Completed No litigation declared Residential / Group Housing project

Intelligentia Infinity by Haware Properties

By Haware Housing

RG-MH-27939 · RERA P51900025015 · Last updated on MahaRERA portal: 20 May 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
44 of 44Construction stages doneacross 4 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

Intelligentia Infinity by Haware Properties is a Residential / Group Housing project by Haware Housing in Mumbai City, Maharashtra, registered with MahaRERA as P51900025015 on 18 Mar 2020. The registration is recorded completed; possession was promised by 30 Dec 2025.

At a glance

Project

  • NameIntelligentia Infinity by Haware Properties
  • TypeResidential / Group Housing
  • Location
    • Road no 12
    • Chembur West
    • Tilak Nagar
    • Mumbai
    • Behind Shoppers Stop near Chembur Ghatkopar
    • Mumbai City
    • 400089
  • Pincode400089
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900025015
  • ReraGenie IDRG-MH-27939

Builder

  • NameHaware Housing
  • Entity typePartnership
  • PartnersAmit Suresh Haware, Suresh Kashinath Haware
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredMar 2020PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Mar 2020
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings4 building records
  • Documents filed24 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing A - 1st to 4th FloorNA50000
Wing A - Ground and 5th to 19th FloorNA200000
Wing B - 1st to 4th FloorNA50000
Wing B - Ground and 5th to 19th FloorNA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 20 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

44 of 44 construction stages are filed complete across 4 buildings.

Wing A - 1st to 4th Floor100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing A - Ground and 5th to 19th Floor100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B - 1st to 4th Floor100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B - Ground and 5th to 19th Floor100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 20 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
GymnasiumYes0%

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Closed/Covered33
BuildingClosed/CoveredTotal
Wing A - 1st to 4th Floor44
Wing A - Ground and 5th to 19th Floor1111
Wing B - 1st to 4th Floor44
Wing B - Ground and 5th to 19th Floor1414

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,154 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5572.0
Proposed, not sanctioned4,059 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHdfc Annexe, Plot No 82 sector 17, Vashi Navi Mumbai

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Haware Housing-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Feb 2025

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Intelligentia Infinity By Haware Properties- Feb 25 SIGNED.pdf20 May 2025
Other - FinanceFile: FORM_4_NDR_30.pdf17 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 12079_OCC_Signed.pdf5 Feb 2025
Details of encumbrancesFile: NDR 30 Details of Encumbrances Sep2021.pdf22 Sep 2021
Layout approvalFile: NDR 30 Layout_compressed.pdf26 Aug 2021
Copy of the legal title reportFile: NDR 30 Title Certificate-Updated_compressed.pdf26 Aug 2021
Copy of Layout Approval (in case of layout)File: NDR 30 Layout_compressed.pdf26 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Amended CC up to 17 floors.pdf26 Aug 2021
Proforma of Allotment letterFile: Draft Agreement Aug 2021.pdf26 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: NDR 30 CC Gplus4 19-Jan-2021.pdf3 Jun 2021
Building plan approvalFile: Intelligentia Infinity Approved Plan 1_compressed.pdf8 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: Intelligentia Infinity Approved Plan 1_compressed.pdf8 Apr 2021
PAN CardFile: Haware Housing Pan Card.pdf12 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Intelligentia Infinity CC.pdf12 Mar 2020
Proforma of Allotment letterFile: Draft Agreement for Sale 2020-02-19.pdf12 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Intelligentia Infinity Certificate_compressed.pdf29 Feb 2020
Layout approvalFile: NDR 30 Plan 1 compressed.pdf28 Feb 2020
Building plan approvalFile: NDR 30 Plan 1 compressed.pdf28 Feb 2020
Copy of the legal title reportFile: NDR 30 Title Certificate_compressed.pdf28 Feb 2020
Details of encumbrancesFile: Intelligentia Infinity Encumbrances.pdf28 Feb 2020
Copy of Layout Approval (in case of layout)File: NDR 30 Plan 1 compressed.pdf28 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: NDR 30 Plan 1 compressed.pdf28 Feb 2020
Declaration in FORM BFile: Intelligentia Infinity Form B.pdf28 Feb 2020
Proforma of Allotment letterFile: Intelligentia Infinity Allotment Letter RERA.pdf28 Feb 2020

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one has not
25%of Mumbai City registrations have lapsed or been cancelledthis one is completed

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Intelligentia Infinity by Haware Properties on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Behind Shoppers Stop near Chembur Ghatkopar780+ in Mumbai City

2 kmIntelligentia Infinity bCompleted 16Lapsed / revoked 43Other 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 86 registered projects within 2 km.

Builder: Haware Housing

Haware Housing has 3 registrations on MahaRERA, including Intelligentia Spectrum Thane by Haware Properties and Intelligentia Vector by Haware Properties. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if Intelligentia Infinity by Haware Properties is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Intelligentia Infinity by Haware Properties?

The registered promoter entity is Haware Housing, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Intelligentia Infinity by Haware Properties?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Intelligentia Infinity by Haware Properties?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Intelligentia Infinity by Haware Properties?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Intelligentia Infinity by Haware Properties. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Intelligentia Infinity by Haware Properties to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.