ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / SEJAL SQUARE

Registered Litigation declared Commercial project

SEJAL SQUARE

By ALCHEMI DEVELOPERS PRIVATE LIMITED

RG-MH-18221 · RERA P51800056052 · Last updated on MahaRERA portal: 3 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 8 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Basement (if any), 35%
66 of 296Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 195 documents Report an error

SEJAL SQUARE is a Commercial project by ALCHEMI DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800056052 on 10 May 2024. Possession is promised by 31 Dec 2029. 230 of the 296 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameSEJAL SQUARE
  • TypeCommercial
  • Location
    • Gokuldham General Arunkumar Vaidya Marg
    • Malad (E)
    • Goregaon (E)
    • Malad
    • Borivali
    • Mumbai Suburban
    • 400063
  • Pincode400063
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800056052
  • ReraGenie IDRG-MH-18221

Builder

  • NameALCHEMI DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45309MH2020PTC347521
  • GSTIN27AAUCA1743M1Z5
  • Managing DirectorsHarsh Shantilal Gada, Mayur Shhanttibhai Gada
  • Other registrations3 more →

Key dates

this monthRegisteredMay 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 May 2024
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed195 files

Current status

78%230 of 296 units booked
37.5%Work done, per cost certificate

Figures as on 3 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing D and Wing ENA37270296296

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 35%.

Wing D and Wing E: 12% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)35%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed635

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots635
Closed/Covered635

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,201 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 Sep 2024

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI44301.48
Proposed, not sanctioned44,301 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAndheri Link Road Branch, Morya Estate, Ground Floor, Andheri West, Mumbai - 400053
Estimated costRs 194.17 cr
Cost incurredRs 72.89 cr
Work done37.54%
BuildingWingEstimatedIncurred
Wing D and Wing ENARs 190.29 crRs 72.89 cr
-NARs 3.88 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAB Associates
EngineerAbhijeet Ashok Londhe
Chartered AccountantKSPM & Associates
Chartered AccountantGokhale & Sathe
Chartered AccountantRutuja Narsingh & Associates
PartnerRole in project
ALCHEMI DEVELOPERS PRIVATE LIMITED-

Litigation declared8

CaseCourtStatus
1149/2021City Civil Court MumbaiPending
5243/2022Bombay High CourtOngoing
1285/2022City Civil Court MumbaiOngoing
633/2022Bombay High CourtOngoing
34867/2022Bombay High CourtDisposed off
13068/2023Bombay High CourtOngoing
12911/2023Bombay High CourtOngoing
1149/2021City Civil Court MumbaiOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed195

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 195 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Sejal Square as on June 2026.pdf3 Sep 2026
Withdrawal Update Form 2File: Form 2 - Sejal Square as on June 2026.pdf3 Sep 2026
Withdrawal Update Form 3File: Form 3 - Sejal Square as on June 2026.pdf3 Sep 2026
Withdrawal Update Form 1File: Form 1 - Sejal Square as on June 2026.pdf21 Jul 2026
Withdrawal Update Form 2File: Form 2 - Sejal Square as on June 2026.pdf21 Jul 2026
Withdrawal Update Form 3File: Form 3 - Sejal Square as on June 2026.pdf21 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A FY 2025-26.pdf17 Jul 2026
Form 2A (FY 2024-2025)File: Sejal Square Form 2A- FY 2024-25.PDF26 Jun 2026
Form 5 (FY 2024-2025)File: Sejal Square Form 5- FY 2024-25.pdf8 Jun 2026
Withdrawal Update Form 1File: Form 1- Sejal Square as on March 2026.pdf18 May 2026
Withdrawal Update Form 2File: Form 2 - Sejal Square as on March 2026.pdf18 May 2026
Withdrawal Update Form 3File: Form 3 - Sejal Square as on March 2026.pdf18 May 2026
Form 1File: Form 1 - Sejal Square as on Sep 2025.pdf10 Feb 2026
Form 2File: Form 2 - Sejal Square as on Sep 2025.pdf10 Feb 2026
Form 3File: Form 3 - Sejal Square as on Sep 2025.pdf10 Feb 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Sejal Square as on Sep 2025.pdf10 Feb 2026
Form 1File: Form 1 - Sejal Square as on Dec 2025.pdf10 Feb 2026
Form 2File: Form 2 - Sejal Square as on Dec 2025.pdf10 Feb 2026
Form 3File: Form 3 - Sejal Square as on Dec 2025.pdf10 Feb 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Sejal Square as on Dec 2025.pdf10 Feb 2026
Form 1File: Form 1 - Sejal Square as on June 2025.pdf11 Sep 2025
Form 2File: Form 2 - Sejal Square as on June 2025.pdf11 Sep 2025
Form 3File: Form 3- Sejal Square as on June 2025.pdf11 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Sejal Square as on June 2025.pdf11 Sep 2025
Form 1File: Form 1- Sejal Square as on March 2025.pdf6 Sep 2025
Form 2File: Form 2 - Sejal Square as on March 2025.pdf6 Sep 2025
Form 3File: Form 3 - Sejal Square as on March 2025.pdf6 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Sejal Square as on March 2025.pdf6 Sep 2025
Proforma of Agreement for saleFile: Agreement for sale Sejal Sqaure 22nd May 2025 (2).pdf29 May 2025
Building plan approvalFile: 2.pdf11 Feb 2025
Building plan approvalFile: 3.pdf11 Feb 2025
Building plan approvalFile: 4.pdf11 Feb 2025
Building plan approvalFile: 5.pdf11 Feb 2025
Building plan approvalFile: 6.pdf11 Feb 2025
Building plan approvalFile: 7.pdf11 Feb 2025
Building plan approvalFile: 8.pdf11 Feb 2025
Building plan approvalFile: 9.pdf11 Feb 2025
Building plan approvalFile: 10.pdf11 Feb 2025
Building plan approvalFile: 11.pdf11 Feb 2025
Building plan approvalFile: 12.pdf11 Feb 2025
Building plan approvalFile: 13.pdf11 Feb 2025
Building plan approvalFile: 14.pdf11 Feb 2025
Building plan approvalFile: 15.pdf11 Feb 2025
Building plan approvalFile: 16.pdf11 Feb 2025
Building plan approvalFile: 17.pdf11 Feb 2025
Building plan approvalFile: 18.pdf11 Feb 2025
Building plan approvalFile: 19.pdf11 Feb 2025
Building plan approvalFile: 20.pdf11 Feb 2025
Building plan approvalFile: 21.pdf11 Feb 2025
Building plan approvalFile: 22.pdf11 Feb 2025
Building plan approvalFile: 23.pdf11 Feb 2025
Building plan approvalFile: 24.pdf11 Feb 2025
Building plan approvalFile: 25.pdf11 Feb 2025
Building plan approvalFile: 26.pdf11 Feb 2025
Building plan approvalFile: 27.pdf11 Feb 2025
Building plan approvalFile: 28.pdf11 Feb 2025
Building plan approvalFile: 29.pdf11 Feb 2025
Building plan approvalFile: 30.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 10.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 11.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 12.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 13.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 9.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 14.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 15.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 16.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 17.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 18.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 19.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 20.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 21.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 22.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 23.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 24.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 25.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 26.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 27.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 28.pdf11 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 29.pdf11 Feb 2025

How this compares with Mumbai Suburban

78%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SEJAL SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malad (E), Goregaon (E)6,700+ in Mumbai Suburban

2 kmSEJAL SQUARECompleted 100Lapsed / revoked 62Other 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 265 registered projects within 2 km.

Builder: ALCHEMI DEVELOPERS PRIVATE LIMITED

ALCHEMI DEVELOPERS PRIVATE LIMITED has 4 registrations on MahaRERA, including SEJAL SQUARE and S-CITY-C1. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SEJAL SQUARE is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SEJAL SQUARE?

The registered promoter entity is ALCHEMI DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U45309MH2020PTC347521 and GSTIN 27AAUCA1743M1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SEJAL SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SEJAL SQUARE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SEJAL SQUARE?

The professionals named in the filing: Architect: AB Associates; Engineer: Abhijeet Ashok Londhe; Chartered Accountant: KSPM & Associates; Chartered Accountant: Gokhale & Sathe; Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SEJAL SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SEJAL SQUARE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SEJAL SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.