Home / Browse projects / Aurangabad, Maharashtra / Infinity Homes
Infinity Homes
By Barkatulla Shaukatulla Siddiqui
RG-MH-08452 · RERA P51500020552 · Last updated on MahaRERA portal: 26 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 65 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Infinity Homes is a Residential / Group Housing project by Barkatulla Shaukatulla Siddiqui in Aurangabad, Maharashtra, registered with MahaRERA as P51500020552 on 22 Apr 2019. Possession is promised by 31 Dec 2029. The completion date has moved by 65 months from the original filing. 11 of the 24 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.
At a glance
Project
- NameInfinity Homes
- TypeResidential / Group Housing
- Location
- Gut no 13p
- Padegaon
- Aurangabad (M Corp.)
- Aurangabad
- 431005
- Pincode431005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500020552
- ReraGenie IDRG-MH-08452
Builder
- NameBarkatulla Shaukatulla Siddiqui
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Apr 2019
- Promised completion31 Dec 2029
- Revised completionRevised to 31 Dec 2029 (originally 31 Jul 2024)
- Buildings2 building records
- Documents filed133 files
Current status
Figures as on 26 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Infinity Homes Building A | NA | 2 | 1 | 12 | 0 | 12 |
| Infinity Homes Building B | NA | 2 | 1 | 12 | 0 | 12 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 26 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
Infinity Homes Building A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Infinity Homes Building B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 26 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mrs Anjum Quadri w/o Aziz Ahmed | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Infinity Homes Building A | NA | Rs 1.68 cr | Rs 1.57 cr |
| Infinity Homes Building B | NA | Rs 1.68 cr | Rs 1.57 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AMRISH JOSHI |
| Engineer | JV STRUCTURAL ENGINEERS AND CONSULTANTS |
| Engineer | PLAN WELL CONSULTANT |
| Chartered Accountant | WASIM AMIN BAIG |
| Chartered Accountant | FAIZAN KHAN |
| Partner | Role in project |
|---|---|
| Barkatulla Shaukatulla Siddiqui | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThis Proposed date i.e 31-07-2024 was Declared in 22-04-2019 at the time of registration with MAHARERA, however in late 2019 COVID gripped the Whole Country. W.H.O (World Health Organization) declared COVID Pandemic in March 2020, thereby stopped all activities of Construction activities. W.H.O declared COVID Pandemic is over in May 2023, thereafter the activities including Construction started but with slower pace. Therefore, additional grace period of Completion should be given to the Project till 31-12-2029
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Feb 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Feb 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Feb 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed133
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Infinity 2025-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Infinity 2025-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Infinity 2025-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Infinity 2025-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 2File: Infinity Form 2 2025-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 2File: Infinity Form 2 2025-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 2File: Infinity Form 2 2025-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 2File: Infinity Form 2 2025-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 3File: QPR 4 FORM 3 25-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 3File: QPR 4 FORM 3 25-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 3File: QPR 4 FORM 3 25-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 3File: QPR 4 FORM 3 25-26.pdf | 26 Jun 2026 |
| Form 2A (FY 2025-2026)File: FORM 2-A 2025-26.pdf | 26 Jun 2026 |
| Form 5 (FY 2025-2026)File: Form 5 2025-26.pdf | 26 Jun 2026 |
| Form 1File: QPR 3 FORM 1.pdf | 25 Jun 2026 |
| Form 2File: QPR 3 Form 2 2024-25.pdf | 25 Jun 2026 |
| Form 3File: QPR 3 FORM 3 24-25.pdf | 25 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 3 SOLD 2024-25.pdf | 25 Jun 2026 |
| Form 1File: QPR 4 FORM 1 2024-25.pdf | 25 Jun 2026 |
| Form 2File: QPR 4 Form 2 2024-25.pdf | 25 Jun 2026 |
| Form 3File: QPR 4 FORM 3 24-25.pdf | 25 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 4 SOLD 2024-25.pdf | 25 Jun 2026 |
| Form 2A (FY 2019-2020)File: FORM 2-A 2019-20.pdf | 15 Jan 2026 |
| Form 2A (FY 2020-2021)File: FORM 2-A 2020-21.pdf | 15 Jan 2026 |
| Form 2A (FY 2021-2022)File: FORM 2-A 2021-22.pdf | 15 Jan 2026 |
| Form 2A (FY 2022-2023)File: FORM 2-A 2022-23.pdf | 15 Jan 2026 |
| Form 2A (FY 2023-2024)File: FORM 2-A 2023-24.pdf | 15 Jan 2026 |
| Form 2A (FY 2024-2025)File: FORM 2-A 2024-25.pdf | 15 Jan 2026 |
| Form 1File: QPR 1 FORM 1 2024-25.pdf | 11 Jan 2026 |
| Form 2File: QPR 1 Form 2 2024-25.pdf | 11 Jan 2026 |
| Form 3File: QPR 1 FORM 3 2024-25.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR1 SOLD 2024-25.pdf | 11 Jan 2026 |
| Form 1File: QPR 2 FORM 1 2024-25.pdf | 11 Jan 2026 |
| Form 2File: QPR 2 Form 2 2024-25.pdf | 11 Jan 2026 |
| Form 3File: QPR 2 FORM 3 24-25.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 2 SOLD 24-25.pdf | 11 Jan 2026 |
| Form 1File: QPR 1 FORM 1 2023-24.pdf | 11 Jan 2026 |
| Form 2File: QPR 1 FORM 2 2023-24.pdf | 11 Jan 2026 |
| Form 3File: QPR 1 FORM 3 2023-24.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 1 SOLD Inventory 23-24.pdf | 11 Jan 2026 |
| Form 1File: QPR 2 FORM 1 2023-24.pdf | 11 Jan 2026 |
| Form 2File: QPR 2 FORM 2 2023-24.pdf | 11 Jan 2026 |
| Form 3File: QPR 2 FORM 3 2023-24.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 2 SOLD 23-24.pdf | 11 Jan 2026 |
| Form 1File: QPR 3 FORM 1 2023-24.pdf | 11 Jan 2026 |
| Form 2File: QPR 3 FORM 2 2023-24.pdf | 11 Jan 2026 |
| Form 3File: QPR 3 FORM 3 2023-24.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 3 SOLD 23-24.pdf | 11 Jan 2026 |
| Form 1File: QPR 3 FORM 1 2023-24.pdf | 11 Jan 2026 |
| Form 2File: QPR 3 FORM 2 2023-24.pdf | 11 Jan 2026 |
| Form 3File: QPR 3 FORM 3 2023-24.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 3 SOLD 23-24.pdf | 11 Jan 2026 |
| Form 1File: QPR 1 FORM 1 2022-23.pdf | 8 Jan 2026 |
| Form 2File: QPR 1 FORM 2 2022-23.pdf | 8 Jan 2026 |
| Form 3File: QPR 1 FORM 3 2022-23.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 1 SOLD 22-23.pdf | 8 Jan 2026 |
| Form 1File: QPR 2 FORM 1 2022-23.pdf | 8 Jan 2026 |
| Form 2File: QPR 2 FORM 2 2022-23.pdf | 8 Jan 2026 |
| Form 3File: QPR 2 FORM 3 2022-23.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 2 SOLD 22-23.pdf | 8 Jan 2026 |
| Form 1File: QPR 2 FORM 1 2022-23.pdf | 8 Jan 2026 |
| Form 2File: QPR 2 FORM 2 2022-23.pdf | 8 Jan 2026 |
| Form 3File: QPR 2 FORM 3 2022-23.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 2 SOLD 22-23.pdf | 8 Jan 2026 |
| Form 1File: QPR 4 FORM 1 2022-23.pdf | 8 Jan 2026 |
| Form 2File: QPR 4 FORM 2 2022-23.pdf | 8 Jan 2026 |
| Form 3File: QPR 4 FORM 3 2022-23.pdf | 8 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 4 SOLD 22-23.pdf | 8 Jan 2026 |
| Form 1File: QPR 1 FORM 1 2019-20.pdf | 4 Jan 2026 |
| Form 2File: Form 2 QPR 1 2019-20.pdf | 4 Jan 2026 |
| Form 3File: QPR 1 2019-2020.pdf | 4 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Inventory QPR 1 2019-20.pdf | 4 Jan 2026 |
| Form 1File: QPR 2 FORM 1 2019-20.pdf | 4 Jan 2026 |
| Form 2File: QPR 2 FORM 2 2019-20.pdf | 4 Jan 2026 |
| Form 3File: QPR 2 FORM 3 2019-20.pdf | 4 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 2 SOLD 2019-20.pdf | 4 Jan 2026 |
| Form 1File: QPR 3 FORM 1 2019-20.pdf | 4 Jan 2026 |
| Form 2File: QPR 3 FORM 2 2019-20.pdf | 4 Jan 2026 |
| Form 3File: QPR 3 FORM 3 2019-2020.pdf | 4 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: QPR 3 SOLD 2019-20.pdf | 4 Jan 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 133 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Infinity Homes on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Padegaon1,400+ in Aurangabad
Filed coordinates, straight-line distance. 17 registered projects within 2 km.
One World Phase I
SIMAR PRIDE VENTURES LLP
The Solitairee Phase I
Dizzi Land Farms Private Limited
Neo Orbit
Piyush Infratech Pvt.Ltd.
180 and 51 Greens
A.M.PATEL INFRA PVT LTD
MILLENNIUM BUSINESS CENTER
MILLENNIUMPRO NEST LLP
The Solitairee Phase II
Dizzi Land Farms Private Limited
See every Aurangabad project, with the district possession charts
Builder: Barkatulla Shaukatulla Siddiqui
Barkatulla Shaukatulla Siddiqui has 1 registration on MahaRERA, including Infinity Homes. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if Infinity Homes is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Infinity Homes?
The registered promoter entity is Barkatulla Shaukatulla Siddiqui, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Infinity Homes?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Infinity Homes?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Infinity Homes?
The professionals named in the filing: Architect: AMRISH JOSHI; Engineer: JV STRUCTURAL ENGINEERS AND CONSULTANTS; Engineer: PLAN WELL CONSULTANT; Chartered Accountant: WASIM AMIN BAIG; Chartered Accountant: FAIZAN KHAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Infinity Homes?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback