Home / Browse projects / Infinity Residences

Registered Litigation declared Residential / Group Housing project

Infinity Residences

By Infinity Associates

RG-MH-30359 · RERA P51900030602 · Last updated on MahaRERA portal: 17 Apr 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 1 complaint at MahaRERA

Clear

  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2028Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 71%
1Complaints at MahaRERAon this registration
Jump to the 176 documents Report an error

Infinity Residences is a Residential / Group Housing project by Infinity Associates in Kala Chowky, 400033, registered with MahaRERA as P51900030602 on 1 Sep 2021. Possession is promised by 31 Dec 2028. 1 complaint is on record with the regulator.

At a glance

Project

  • NameInfinity Residences
  • TypeResidential / Group Housing
  • Location
    • G D Ambedkar Road
    • Kala Chowky
    • 400033
  • Pincode400033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900030602
  • ReraGenie IDRG-MH-30359

Builder

  • NameInfinity Associates
  • Entity typePartnership
  • PartnersKishor Kantilal Velani, Shrenik Dheerajmal Siroya, Kailash Chandra Sethi, Anand Kumar Thirani
  • Other registrations1 more →

Key dates

this monthRegisteredSep 2021PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Sep 2021
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed176 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Infinity ResidencesNA400000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 71%.

Infinity Residences: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure71%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed73

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots73
Closed/Covered73

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,440 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI60000.0
Proposed, not sanctioned24,831 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPlot No 11 By 4, Sanjona Park, Sindhi So Off, Sion, Mumbai, Maharashtra, 4000071

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Infinity Associates-

Litigation declared2

CaseCourtStatus
1152/2002High Court BombayClosed
3913-3914/2017Supreme Court of IndiaPending

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12502048Infinity AssociatesBharat Kumar23/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed176

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 176 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - Infinity Residence as on March 2026.pdf17 Apr 2026
Form 2File: Form 2 - Infinity Residence as on March 2026.pdf17 Apr 2026
Form 3File: Form 3 - Infinity Residence as on March 2026.pdf17 Apr 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Infinity Residences.pdf17 Apr 2026
Form 1File: Form 1 - Infinity Residences as on Dec 2025.pdf16 Jan 2026
Form 2File: Form 2 - Infinity Residences as on Dec 2025.pdf16 Jan 2026
Form 3File: Form 3 - Infinity Residences as on Dec 2025.pdf16 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Infinity Residences as on Dec 2025.pdf16 Jan 2026
Form 1File: Form 1 - Infinity Residences as on Sep 2025.pdf18 Oct 2025
Form 2File: Form 2 - Infinity Residences as on Sep 2025.pdf18 Oct 2025
Form 3File: Form 3 - Infinity Residences as on Sep 2025.pdf18 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 -Infinity Residences as on Sep 2025.pdf18 Oct 2025
Form 1File: Form 1 - Infinity Residences as on June 2025.pdf20 Jul 2025
Form 2File: Form 2 - Infinity Residences as on June 2025.pdf20 Jul 2025
Form 3File: Form 3 - Infinity Residences as on June 2025.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Infinity Residences as on June 2025.pdf20 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Infinity Residences as on 31-03-2025.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Infinity Residences as on March 2025.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Infinity Residences as on March 2025.pdf11 Apr 2025
Disclosure of sold/ booked inventoryFile: Circular 29 - Infinity Residences as on March 2025.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Infinity Residences as on 31-12-2024.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Infinity Residences as on 31-12-2024.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Infinity Residences as on Dec 2024.pdf6 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Infinity Residences for FY 2023-24.pdf6 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_compressed.pdf12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf12 Nov 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR-29.pdf12 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023-24.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Infinity Residences as on Sep 2024.pdf9 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Infinity Residences for FY 2023-24.pdf9 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Infinity Residences as on 30-09-2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Infinity Residences as on Sept 2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Infinity Residences as on June 2024.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Infinity Residences as on 30-06-2024.pdf17 Jul 2024
Layout approvalFile: 1A.pdf11 Jul 2024
Layout approvalFile: 1B.pdf11 Jul 2024
Building plan approvalFile: 2.pdf11 Jul 2024
Building plan approvalFile: 3.pdf11 Jul 2024
Building plan approvalFile: 4.pdf11 Jul 2024
Building plan approvalFile: 5.pdf11 Jul 2024
Building plan approvalFile: 6.pdf11 Jul 2024
Building plan approvalFile: 7.pdf11 Jul 2024
Building plan approvalFile: 8.pdf11 Jul 2024
Building plan approvalFile: 9.pdf11 Jul 2024
Building plan approvalFile: 10.pdf11 Jul 2024
Building plan approvalFile: 11.pdf11 Jul 2024
Building plan approvalFile: 12.pdf11 Jul 2024
Building plan approvalFile: 13.pdf11 Jul 2024
Building plan approvalFile: 14.pdf11 Jul 2024
Building plan approvalFile: 15.pdf11 Jul 2024
Copy of Layout Approval (in case of layout)File: 1A.pdf11 Jul 2024
Copy of Layout Approval (in case of layout)File: 1B.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 5.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 6.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 7.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 8.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 9.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 10.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 11.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 12.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 13.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 14.pdf11 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 15.pdf11 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Infinity Residences as on June 2024.pdf4 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Infinity Residences for FY 2023-24.pdf4 Jul 2024
Home Buyer /Allottee Grievance Redressal CellFile: Declaration of Establishment of Complaint Redressal Cell - Infinity Associates.pdf27 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Infinity Residences as on March 2024.pdf10 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Infinity Residences as on March 2024.pdf10 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Infinity Residences as on March 2024.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: Information of sold -booked inventory-(Building Wise)_compressed.pdf20 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Infinity Residences as on Dec 2023.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Form 3 - Final Infinity Residences as on 31-12-2023.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Infinity Residences.pdf3 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Infinity Residences 2023.pdf3 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Infinity Residences as on 30-09-2023_compressed.pdf28 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Infinity Residences as on 30-09-2023.pdf20 Oct 2023

Keep Infinity Residences on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kala Chowky

Builder: Infinity Associates

Infinity Associates has 2 registrations on MahaRERA, including Infinity Residences and Legacy Milestone. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What are my rights if Infinity Residences is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Infinity Residences?

The registered promoter entity is Infinity Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Infinity Residences?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Infinity Residences?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Infinity Residences?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Infinity Residences?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Infinity Residences. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Infinity Residences to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.