INDIAN NEWSPAPER SOCIETY - INS
RG-MH-40158 · RERA P51800006763 · Last updated on MahaRERA portal: 14 Jul 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 58 months past the filed date
- 33 complaints at MahaRERA
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
INDIAN NEWSPAPER SOCIETY - INS is a Commercial project by ORBIT ENTERPRISES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006763 on 16 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 24 months from the original filing. 33 complaints are on record with the regulator.
At a glance
Project
- NameINDIAN NEWSPAPER SOCIETY - INS
- TypeCommercial
- Location
- BKC Road
- Bandra Kurla Complex
- Andheri
- Mumbai Suburban
- 400051
- Pincode400051
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800006763
- ReraGenie IDRG-MH-40158
Builder
- NameORBIT ENTERPRISES
- Entity typeOthers
- PartnerRajen Vasant Dhruv
- Named personsBHUTA SECURITIES LIMITED, STARLINK REALTY PRIVATE LIMITED, NAVNIT INFRA PROJECT PRIVATE LIMITED, RAJEN VASANKUMAR DHRUV
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on16 Aug 2017
- Promised completion30 Dec 2021
- Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed43 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| INS A WING | NA | 17 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
INS A WING: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 14 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 99% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed386
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| INDIAN NEWSPAPER SOCIETY | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Y E RAFIK |
| Architect | Raja Aederi Consultants Pvt. Ltd. |
| Engineer | JW Consultants |
| Chartered Accountant | Prakash Patil & Associates |
| Chartered Accountant | Ramesh Vora & Co |
| Partner | Role in project |
|---|---|
| ORBIT ENTERPRISES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project is delayed for reasons beyond our control.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 3373/2017 | BOMBAY HIGH COURT | PENDING |
Complaints filed with MahaRERA33
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000171685 | Samruddha Resources Limited | Orbit Enterprises | 27/11/2019 |
| CC006000000056595 | M/S PRISM CORPORATION | M/S ORBIT ENTERPRISES | 16/10/2018 |
| CC006000000056597 | M/S OFFICE DEPOT | ORBIT ENTERPRISES | 16/10/2018 |
| CC006000000056620 | M/S OFFICE DEPOT | ORBIT ENTERPRISES | 23/10/2018 |
| CC006000000056953 | SURESH HASSANAND VAZIRANI | M/s. Orbit Enterprises | 19/11/2018 |
| CC006000000057197 | Suresh Vazirani | M/s. Orbit Enterprises | 06/12/2018 |
| CC006000000057464 | Suresh Hassanand Vazirani | M/s. Orbit Enterprises | 28/12/2018 |
| CC006000000056760 | Vinar Overseas Pvt. Ltd. | M/s Orbit Enterprises | 29/10/2018 |
| CC006000000057716 | KISHANCHAND K RAMANI | ORBIT ENTERPRISES | 17/01/2019 |
| CC006000000192661 | KISHANCHAND K RAMANI | M/S ORBIT ENTERPRISES | 18/02/2020 |
| CC006000000057769 | Saif Ali Khan Pataudi | ORBIT ENTERPRISES | 01/02/2019 |
| CC006000000078632 | M/S ALLIANCE BUSINESS SOLUTIONS | M/S ORBIT ENTERPRISES | 25/03/2019 |
| CC006000000078980 | ORBIT ENTERPRISES | VINAR OVERSEAS PRIVATE LIMITED | 14/05/2019 |
| CC006000000089592 | GOVINDARAJAN SANKARAN | ORBIT ENTERPRISES | 04/06/2019 |
| CC006000000100423 | MANIRATNA ENTERPRISES | ORBIT ENTERPRISES | 22/08/2019 |
| CC006000000100547 | JAGRUTI GEMS | ORBIT ENTERPRISES | 22/08/2019 |
| CC006000000100556 | DAKSH | ORBIT ENTERPRISES | 22/08/2019 |
| CC006000000100545 | S R GEMS EXPORTS | ORBIT ENTERPRISES | 22/08/2019 |
| CC006000000100551 | RAJEEV BOTHRA | ORBIT ENTERPRISES | 22/08/2019 |
| CC006000000100558 | CHETANKUMAR K SHAH & OTHERS | ORBIT ENTERPRISES | 25/09/2019 |
| CC006000000100602 | SAMKIT DIAMOND EXPORT PVT LTD | ORBIT ENTERPRISES | 22/08/2019 |
| CC006000000141075 | RKB GLOBAL LTD | Orbit Enterprises | 27/09/2019 |
| CC006000000194942 | KUNAL UDAY GANDHI & UDAY SHANTILAL GANDHI | ORBIT ENTERPRISES & INDIAN NEWSPAPER SOCIETY | 19/11/2020 |
| CC006000000251655 | ORBIT ENTERPRISES | Dr. Govindrajan Sankaran | 29/06/2022 |
| CC006000000262052 | ORBIT ENTERPRISES | Transaia Bio-Medicals Ltd | 27/07/2022 |
| CC006000000282111 | ORBIT ENTERPRISES | Transaia Bio-Medicals Ltd | 27/07/2022 |
| CC006000000282113 | ORBIT ENTERPRISES | Transaia Bio-Medicals Ltd | 27/07/2022 |
| CC006000000303223 | ORBIT ENTERPRISES | Saif Ali Khan Pataudi | 03/11/2022 |
| CC006000000272092 | Rajkumar Sharma And Meenakshi Sharma | M/s. Orbit Enterprises | 26/07/2022 |
| CC006000000272095 | Twiga Enterprises LLP | M/s. Orbit Enterprises | 26/07/2022 |
| CC12500211 | Vandit Vaghasia | ORBIT ENTERPRISES | 21/01/2025 |
| CC12501139 | Vandit Vaghasia | ORBIT ENTERPRISES | 05/04/2025 |
| CC12501142 | Vandit Vaghasia | ORBIT ENTERPRISES | 05/04/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 12 Apr 2021
Documents filed43
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: scanned form B 13723.pdf | 14 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 27 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Rehab31122022.pdf | 27 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate sale31122022.pdf | 27 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Rehab31032023.pdf | 27 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate sale31032023.pdf | 27 Jun 2023 |
| Certificates of CA (Form 3)File: CA Certiifcate 31122022 Final.pdf | 27 Jun 2023 |
| Certificates of CA (Form 3)File: CA Certiifcate 31032023 Final.pdf | 27 Jun 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate3112018.pdf | 27 Jun 2023 |
| Certificates of CA (Form 3)File: form 3 09012020 170157.pdf | 27 Jun 2023 |
| Declaration about Commencement CertificateFile: Declaration for CC.pdf | 3 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate.pdf | 3 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engg Certificate - Rehab.pdf | 3 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engg Certificate - Sale.pdf | 3 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - 31032020.pdf | 3 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - 31032021.pdf | 3 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 31032022.pdf | 3 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Sold - Unsold details.pdf | 3 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 - CA Certificate.pdf | 3 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5_ 2017_18.pdf | 3 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_2018_19.pdf | 3 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_2019_20.pdf | 3 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_2021_22.pdf | 3 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_2020_21.pdf | 3 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_2021_22.pdf | 3 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Bank Account.pdf | 3 Jan 2023 |
| OtherFile: Part OC.pdf | 19 Apr 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Scan.pdf | 12 Apr 2021 |
| Layout approvalFile: NO LAYOUT DECLARATION.pdf | 30 Jul 2017 |
| Building plan approvalFile: CC upto 14 floor from MMRDA to INS dt 1.pdf | 30 Jul 2017 |
| PAN CardFile: Pan Card Orbit.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: NO LAYOUT DECLARATION.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: CC upto 14 floor from MMRDA to INS dt 1.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC upto 14 floor from MMRDA to INS dt 1.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: Form B.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Sale Wing.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate- Rehab Wing.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: ca certificate.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Declaration for No Agreement.pdf | 30 Jul 2017 |
| OtherFile: Self Declaration.pdf | 30 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 43 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep INDIAN NEWSPAPER SOCIETY - INS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bandra Kurla Complex6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 234 registered projects within 2 km.
12 PEGASUS
Jayant Enterprises S N Project
Kalpataru Magnus
Kalpataru Properties Pvt. Ltd.
Plotted Development Scheme at Sindhudurhnagari
MAHARASHTRA HOUSING AND AREA DEVELOPMENT A
SAJAY AVENUE 18
Vinca Realtors Private Limited
Sahakar excel Acropolis - I
EXCEL ENTERPRISES REALTY LLP
ADDRESS 51
V LAXMI EKTA DEVELOPERS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: ORBIT ENTERPRISES
ORBIT ENTERPRISES has 1 registration on MahaRERA, including INDIAN NEWSPAPER SOCIETY - INS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that INDIAN NEWSPAPER SOCIETY - INS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if INDIAN NEWSPAPER SOCIETY - INS is delayed beyond 30 Dec 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of INDIAN NEWSPAPER SOCIETY - INS?
The registered promoter entity is ORBIT ENTERPRISES, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in INDIAN NEWSPAPER SOCIETY - INS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against INDIAN NEWSPAPER SOCIETY - INS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for INDIAN NEWSPAPER SOCIETY - INS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at INDIAN NEWSPAPER SOCIETY - INS?
The professionals named in the filing: Architect: Y E RAFIK; Architect: Raja Aederi Consultants Pvt. Ltd.; Engineer: JW Consultants; Chartered Accountant: Prakash Patil & Associates; Chartered Accountant: Ramesh Vora & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in INDIAN NEWSPAPER SOCIETY - INS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback