Red flags

  • Completion date moved by 48 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 102 documents Report an error

Hirkani Co-operative Housing Society is a Residential / Group Housing project by Vraj Kamman Real Estate Developers Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003206 on 5 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2027. The completion date has moved by 48 months from the original filing.

At a glance

Project

  • NameHirkani Co-operative Housing Society
  • TypeResidential / Group Housing
  • Location
    • Pandurang wadi
    • Road no. 3
    • Goregaon east
    • Borivali
    • Mumbai Suburban
    • 400063
  • Pincode400063
  • RERA no.P51800003206
  • ReraGenie IDRG-MH-24803

Builder

  • NameVraj Kamman Real Estate Developers Private Limited
  • Entity typeCompany
  • DirectorJay MORZARIA
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toDec 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion30 Dec 2027
  • Revised completionRevised to 30 Dec 2027 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed102 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Hirkani Co-operative Housing SocietyNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Hirkani Co-operative Housing Society: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities19

As on 26 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
Intercom FacilityYes0%
Wifi FacilityYes0%
CCTV FacilityYes0%
AC Entrance LobbyYes0%

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered14
Open Space6

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area659 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Hirkani Co-operative Housing SocietyBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI1778.56
Proposed, not sanctioned443 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI BANK GOREGAON EAST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNiten Dedhia
Chartered AccountantSanket B Koya
PartnerRole in project
Vraj Kamman Real Estate Developers Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012078Dec 2023 → Dec 2027

Reason as filed by the promoterThis is a Redevelopment of the society. There were issues and differences between members, the society committee, and us. We had not started the project in 2016 nor we have started it till date. The old existing building is still there on the plot but now we have cleared all the differences among‘s Society committee, Society Members, and us. We had registered project because some of the members had purchased the additional area at that time. Old members had purchased the area so we had registered the project at that time cause of the complaints. MahaRERA was registering the project with IOD at

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Apr 2025

Documents filed102

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Hirkani OC Certificate.pdf26 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VKREDPV Form - 1 For Quater 4 .pdf17 Apr 2025
Certificates of CA (Form 3)File: VKREDPV Form - 3 For Quater 4.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VKREDPL Form - 2 For Quater 4 .pdf17 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Hirkani OC Certificate.pdf17 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VKREDPL Form-5 (1).pdf17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VKREDPL Form 1 Q3 Architect Certificate (2).pdf31 Jan 2025
Certificates of CA (Form 3)File: VKREDPL Form 3 Q1 CA Certificate.pdf31 Jan 2025
Certificates of CA (Form 3)File: VKREDPL Form 3 Q2 CA Certificate.pdf31 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: VKREDPL Form 3 Q3 CA Certificate.pdf31 Jan 2025
Building plan approvalFile: hIRKANI APPROVED PLAN.pdf23 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA NEW FORMAT-08 (1).pdf23 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA NEW FORMAT-09 (1).pdf23 Jan 2025
Building Plan Approval (IOD)File: hIRKANI APPROVED PLAN.pdf23 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Scanned Revised Form 3 Hirkani New Format (7).pdf23 Jan 2025
Certificates of CA (Form 3)File: 5 Certificates of CA (Form 3).pdf16 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate of Architect Form 1 qT3.pdf16 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate of Architect Form 1 qTR 4.pdf16 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA NEW FORMAT-07 (2).pdf16 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate of Architect Form 1 qT3.pdf16 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate of Architect Form 1 qTR 4.pdf16 Nov 2024
Certificates of CA (Form 3)File: 5 Certificates of CA (Form 3).pdf16 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA NEW FORMAT-07 (2).pdf16 Nov 2024
Certificates of CA (Form 3)File: Form 3 VKredpl.pdf4 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf29 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Vkredpl Format A.pdf29 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate of Architect - Form 1 (6).pdf13 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA NEW FORMAT.pdf13 Jun 2024
Certificates of CA (Form 3)File: Scanned Revised Form 3 Hirkani New Format_compressed.pdf13 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Certificate - 22-23 (2).pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate of Architect - Form 1 (5).pdf28 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hirkani form 1 (2).pdf26 Feb 2024
Certificates of CA (Form 3)File: scanned Form 3 of VRKEDPL (1).pdf26 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC signed (1).pdf16 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 hIRKANI.pdf16 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Hirkani Jan.pdf16 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Hirkani form 1.pdf30 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Hirkani.pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer certificate Form 2 (Form 2A FY 2021-22).pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 Hirkani.pdf30 Oct 2023
Certificates of CA (Form 3)File: Hirkani CA Certificate Form 3- Qtr 4_compressed (2).pdf30 Oct 2023
PAN CardFile: New Doc 03-01-2023.pdf1 Mar 2023
Details of encumbrances concerned to FinanceFile: Legal encumbrance.pdf1 Mar 2023
Details of encumbrances concerned to LegalFile: Legal encumbrance.pdf1 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other organisation.pdf1 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account seperate details in Format A.pdf1 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation Report Allotment letter.pdf1 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report Agreement for sale.pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE.pdf2 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf2 Feb 2023
Proforma of Agreement for saleFile: Draft Agreement for Sale.pdf2 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: Hirkani CC.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer certificate Form 2 (Form 2A FY 2021-22).pdf1 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual statement of accounts Form 5 (FY 2021-22).pdf1 Feb 2023
CERSAI detailsFile: Hirkani Encumbrance letter.pdf30 Jun 2022
Disclosure of sold/ booked inventoryFile: Disclosure.pdf24 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Hirkani CA Certificate 2018-19.pdf22 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Hirkani CA Certificate 2019-20.pdf22 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Hirkani CA Certificate 2020-21.pdf22 Jun 2022
Declaration about Commencement CertificateFile: vkredpl commencement letter format - D .pdf20 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: vkredpl concern letter .pdf20 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: vkredpl concern letter -0001.pdf20 Jun 2022
OtherFile: Hirkani RERA.pdf21 Jun 2021
Building plan approvalFile: Iod.pdf8 Aug 2020
Building plan approvalFile: IOD PLAN1.pdf8 Aug 2020
Building Plan Approval (IOD)File: Iod.pdf8 Aug 2020
Building Plan Approval (IOD)File: IOD PLAN1.pdf8 Aug 2020
OtherFile: Supplementary deed 2 Pg1to15.pdf9 Sep 2019
OtherFile: Supplementary deed 2 Pg 16to25.pdf9 Sep 2019
OtherFile: Supplementary deed 2 Pg 26 to 35.pdf9 Sep 2019
OtherFile: Supplementary deed 2 Pg 36 to 45.pdf9 Sep 2019
OtherFile: Supplementary deed 2 Pg 46to 55.pdf9 Sep 2019
OtherFile: Supplementary deed 2 Pg 56 to 67.pdf9 Sep 2019
OtherFile: Hirkani Supplymentry deed for rera-min.pdf24 Oct 2018
Certificates of CA (Form 5)File: From 5 Certied.pdf30 Sep 2018
OtherFile: RERA Update letter-20180810162601.pdf10 Aug 2018
OtherFile: Hirkani Rera update-20180612182819.pdf14 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: HIRKANI RERA UPDATE1.pdf6 Apr 2018
OtherFile: RERA Letter.pdf8 Jan 2018
OtherFile: RERA DECLARATION.pdf14 Oct 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
VRAJ GATEWAY-APARNA CHSLP51800051086Borivali West, Mumbai SuburbanMay 2023Certificate SignedDec 2028Jan 1970
Vraj One - Andheri Sheetal Dhara Premises CHSLP51800023492Bhardawadi Road, Mumbai SuburbanDec 2019CompletedDec 2024Jan 1970

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Hirkani Co-operative Housing Society on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Goregaon east6,700+ in Mumbai Suburban

Builder: Vraj Kamman Real Estate Developers Private Limited

Vraj Kamman Real Estate Developers Private Limited has 1 registration on MahaRERA, including Hirkani Co-operative Housing Society. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Hirkani Co-operative Housing Society is delayed beyond 30 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Hirkani Co-operative Housing Society?

The registered promoter entity is Vraj Kamman Real Estate Developers Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Hirkani Co-operative Housing Society?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Hirkani Co-operative Housing Society?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Hirkani Co-operative Housing Society?

The professionals named in the filing: Architect: Niten Dedhia; Chartered Accountant: Sanket B Koya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Hirkani Co-operative Housing Society?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Hirkani Co-operative Housing Society. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Hirkani Co-operative Housing Society to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.