Home / Browse projects / Pune, Maharashtra / HM ROYAL

Registration lapsed No litigation declared Residential / Group Housing project

HM ROYAL

By ARTI PROPERTIES PRIVATE LIMITED

RG-MH-17129 · RERA P52100028047 · Last updated on MahaRERA portal: 15 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 24 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2024Possession promised24 months past this date
20 of 55Construction stages doneacross 5 buildings; furthest along: Podiums (if any), 92%
1Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

HM ROYAL is a Residential / Group Housing project by ARTI PROPERTIES PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100028047 on 27 Jan 2021. Possession was promised by 30 Oct 2024 and is now 24 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameHM ROYAL
  • TypeResidential / Group Housing
  • Location
    • S NO 18/19
    • OPPOSITE TALAB FACTORY
    • KONDHWA BUDRUK
    • PUNE
    • kondhwa BK
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • RERA no.P52100028047
  • ReraGenie IDRG-MH-17129

Builder

  • NameARTI PROPERTIES PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsDEEPAK MANSUKHLAL KOTHARI, SANJAY KUMAR AGARWAL, KAMLESH NATWARLAL MEHTA

Key dates

24 months past promisethis monthRegisteredJan 2021PromisedOct 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on27 Jan 2021
  • Promised completion30 Oct 2024
  • Revised completionNone
  • Buildings5 building records
  • Documents filed77 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
3BNA150000
3CNA150000
3DNA140000
5ANA140000
5CNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 15 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 92%.

3B79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)92%
Plinth100%
Stilt Floor78%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.52%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
3C79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)92%
Plinth100%
Stilt Floor78%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.52%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
3D79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)92%
Plinth100%
Stilt Floor78%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.52%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
5A79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)92%
Plinth100%
Stilt Floor78%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.52%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
5C79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)92%
Plinth100%
Stilt Floor78%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.52%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities34

As on 15 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes85%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsYes85%
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes95%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes65%
Aggregate area of recreational Open SpaceYes95%
Open ParkingYes10%
GymnasiumYes99%
Jogging Track & Sand PitsYes99%
Landscape GardenYes99%
LibraryYes99%
Multi purpose Hall Community Hall Table Tennis Cards CarromYes98%
Party LawnYes99%
Pool Side Party DeckYes99%
Practise Basketball CourtYes99%
Recreational RoomYes0%
Skating RinkYes99%
Steam & Sauna BathYes99%
Stepped GardenYes99%
Swimming PoolYes99%
Tennis CourtYes99%
Elder park with acupressure pathYes99%
Children ParksYes99%
Billiards roomYes99%
AmphitheatreYes99%
Aerobics, Yoga and MeditationYes99%

Parking filed243

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots243
Closed/Covered228
Open Space15
BuildingClosed/CoveredOpen SpaceTotal
3B91091
3C78078
3D371350
5A18018
5C426

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,734 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14912.5
Proposed, not sanctioned14,912 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch4TH FLOOR SALARPURA WINDSOR, NO 3 ULSOOR ROAD

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARUN GOKHALE
ArchitectA DESIGN STUDIO
EngineerS. N. Joshi Consultants (P) Ltd.
EngineerArun N. Gokhale
EngineerPratik Shashikant Atole
Chartered AccountantB K KOTHARI & ASSOCIATES LLP
PartnerRole in project
ARTI PROPERTIES PRIVATE LIMITED-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12503088Imran Kasam KachhiARTI PROPERTIES PRIVATE LIMITED02/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jan 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jan 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jan 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Apr 2025

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Q3.pdf15 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q3.pdf15 May 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: O C ORIGINAL.pdf7 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 certificate FY 2023-24.pdf11 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_Certificate_APPL_Q1_FY 24-25.pdf6 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_Certificate_APPL_Q2_FY 24-25 final.pdf6 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch cert aug 2024.pdf4 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate up to 30th Sept 2024.pdf4 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate - Up to 30 June 2024.pdf4 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate up to 30th Sept 2024.pdf4 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 CA signed_compressed.pdf21 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate APPL.pdf18 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate_compressed.pdf18 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of alloment_compressed.pdf18 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Certificate From 5 FY 2022-23.pdf15 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality assurance.pdf2 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf19 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf19 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of alloment.pdf19 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_Certificate_Q2_FY 23-24_compressed.pdf19 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_Certificate_APPL_Q3_FY 23-24_compressed.pdf19 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_compressed.pdf2 Nov 2023
Disclosure of sold/ booked inventoryFile: disclosure of flat oct 23.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf31 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate Up to 30 June 23 of H M Royal, Kondhwa.pdf28 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure of alloment of flat.pdf28 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf28 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Q4 FY 2022-23.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate Q4 FY 2022-23.pdf6 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold,Booked Inventory Q4 FY 2022-23.pdf6 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_Certificate.pdf6 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Certificate Form 5 FY 2020-21.pdf4 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Certificate Form 5 FY 2021-22.pdf4 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q3 FY 22-23-COMPRESSED.pdf14 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf13 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate compressed.pdf13 Jan 2023
Disclosure of sold/ booked inventoryFile: disclosure_compressed.pdf13 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of alloment of flat_compressed.pdf5 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Signed_compressed.pdf1 Nov 2022
Details of encumbrances concerned to FinanceFile: No Encumbrance.pdf31 Oct 2022
Details of encumbrances concerned to LegalFile: No Encumbrance.pdf31 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engr cert_merged.pdf31 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate.pdf14 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Rera Letter - Format A.pdf11 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Compressed.pdf4 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate compressed.pdf4 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: APPL - BALANCE SHEET 2018-2019 Final signed.pdf6 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: APPL BS FY 2019-20 Final signed_compressed.pdf6 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: APPL BS FY 2020-21 Final signed.pdf6 May 2022
OtherFile: noc Architect.pdf6 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf5 May 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Flat sold_compressed.pdf26 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_compressed.pdf22 Apr 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate.pdf22 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_Compressed.pdf1 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final engineer certificate.pdf1 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf1 Mar 2022
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT.pdf28 Feb 2022
CERSAI detailsFile: CERSAI Search Report.pdf28 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form - 2A - Compress.pdf22 Jan 2021
Layout approvalFile: 4 Layout.pdf20 Jan 2021
Building plan approvalFile: NA.pdf20 Jan 2021
Copy of the legal title reportFile: 2 Legal Title Report.pdf20 Jan 2021
Details of encumbrancesFile: 3 Encumbrance Certificate.pdf20 Jan 2021
Copy of Layout Approval (in case of layout)File: 4 Layout.pdf20 Jan 2021
Building Plan Approval / NA Order for plotted developmentFile: NA.pdf20 Jan 2021
Commencement Certificates / NA Order for plotted developmentFile: 6 Commencement Certificate.pdf20 Jan 2021
Declaration in FORM BFile: 7 Form - B.pdf20 Jan 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Architect Certificate (Form 1).pdf20 Jan 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 Engineers Certificate (Form 2).pdf20 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf20 Jan 2021
Proforma of Allotment letterFile: 15 Allotment Letter.pdf20 Jan 2021
Proforma of Allotment letterFile: 15 Draft Agreement of sale.pdf20 Jan 2021
OtherFile: Memorandum of Association.pdf20 Jan 2021
OtherFile: 21 Development Agreement - Part1.pdf20 Jan 2021
OtherFile: 21 Development Agreement - Part2.pdf20 Jan 2021
PAN CardFile: 1 PAN.pdf6 Jan 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HM ROYAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KONDHWA BUDRUK, PUNE13,700+ in Pune

Builder: ARTI PROPERTIES PRIVATE LIMITED

ARTI PROPERTIES PRIVATE LIMITED has 1 registration on MahaRERA, including HM ROYAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that HM ROYAL shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HM ROYAL is delayed beyond 30 Oct 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HM ROYAL?

The registered promoter entity is ARTI PROPERTIES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HM ROYAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HM ROYAL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HM ROYAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HM ROYAL?

The professionals named in the filing: Architect: ARUN GOKHALE; Architect: A DESIGN STUDIO; Engineer: S. N. Joshi Consultants (P) Ltd.; Engineer: Arun N. Gokhale; Engineer: Pratik Shashikant Atole; Chartered Accountant: B K KOTHARI & ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HM ROYAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HM ROYAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HM ROYAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.