHWAR BLISS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ISHWAR BLISS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ISHWAR BLISS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.